Paulson v. Wis. Dep't of Natural Res.

2019 WI App 5, 925 N.W.2d 789, 385 Wis. 2d 515
CourtCourt of Appeals of Wisconsin
DecidedDecember 11, 2018
DocketAppeal No. 2018AP696
StatusPublished

This text of 2019 WI App 5 (Paulson v. Wis. Dep't of Natural Res.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paulson v. Wis. Dep't of Natural Res., 2019 WI App 5, 925 N.W.2d 789, 385 Wis. 2d 515 (Wis. Ct. App. 2018).

Opinion

PER CURIAM.

¶1 Troy Paulson, pro se, appeals an order dismissing his lawsuit against the Wisconsin Department of Natural Resources (DNR). We conclude Paulson's lawsuit was properly dismissed because he did not timely seek judicial review of the DNR's decision denying him a permit to discharge fill material onto a wetland under WIS. STAT. ch. 227 (2015-16).1 As a result, the circuit court lacked competency to proceed to judgment on Paulson's complaint. We therefore affirm the order dismissing Paulson's lawsuit, albeit on different grounds than those relied upon by the circuit court.

BACKGROUND

¶2 The following facts are undisputed. Paulson, his wife, and two other individuals own a parcel of wetland property in Polk County, Wisconsin. Paulson wanted to build two detached garages on the property, but in order to do so he needed to fill in approximately 8755 square feet of wetland. In order to place fill in a wetland, a property owner must obtain either a wetland general permit or a wetland individual permit from the DNR. See WIS. STAT. § 281.36(3b)(b).

¶3 On November 4, 2015, Paulson submitted an application to the DNR for a wetland general permit under WIS. STAT. § 281.36(3g). Under that statute, the DNR has thirty days to issue a decision on an individual's permit application. See § 281.36(3g)(h)2. If the DNR does not, within that thirty-day time period, either request additional information or inform the applicant that a wetland individual permit will be required, the discharge "shall be considered to be authorized under the wetland general permit and the applicant may proceed without further notice." Id. An exception to the thirty-day time limit exists, however, when "adverse weather conditions prevent the [DNR] from conducting an accurate on-site inspection" during the thirty-day period. Sec. 281.36(3g)(h)2m. Under those circumstances, the DNR "shall give notice to the person wishing to proceed with the discharge that adverse weather conditions will prevent the [DNR] from complying with the 30-day deadline and shall complete the inspection as soon as weather conditions permit." Id.

¶4 On December 3, 2015-twenty-nine days after Paulson submitted his permit application-the DNR informed Paulson that it would need to perform a site visit the following spring "to evaluate the functions and values of the wetland" during the growing season. The site visit ultimately took place on May 6, 2016. On May 16, 2016-ten days after the site visit-the DNR sent Paulson a letter stating his application was denied because the project did not "meet the alternatives analysis of the general permit."

¶5 In the same letter, the DNR also informed Paulson that the wetland on his property had a navigable connection to a nearby lake, "which makes a portion of this wetland complex lakebed." The DNR therefore explained that, regardless of whether it granted Paulson's application for a wetland general permit, before constructing the proposed garages Paulson would also be required to obtain an "individual permit" under WIS. STAT. § 30.12 allowing him to place structures on a lakebed. However, the DNR stated Paulson's application for an individual permit under § 30.12 would "likely be denied" because granting the permit "would be detrimental to the public's interests."

¶6 Paulson did not file a petition for judicial review of the DNR's May 16, 2016 decision under WIS. STAT. ch. 227, nor did he apply for an individual permit under WIS. STAT. § 30.12. Instead, on April 19, 2017-approximately eleven months after the DNR issued its decision-Paulson commenced the instant lawsuit against the DNR by the filing of a summons and complaint, seeking injunctive relief. Paulson asserted the DNR's denial of his wetland general permit application was invalid because it was not issued within the thirty-day time limit set forth in WIS. STAT. § 281.36(3g)(h)2. Because the DNR had failed to timely act on his application, Paulson argued his proposed discharge of fill material should be "considered to be authorized." Paulson subsequently filed an amended complaint adding an argument that, because his wetland general permit was deemed granted under § 281.36(3g)(h)2., he had necessarily satisfied the permitting requirements in § 30.12(1) for placing structures on a lakebed. His amended complaint requested declaratory and injunctive relief, along with compensatory and punitive damages.

¶7 In its responses to Paulson's complaint and amended complaint, the DNR asserted that its denial of Paulson's wetland general permit application "was issued in compliance with all procedural requirements, was based upon substantial evidence contained in the record, was a correct interpretation and application of the law, and was within the discretion permitted by law." The DNR also argued that, regardless of whether it had properly denied Paulson's wetland general permit application, Paulson could not perform the proposed work until he applied for and obtained an individual permit under WIS. STAT. § 30.12(1). The DNR further argued that Paulson's lawsuit was subject to the judicial review provisions of WIS. STAT. ch. 227. Finally, the DNR reserved its right to raise a sovereign immunity defense.

¶8 The DNR subsequently filed a motion to classify Paulson's lawsuit "as an Administrative Agency Review action subject to the procedures and requirements in WIS. STAT. ch. 227." On the same day, the DNR moved to dismiss Paulson's lawsuit, arguing it was not timely filed within thirty days after the DNR mailed its decision denying his permit application, as required by WIS. STAT. § 227.53(1)(a)2m. Because Paulson did not timely seek judicial review of the DNR's decision, the DNR contended the circuit court "lack[ed] competency to proceed with judgment" on his complaint.

¶9 The circuit court issued an oral ruling on the DNR's motions. The court first rejected the DNR's argument that Paulson's lawsuit should be reclassified as an action for judicial review under WIS. STAT. ch. 227 and should therefore be dismissed as untimely. The court reasoned that the DNR's May 16, 2016 letter denying Paulson's wetland general permit application was not issued within the thirty-day time period set forth in WIS. STAT. § 281.36(3g)(h)2. The court conceded that the DNR's December 3, 2015 letter qualified as an adverse weather notice under § 281.36(3g)(h)2m. and therefore "forestall[ed] the 30-day time period" for issuing a decision. However, the court concluded the time limit began to run again on May 6, 2016-the date of the DNR's site visit. The court therefore ruled that the DNR was required to issue its decision by May 8, 2016, which it did not do. Accordingly, the court concluded the DNR's May 16, 2016 letter denying Paulson's permit application was not a valid agency decision and, as such, was not subject to judicial review under ch. 227.

¶10 The circuit court further concluded that Paulson's application for a wetland general permit should be deemed granted because the DNR did not issue a decision denying Paulson's application within the statutory thirty-day time limit. Nevertheless, the court agreed with the DNR that Paulson's project could not proceed because a separate, individual permit was required under WIS. STAT. § 30.12(1) for Paulson to place structures on a lakebed. The court rejected Paulson's argument that his wetland general permit automatically fulfilled the permitting requirements set forth in § 30.12(1). The court therefore granted the DNR's motion to dismiss Paulson's complaint, and Paulson now appeals.

DISCUSSION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turkow v. Wisconsin Department of Natural Resources
576 N.W.2d 288 (Court of Appeals of Wisconsin, 1998)
Wisconsin Power & Light Co. v. Public Service Commission
2006 WI App 221 (Court of Appeals of Wisconsin, 2006)
Currier v. Wisconsin Department of Revenue
2006 WI App 12 (Court of Appeals of Wisconsin, 2005)
Village of Trempealeau v. Mikrut
2004 WI 79 (Wisconsin Supreme Court, 2004)
State v. Jones (In Re Commitment of Jones)
2018 WI 44 (Wisconsin Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2019 WI App 5, 925 N.W.2d 789, 385 Wis. 2d 515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paulson-v-wis-dept-of-natural-res-wisctapp-2018.