Patton v. Mutual of Enumclaw Insurance

337 P.3d 874, 266 Or. App. 154, 2014 Ore. App. LEXIS 1405
CourtCourt of Appeals of Oregon
DecidedOctober 8, 2014
Docket031112054; A150143
StatusPublished
Cited by4 cases

This text of 337 P.3d 874 (Patton v. Mutual of Enumclaw Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patton v. Mutual of Enumclaw Insurance, 337 P.3d 874, 266 Or. App. 154, 2014 Ore. App. LEXIS 1405 (Or. Ct. App. 2014).

Opinion

NAKAMOTO, J.

This insurance coverage case comes before us a second time. In the first appeal, Patton v. Mutual of Enumclaw Ins. Co., 238 Or App 101, 242 P3d 624 (2010), rev den, 349 Or 654 (2011) (Patton I), this court reversed a judgment for plaintiff on his breach of contract claim on a homeowners’ insurance policy and remanded for a new trial. On remand, the trial court granted the motion for summary judgment filed by defendant Mutual of Enumclaw Insurance Company (defendant or MOE), ruling that, under the terms of the policy as written, and as interpreted by this court in Patton I, plaintiffs claim was untimely. The trial court then entered a general judgment in defendant’s favor. Plaintiff appeals. We review for errors of law and, for the reasons set forth below, reverse and remand.1

In addition to basic coverage, and coverage for loss of use and damage to personal property, plaintiffs policy included an endorsement for “guaranteed replacement cost” of the house. Patton I, 238 Or App at 103-04. Pursuant to that endorsement, in the event of loss, as an alternative to payment of the basic coverage liability limit, MOE agreed to pay:

“not more than the lesser of:

“1. The replacement cost of that part of the building damaged for like construction and use on the same premises; or
“2. The necessary amount required to repair or replace the damaged building.”

As relevant to this appeal, the policy contains the following additional terms explaining that covered losses were to be settled as follows:

“(4) We will pay no more than the actual cash value of the damage unless:
[157]*157“(a) actual repair or replacement is complete; or
“(b) the cost to repair or replace the damage is both:
“(i) less than 5% of the amount of insurance in this policy on the building; and
“(ii) less than $2,500.
“(5) You may disregard the replacement cost loss settlement provisions and make claim under this policy for loss or damage to buildings on an actual cash value basis. You may then make claim within 180 days after loss for additional liability on a replacement cost basis.”

An additional endorsement, which we refer to as the “no-action” clause, provides that “[n]o action can be brought unless the policy provisions have been complied with and the action is started within two years after the date of loss.”

Plaintiff’s house burned down on November 8, 2001 (thus giving plaintiff, under the terms of the policy, until November 8, 2003, to bring suit against MOE). Patton I, 238 Or App at 105. Plaintiff made a claim under the policy and notified MOE of his intent to invoke the policy’s replacement-cost endorsement. Id. In the ensuing months, plaintiff received several estimates for the cost of replacing his home: one for between $3.6 and $4 million, a second for $3,858 million, and a third — obtained by MOE’s adjuster from Oregon Home Improvement Company (OHI) — for $1,544 million. Id.

Plaintiff did not begin reconstruction at that time because he was initially unable to obtain the required building permit. Id. After plaintiff notified MOE of the problem, plaintiff received several letters from MOE’s attorney, Smith, reminding plaintiff that he could not recover replacement costs until reconstruction was complete and that he only had two years from the date of the fire to bring any action against MOE. Id. at 106-09. Approximately two months before the second anniversary of the fire, plaintiff entered into a construction contract to rebuild the home at a cost over twice the estimate that MOE had obtained from OHI. Id. at 110.

Shortly before the second anniversary of the fire, plaintiff filed a complaint against MOE. Due to continuing [158]*158delays in the permitting process, plaintiff had not yet begun reconstruction. Plaintiff sought a declaration that, under the policy, MOE was obligated to compensate plaintiff for replacement costs incurred more than two years from the date of loss. Plaintiff further alleged that MOE had breached the policy by refusing to pay replacement costs in excess of the amount of OHI’s bid. Id. at 110.

In Patton I, MOE moved for summary judgment on both the breach of contract and declaratory judgment claims. Id. at 117 n 6. With regard to plaintiffs claim for declaratory relief, defendant argued that the policy required completion of construction as a condition for payment of replacement cost benefits and that plaintiff had not yet replaced the home. Id. at 110. Specifically, MOE argued that,

“as a matter of law, the unambiguous terms of the policy did not allow for recovery of replacement costs for work completed more than two years from the date of loss. MOE pointed out that the ‘settlement of loss’ section of the policy requires that, in order to recover damages in excess of ‘actual cash value of the damage,’ the actual repair or replacement must be complete. In MOE’s view, that requirement is a ‘policy provision’ that must be complied with in order to recover replacement costs. MOE asserted that, in light of the two-year limitation on filing suit, and in view of the further requirement that ‘[n]o action can be brought unless the policy provisions have been complied with,’ necessarily, the replacement of a residence must be actually completed within two years of the loss in order to recover replacement costs, and no replacement costs incurred after the two-year limitation may be recovered.”

Id. at 110-11 (footnote omitted). With regard to the breach of contract claim,

“MOE asserted that, in order to have recovered replacement cost benefits over and above those that MOE had previously advanced, plaintiff had only been required to submit sufficient documentation to show that additional costs were necessary and actually spent on reconstruction. Further, MOE contended, although it had advanced plaintiff funds in excess of the actual cash value of the home, i.e., the policy limits for the dwelling, MOE did not have an obligation to do so under the policy and had no obligation to pay further benefits.”

[159]*159Id. at 110. Thus, defendant argued in its first summary judgment motion that plaintiff could not recover any replacement costs for the reconstruction of his home because he had not even begun to construct the new house at the time he commenced the action.

The trial court denied MOE’s summary judgment motion in Patton I, rejecting MOE’s interpretation of the policy and its contention that the only repairs and replacements compensable were those completed within two years of loss:

“The court noted the policy’s requirement that suit could not be brought until ‘the policy provisions have been complied with,’ and agreed that completion of construction was a condition for recovery of replacement costs, but disagreed with MOE’s view that the policy required completion of construction within two years of the loss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Patton v. Mut. of Enumclaw Ins. Co.
438 P.3d 441 (Court of Appeals of Oregon, 2019)
State v. Weikert
929 P.2d 1070 (Court of Appeals of Oregon, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
337 P.3d 874, 266 Or. App. 154, 2014 Ore. App. LEXIS 1405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patton-v-mutual-of-enumclaw-insurance-orctapp-2014.