Paulette Petkovich v. Prime Contractors Co., Inc.

CourtIndiana Court of Appeals
DecidedNovember 20, 2012
Docket64A03-1203-MF-102
StatusUnpublished

This text of Paulette Petkovich v. Prime Contractors Co., Inc. (Paulette Petkovich v. Prime Contractors Co., Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paulette Petkovich v. Prime Contractors Co., Inc., (Ind. Ct. App. 2012).

Opinion

Pursuant to Ind.Appellate Rule 65(D), this Memorandum Decision shall not be FILED regarded as precedent or cited before any Nov 20 2012, 8:49 am court except for the purpose of establishing the defense of res judicata, collateral CLERK of the supreme court, estoppel, or the law of the case. court of appeals and tax court

ATTORNEY FOR APPELLANTS: ATTORNEY FOR APPELLEE:

PATRICK B. McEUEN RICHARD N. SHAPIRO Rhame & Elwood Law Office of Richard N. Shapiro, P.C. Portage, Indiana Schererville, Indiana

IN THE COURT OF APPEALS OF INDIANA

PAULETTE PETKOVICH, ET AL, ) ) Appellants-Defendants, ) ) vs. ) No. 64A03-1203-MF-102 ) PRIME CONTRACTORS CO., INC., ) ) Appellee-Plaintiff. ) )

APPEAL FROM THE PORTER SUPERIOR COURT The Honorable William E. Alexa, Judge Cause No. 64D02-0901-MF-686

November 20, 2012

MEMORANDUM DECISION - NOT FOR PUBLICATION

VAIDIK, Judge Case Summary

Paulette and Nancy Petkovich (collectively “Petkovich”) appeal the trial court’s

decision to foreclose on Prime Contractors Company, Inc.’s (“Prime”) mechanic’s lien on

their home and award attorney’s fees to Prime. Petkovich contends that Prime did not

complete the contract at issue, the trial court erred in setting the priority of the various

liens on the home, and the attorney’s fees awarded to Prime were excessive. Prime

contends that it should also be awarded appellate attorney’s fees for defending this

appeal. We find that Prime did complete the contract and the attorney’s fees awarded to

Prime were not excessive. We also find that Prime is not entitled to appellate attorney’s

fees. However, the trial court did err in setting the priority of the various liens on the

home. We therefore affirm in part, reverse in part, and remand.

Facts and Procedural History

On December 23, 2007, an oak tree was uprooted during an ice and wind storm

and fell on the Petkovich’s Valparaiso home, breaking through the roof. On the advice of

the insurance company, Petkovich contacted a contractor to secure the home and remove

the tree before the insurance adjuster came to the house. Several days later, Petkovich

met with Prime to discuss the cost of repairing the home. Prime estimated the damages

to be $84,773.40 on January 3, 2008, and a few days later, Petkovich signed the proposal

outlining the work to be completed. Plaintiff’s Ex. 1.

On January 20, 2008, before any work began and before receiving an estimate

from the insurance adjuster, Prime increased the proposal by $55,295.00 for damage to

the basement that resulted from a rain storm that took place before the roof was secured.

2 Prime did not start work until after the insurance adjuster, Calvin Coley, visited the house

and estimated the loss to be $153,781.79 in late January 2008. Also in January, Prime

loaned a total of $14,200.00 to Nancy and Paulette individually, an amount that was paid

out of the initial insurance payment of $153,781.79.

After beginning work, Prime increased its proposal again by $13,904.57 on

February 10, 2008. This increase included costs for demolition, moving contents, and

placing the home back in its pre-damaged condition; all of these charges were mentioned

to Coley, but they were not noted in his final estimate. Id. Prime walked off the job site

in early March 2008 before work was completed because Prime contends there was not

enough money to finish the job due to upgrades in repairs requested by Petkovich,

changes in orders, and loans made to Petkovich. Prime contends that it completed

approximately $100,000.00 worth of work when it left the job site, but Coley testified

that he could only account for $51,402.37 in completed work. Tr. p. 225-26.

Prime had Petkovich sign an “extras contract” on March 26, 2008, for $57,765.40

in add-ons that were not covered by the insurance estimate in order to resume work. The

contract stated that “THIS PROPOSAL MUST BE SIGNED IN ORDER TO

CONTINUE JOB SITE.” Plaintiff’s Ex. 6. The contract was signed by both Petkovich

and Prime. After the contract was signed, Prime resumed work only to finish the roof

before walking off the job site for good. Tr. p. 280-81.

Prime recorded a mechanic’s lien in Porter County on April 9, 2008, against

Petkovich’s property in the amount of $75,760.05. This reflected what Prime felt it was

still owed on the project, including payments that Prime made that were not included

3 under the original insurance contract or the extras contract, such as $8500 for appliances,

$2000 for windows, $9500 for kitchen cabinets, over $25,000 for other multiple

upgrades, and $25,000 for change-order requests. Id. at 24-26, 273-74. Nine months

later, Prime filed a complaint to foreclose the mechanic’s lien, naming as defendants

Petkovich and those who had claims, judgments, or liens on the property, as revealed by

the public records of Porter County. Fifteen months later, Prime amended its complaint

to add as a defendant Household Finance Corporation III, the mortgage company with a

lien on the house that was recorded on September 20, 1999. The trial court entered an

Order on Priority in May 2010, listing Prime’s mechanic’s lien third, subordinate only to

a default judgment in favor of Chicago Patrolmens Federal Credit Union and a judgment

in favor of Gerald Lambert; Prime’s mechanic’s lien was not subordinate to the 1999

mortgage. Appellant’s App. p. 42.

A bench trial was held, and three months later, the trial court entered findings and

ordered the mechanic’s lien foreclosed. Judgment was entered in favor of Prime, but not

for the full amount of the mechanic’s lien – instead, judgment was entered for

$31,080.67. The trial court also ordered a sheriff’s sale of the property. Petkovich filed a

motion to correct errors, which was denied. Prime filed an affidavit seeking attorney’s

fees in the amount of $36,489.75, but the trial court awarded Prime only $27,543.75.

Petkovich now appeals.

Discussion and Decision

Petkovich makes four arguments on appeal: (1) the trial court erred in finding that

Prime completed the contract; (2) the trial court erred in foreclosing Prime’s mechanic’s

4 lien; (3) the trial court erred in setting the priority of the various liens on the property;

and (4) the trial court abused its discretion in awarding Prime $27,543.75 in attorney’s

fees. Prime raises one argument: (5) it is entitled to appellate attorney’s fees in defending

this appeal.

I. Mechanic’s Lien

Because the trial court entered findings of fact and conclusions of law, we apply a

two-tiered standard of review. Mueller v. Karns, 873 N.E.2d 652, 657 (Ind. Ct. App.

2007), reh’g denied. We determine first whether the evidence supports the findings and

second whether the findings support the judgment. Id. We will not reverse the trial

court’s findings or the judgment unless clearly erroneous. Ind. Trial Rule 52(A);

Mueller, 873 N.E.2d at 657. A finding is clearly erroneous when the record lacks any

evidence or reasonable inferences from the evidence to support it. Mueller, 873 N.E.2d

at 657. The judgment is clearly erroneous when it is unsupported by the findings and the

conclusions. Id. In conducting this review, we neither reweigh evidence nor judge

witness credibility and consider the evidence in a light that is most favorable to the

judgment. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greyhound Financial Corp. & Terre Haute v. Rlc, Inc.
637 N.E.2d 1325 (Indiana Court of Appeals, 1994)
Bielat v. FOLTA
229 N.E.2d 474 (Indiana Court of Appeals, 1967)
Estate of Mueller v. Karns
873 N.E.2d 652 (Indiana Court of Appeals, 2007)
Harness v. Schmitt
924 N.E.2d 162 (Indiana Court of Appeals, 2010)
Korellis Roofing, Inc. v. Stolman
645 N.E.2d 29 (Indiana Court of Appeals, 1995)
Bergerson v. Bergerson
895 N.E.2d 705 (Indiana Court of Appeals, 2008)
Farah, LLC v. Architura Corp.
952 N.E.2d 328 (Indiana Court of Appeals, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Paulette Petkovich v. Prime Contractors Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/paulette-petkovich-v-prime-contractors-co-inc-indctapp-2012.