Paulsen Lumber, Inc. v. Meyer

177 N.W.2d 884, 47 Wis. 2d 621, 1970 Wisc. LEXIS 1023
CourtWisconsin Supreme Court
DecidedJune 26, 1970
Docket315
StatusPublished
Cited by4 cases

This text of 177 N.W.2d 884 (Paulsen Lumber, Inc. v. Meyer) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paulsen Lumber, Inc. v. Meyer, 177 N.W.2d 884, 47 Wis. 2d 621, 1970 Wisc. LEXIS 1023 (Wis. 1970).

Opinion

Hanley, J.

Sec. 235.701, Stats. 1961, provides:

“Building loans; trust funds. The proceeds of any such mortgage referred to in ss. 215.22 and 235.70, shall, when paid out by such state savings and loan association or such federal savings and loan association or of any other mortgage from any other source and received by the owner of the premises or by any contractor or subcontractor performing the work and labor forthwith constitute a trust fund in the hands of such owner or contractor or subcontractor for the payment pro rata of all claims due and to become due or owing from such contractor or subcontractor for lienable labor and materials until all such claims have been paid. The use of any of such moneys by any owner, contractor or subcontractor for any other purpose until all claims, except those which are the subject of a bona fide dispute, have been paid in full, or pro rata in cases of a deficiency, shall constitute theft of any moneys so misappropriated. The district attorney of the county where the premises are situated shall on the complaint of any aggrieved party prosecute such owner, contractor or subcontractor *624 misappropriating such moneys for such theft.” (Emphasis supplied.)

The appellant’s basic contention is that under the terms of the statute the only persons protected by the trust provisions are those to whom the contractor is indebted for lienable labor and materials. Since the statute provides that the trust is imposed for payment of claims due “. . . from such contractor or subcontractor . . .” the contractor himself is not the beneficiary of the statutory trust.

The appellant then argues that since he is the “owner” of the improved land, Paulsen Lumber, Inc., is the “contractor” and thus not afforded the benefit of the trust imposed by sec. 285.701, Stats. 1961.

A reading of the statute clearly reveals that the trust is imposed upon funds “. . . for the payment pro rata of all claims due and to become due or owing from such contractor or subcontractor. . . .” (Emphasis supplied.) The statute does not impose a trust upon funds for the payment of claims owed by the owner unless the owner can also be deemed the contractor. The question thus is whether under the facts of this case, Paulsen Lumber, Inc. (hereinafter the respondent) or Lee Homes, Inc., is the “contractor.” If the respondent is the contractor, it is not protected by the trust and its action must be dismissed.

In support of his contention that the respondent is the contractor in the instant case, the appellant refers this court to the definitions contained in sec. 289.01 (1) (a) and (c), Stats. 1961:

“Contractors’ liens. (1) Definition. In this chapter unless the context or subject matter otherwise requires:
“(a) ‘Contractor’ means a person, other than a laborer, who enters into a contract with the owner of land to improve it or who takes over from a contractor his uncompleted contract; and includes an architect, professional engineer and surveyor employed by the owner.
*625 tt
(c) ‘Owner’ means the owner of any interest in land who enters into a contract for the improvement thereof.”

Appellant then argues that since Lee Homes, Inc., is clearly the owner of the real estate which was to be improved and since sec. 289.01 (1) (a) and (c), Stats. 1961, clearly distinguish between “owner” and “contractor,” the respondent (Paulsen Lumber, Inc.) must be considered the “contractor.”

This argument assumes both that the definitions in sec. 289.01 (1) (a) and (c), Stats. 1961, are applicable to sec. 235.701, Stats. 1961, and that an owner (Lee Homes, Inc.) cannot also act as his own “contractor.”

Cases dealing with secs. 289.01 (1) (a) and (c), Stats. 1961, do lend some support to appellant’s proposition that material suppliers, such as respondent, who deal directly with owners are contractors within the meaning of ch. 289, Stats. 1961. These cases include Warnke v. Braasch (1940), 233 Wis. 398, 289 N. W. 598; Fraser Lumber & Mfg. Co. v. Laeyendecker (1943), 243 Wis. 25, 9 N. W. 2d 97; and Duitman v. Liebelt (1962), 17 Wis. 2d 543, 117 N. W. 2d 672.

In Warnke, supra, the plaintiff, who was engaged in the retail sale of building materials, furnished materials directly to the defendant-homeowners who were to improve their home. Under the statutes then in effect a “contractor” had six months from the date on which material was last furnished in which to file a claim for a lien. Subcontractors, materialmen and laborers, however, had only 120 days from the date of furnishing the last labor or materials in which to file their claims for liens. This court held that since the plaintiff’s lien had not been filed for more than eight months from the date on which the last materials were furnished, it was unnecessary to determine whether the plaintiff was a contractor or a materialman. By way of dictum, however, the court then noted that the thirty-day notice provision *626 relating to subcontractors, materialmen and laborers could have no application “. . . to cases where the materials are sold directly to the owner. . . .”

In Fraser, supra, this court was confronted with whether the plaintiff furnished materials to the defendant as a contractor or as a subcontractor. Again the status of the plaintiff (a lumber company) was significant because it was determinative of whether, under then existing statutes, he had timely filed his notice of claim for a lien. Although the plaintiff merely furnished the materials while another firm did the actual construction work, this court, applying the statutory definition of “contractor,” held that the plaintiff was a contractor.

Duitman v. Liebelt, supra, involved a situation wherein one who had contracted for plumbing improvements sold the home to another before the plaintiff had completed work on the plumbing. Since the status of the plaintiff (plumbing company) was determinative of whether a claim for a lien had been timely filed, this court was called upon to determine whether plaintiff was a contractor or subcontractor with regard to the labor and materials furnished the new owner of the house. This court held that when the new owner files his deed with the register of deeds a materialman who is furnishing lienable labor or materials as a principal contractor is given constructive notice of the sale and thus becomes a subcontractor. Appellant apparently is of the position that implicit in this holding is the fact that before becoming a subcontractor the materialman, who was dealing directly with the first owner, was a contractor.

Admittedly, these cases lend some support for the proposition that a materialman who deals directly with the owner of property is a contractor. However, these cases all concern directly or indirectly the definition of “contractor” as contained in ch. 289, Stats. 1961. The words of sec. 289.01, Stats. 1961, which introduce the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pelletier Corp. v. Chas. M. Freidheim Co.
383 N.W.2d 318 (Court of Appeals of Minnesota, 1986)
Vine v. Lotto (In Re Lotto)
21 B.R. 767 (E.D. Wisconsin, 1982)
Wisconsin Gas Co. v. Craig D. Lawrenz & Associates, Inc.
241 N.W.2d 384 (Wisconsin Supreme Court, 1976)
Town of Lafayette v. City of Chippewa Falls
235 N.W.2d 435 (Wisconsin Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
177 N.W.2d 884, 47 Wis. 2d 621, 1970 Wisc. LEXIS 1023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paulsen-lumber-inc-v-meyer-wis-1970.