Paul E. Johnson v. The Metropolitan Government Of

CourtCourt of Appeals of Tennessee
DecidedDecember 11, 2002
DocketM2001-00633-COA-R3-CV
StatusPublished

This text of Paul E. Johnson v. The Metropolitan Government Of (Paul E. Johnson v. The Metropolitan Government Of) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paul E. Johnson v. The Metropolitan Government Of, (Tenn. Ct. App. 2002).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE January 9, 2002 Session

PAUL E. JOHNSON v. THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY, TENNESSEE, AND LESTER L. WILLIAMS, JR., DIRECTOR OF THE DEPARTMENT OF WATER AND SEWERAGE SERVICES OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY.

Appeal from the Chancery Court for Davidson County No. 99-1886-II Carol McCoy, Chancellor

No. M2001-00633-COA-R3-CV - Filed December 11, 2002

Paul E. Johnson, a Nashville real estate developer, filed a complaint demanding a refund for sewer access fees paid to the Metropolitan Department of Water and Sewerage Services. A counterclaim was filed by Metro alleging Mr. Johnson executed a valid contract to contribute $1,000,000 toward the construction of the Mill Creek sewer trunk line, less the net amount of any excess access fees paid under a previous agreement. Mr. Johnson denied the existence of a contract to share the cost of extending the trunk sewer link. The trial court dismissed Mr. Johnson’s claims and entered judgment in favor of the Metropolitan Department of Water and Sewerage Services for $688,942.88. Mr. Johnson appealed.

Tenn.R.App.P.3 Appeal as of Right; Judgment of the Chancery Court Affirmed

ASH ,S.J., delivered the opinion of the court, in which Ben H. Cantrell, P.J.,M.S., and Patricia Cottrell J., joined.

Carol D. Kilgore, Nashville, Tennessee, for the appellant, Paul E. Johnson.

Thomas G. Cross, Nashville, Tennessee, for the appellees, The Metropolitan Government of Nashville and Davidson County, Tennessee.

1 OPINION

I. Background

In 1988, Paul E. Johnson (“Johnson”/ “the developer”), a Nashville real estate developer, sought sewer access for a parcel of land that was eventually developed as the Bradford Hills and Holt Woods subdivisions. This property naturally drains into Mill Creek, a tributary of the Cumberland River. The Metropolitan Department of Water and Sewerage Services (“Metro”) informed Johnson the sewer line nearest the property, known as the Whittemore Branch sewer, was nearing capacity. At the time, Metro believed the increased flow from proposed development would encroach upon the limited capacity of the Whittemore Branch natural drainage basin. Harold Delk, Johnson’s engineer and agent for sewer project negotiations, wrote to Metro on August 1, 1988, and agreed for the developer to pay $1,000 per lot in lieu of the present $500 per lot access charge, to help finance any necessary enlargements or extensions of the Whittemore trunk line and construction of a new Mill Creek-Holt Creek trunk sewer.1 Correspondence from Metro Director Buddy Williams to Harold Delk, dated March 17, 1989 clarified the $1,000 access fee proposed by Delk by designating $500 as participation in the construction of the Mill Creek sewer trunk and $500 as the sewer charge authorized by the Metropolitan Council through the Metro Charter. Mr. Delk’s letter in response dated March 22, 1989 accepted the terms of the Whittemore Agreement. Johnson developed Bradford Hills and Holt Woods subdivisions as planned and paid Metro $394, 500 over the succeeding years pursuant to the Whittemore Agreement.

Johnson originally planned to engage a contractor to complete the Mill Creek sewer extension, and Metro would contribute funds for part of the cost. Bids were let for the project but returned exceeding the authorized budget of $1.3 million and the project was not undertaken at that time. Negotiations continued between Metro and Johnson and his agents. On March 2, 1994, Metro wrote Johnson regarding his participation in the Mill Creek trunk sewer. Metro acknowledged they had no objection to capping Johnson’s participation at $1,000,000 toward the cost of the project, less credit for the net amount previously paid for excess capacity fees under the Whittemore Agreement. Mr. Johnson wrote Metro on October 17, 1994 to memorialize the terms of the Mill Creek Agreement in a single document. Johnson modified the outlined formal agreement and signed the letter indicating his acceptance of the terms set forth therein. He also stated he would neither be subject to, nor the beneficiary of, any subsequent basis impact fees or participation by other users of the proposed sewer system, and all construction work on phase one would include plans by Anderson Delk and Associates, Inc. approved by the Water Department on June 14, 1993. The agreement by the parties was subject to construction of the sewer beginning not later than June 1, 1995. The Mill Creek Agreement was also contingent

1 The trial court found H arold Delk was Johnson’s agent for sewer project nego tiations. D elk was prominently involved in negotiations with Metro o n behalf of M r. Johnson for bo th the W hittemo re and Mill Creek Agreements. Johnson and D elk co-authored m uch of the pro ject co rrespondence, which was frequently prepared b y Delk’s secretary and mailed from D elk’s office. 2 upon approval of the Metropolitan Council.2 Metro replied to Johnson’s offer by letter dated December 27, 1994 as written confirmation of acceptance of the developer’s latest modifications. However, Metro cautioned Johnson the project involved complex preliminary review of environmental and archeological issues. Consequently, they could not guarantee construction of the project would begin by June 1, 1995. On June 8, 1995, after the expiration of the June 1, 1995 deadline for beginning construction expired, Johnson voluntarily wrote Metro and offered to extend the date to begin construction until August 15, 1995. When construction had not begun by August 15, 1995, Johnson again wrote to Metro on August 30, 1995, stating, “if the Mill Creek Sewer can not be advertised for bids by September 15, 1995, I will have no choice but to withdraw my offer of one million dollars for the construction of this project.” Metro advertised the project for bids on September 3, 1995. Metro then conducted a pre-bid meeting attended by Johnson’s engineer, Harold Delk. The parties did not have any direct contact with each other after this meeting.

Excavation work began in April of 1996. Johnson observed the construction of the project throughout until its completion approximately three years later. Johnson did not contribute anything to the funding of the Mill Creek extension pursuant to the agreement with Metro and reflected in ordinance number095-1488. Furthermore, the developer demanded a refund of the excess access fees paid under the Whittemore Agreement four months after the Bradford Hills and Holt Woods subdivisions were connected to the sewer. Metro completed the project shortly thereafter and requested Johnson pay the outstanding balance under the Mill Creek Agreement. The developer claimed any obligation he may have had to make such payments terminated August 15, 1995 because construction was delayed. Johnson filed a complaint demanding a refund for the sewer access fees. Metro counterclaimed seeking enforcement of the Mill Creek Agreement as either a unilateral or bilateral contract or under unjust enrichment or promissory estoppel theories. Johnson denied the existence of a contract to share the cost of extending a trunk sewer link and claimed the excess access fees were paid under extortion or duress.

The trial court made the following findings of fact and conclusions of law: First, Johnson’s claim that his obligation terminated on August 15, 1995 ignored the existence of a contract with Metro on that date. Second, an ordinance was passed, and Johnson was not entitled to cancel the contract by his silence. Third, Johnson may have been in a position to cancel the contract had he acted affirmatively. However, Johnson unilaterally and voluntarily demanded bids be let by September 16, 1995, and Metro complied with this demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson v. Tennessee Farmers Mutual Insurance Co.
857 S.W.2d 559 (Court of Appeals of Tennessee, 1993)
City of Lebanon v. Baird
756 S.W.2d 236 (Tennessee Supreme Court, 1988)
Allen v. Elliott Reynolds Motor Co.
230 S.W.2d 418 (Court of Appeals of Tennessee, 1950)
APCO Amusement Co. v. Wilkins Family Restaurants of America, Inc.
673 S.W.2d 523 (Court of Appeals of Tennessee, 1984)
Petway v. Loew's Nashville Knoxville Corporation
117 S.W.2d 975 (Court of Appeals of Tennessee, 1938)
Frierson v. International Agricultural Corp.
148 S.W.2d 27 (Court of Appeals of Tennessee, 1940)
Hutchinson v. Dobson-Bainbridge Realty Co.
217 S.W.2d 6 (Court of Appeals of Tennessee, 1946)
Savage v. Spur Distributing Co.
228 S.W.2d 122 (Court of Appeals of Tennessee, 1949)
Thompson v. Menefee
6 Tenn. App. 118 (Court of Appeals of Tennessee, 1927)
Bradley v. State ex rel. Haggard
438 S.W.2d 738 (Tennessee Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
Paul E. Johnson v. The Metropolitan Government Of, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paul-e-johnson-v-the-metropolitan-government-of-tennctapp-2002.