Paulding-Putnam Cooperative, Inc. v. Kuhlman

690 N.E.2d 52, 117 Ohio App. 3d 156
CourtOhio Court of Appeals
DecidedJanuary 8, 1997
DocketNo. 12-96-12.
StatusPublished
Cited by7 cases

This text of 690 N.E.2d 52 (Paulding-Putnam Cooperative, Inc. v. Kuhlman) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paulding-Putnam Cooperative, Inc. v. Kuhlman, 690 N.E.2d 52, 117 Ohio App. 3d 156 (Ohio Ct. App. 1997).

Opinions

*158 Hadley, Presiding Judge.

This appeal follows the judgment entry of the Putnam County Court finding against plaintiff-appellant, Paulding-Putnam Cooperative, Inc. (“appellant”), on its complaint and for defendant-appellees, Kevin and Joan Kuhlman (“appellees”), on their consolidated counter-complaint.

In May 1994, appellees hired Rosengarten Construction to install an inground swimming pool in the backyard of appellees’ residence. During the excavation of the pool the contractors struck electrical wires buried in the backyard, severing electrical .service to appellees’ home. Appellant responded to the service request and spliced the electrical wires in two places, restoring electrical service to the home. At the time the repairs were made the contractor informed appellant that the area necessitating repair would be covered with a concrete patio, making future repairs highly impractical. Rosengarten Construction incurred the fee to restore electricity to the home.

In October 1994, appellees suffered a partial electrical outage resulting from an electrical service wire being “faulted.” Appellant again responded to repair the electrical service. . The damaged electrical wire was located under the concrete patio that had been poured by the contractor earlier in the year. Rather than' damage the concrete, appellant suggested moving appellees’ electrical power meter to a more convenient location and running new electrical wires to the meter for service to the residence. This would allow appellant to completely bypass the faulted wire without damage to the concrete.

Appellees hired an electrician to move the power meter at their expense of $1,078.47. Appellant charged appellees an additional $471.43 for repairs to restore electricity to the home. Appellees refused to pay appellant the $471.43, resulting in appellant’s filing a complaint in the Putnam County Court to collect its service fee. After appellant filed its complaint, appellees filed a complaint in the same court to recover the cost they incurred in moving the power meter. The basis of appellant’s complaint was that appellees owed appellant for services performed. Appellees’ complaint was based on the belief that the initial repair performed by appellant was not completed properly, and, thus, appellant should be responsible for the cost incurred to move the power meter.

On May 20, 1996, the matter was consolidated and heard at trial in the Putnam County Court. Appellant was represented by counsel, and appellees were represented pro se. Both parties presented evidence and called witnesses, with one of appellees’ witnesses being Rick Rosengarten of Rosengarten Construction. The trial judge informed the parties that he, in his private practice, represented Rosengarten Construction and had Rosengarten Construction install his swimming pool, and that the company continues to service the pool. The trial judge *159 found that appellant was not entitled to recover on its complaint and that the appellees were entitled to recover on their counter-complaint. This appeal follows with appellant asserting two assignments of error. We will, for purposes of clarity, address appellant’s second assignment of error first.

Assignment, of Error No. 2

“The judgment of the lower court is manifestly against the weight of the evidence, and is not otherwise supported by the evidence.”

“Judgments supported by some competent, credible evidence going to all the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence.” C.E. Morris Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 8 O.O.3d 261, 376 N.E.2d 578, paragraph one of the syllabus. It is “important that in [considering whether the trial court’s judgment is against the manifest weight of the evidence] a court of appeals be guided by a presumption that the findings of the trier-of-fact were indeed correct.” Seasons Coal Co., Inc. v. Cleveland (1984), 10 Ohio St.3d 77, 79-80, 10 OBR 408, 411, 461 N.E.2d 1273, 1276.

Evidence presented by the appellant revealed that the October 1995 partial power outage was the result of one wire being “faulted” into the ground underneath the area where the concrete patio had been poured earlier, in the year. Appellant contends that the wire was not damaged in the same place in October 1995 as it was in May 1995. Appellant argued that the electrical service wire to the residence was exposed in more than one place in May 1995, when the contractor severed the wires. As a result, appellant contends that the contractor must have subsequently damaged the wire before pouring concrete over the area, and corrosion to the wire caused the damage that resulted in the October power failure.

Yet appellee and the contractor testified that the electrical wires where the October power failure occurred may have been exposed at one time but were never exposed after appellant restored the electrical service in May 1995. There was also competent, credible evidence that appellant’s repair personnel did not thoroughly examine the entire route of exposed wire in May, 1995, including the area of wire where the October power failure occurred. Rather, they merely repaired two areas where the electrical service wire was obviously severed before the wire was reburied by the contractors. 1 Appellant had the equipment (i.e., a *160 fault indicator) to detect any type of damage to the wire even if it was not readily observable to the human eye, including nicks in the wire. Yet they did not utilize that equipment until October, 1995, when the wires were buried under concrete. Neither party disputes the fact that the damage to the electrical wires that caused the October partial power outage was the result of an electrical wire being nicked. After the wire was buried moisture was able to come into contact with the metal, corroding the wire to the point that electrical service was eventually lost from that wire. The only dispute between the parties is when the wire was nicked: before or after the appellant’s repair personnel were at the site in May 1995.

We find from the foregoing that there existed competent, credible evidence setting forth that the damage to the electrical wire occurred before appellant’s repair personnel were present at the site in May 1995. Thus, the trial judge correctly stated that “the electric company did not adequately check the remainder of the wire to assure that there was no damage thereto.” Appellant’s second assignment of error is overruled.

Assignment of Error No. 1

“The lower court committed prejudicial error by not disclosing to the parties, and counsel before the trial commenced, that the court had an attorney-client relationship with the appellee’s [sic ] only witness; and that said witness had constructed the court’s swimming pool and services the same.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sassya v. Morgan
2019 Ohio 1301 (Ohio Court of Appeals, 2019)
Henry v. Richardson
951 N.E.2d 1123 (Ohio Court of Appeals, 2011)
State v. Paxton
742 N.E.2d 1171 (Ohio Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
690 N.E.2d 52, 117 Ohio App. 3d 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paulding-putnam-cooperative-inc-v-kuhlman-ohioctapp-1997.