Patterson v. New River & Pocahontas Consolidated Coal Co.

104 S.E. 491, 87 W. Va. 177, 1920 W. Va. LEXIS 205
CourtWest Virginia Supreme Court
DecidedOctober 12, 1920
StatusPublished
Cited by3 cases

This text of 104 S.E. 491 (Patterson v. New River & Pocahontas Consolidated Coal Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patterson v. New River & Pocahontas Consolidated Coal Co., 104 S.E. 491, 87 W. Va. 177, 1920 W. Va. LEXIS 205 (W. Va. 1920).

Opinion

Rm, Judge:

' ’This action of assumpsit was instituted for the purpose of recovering for the use of certain machinery belonging to the plaintiff’s decedent, which it is contended was used in the de•fendant’s business by a contractor which it had employed to do certain work for it. A trial in the circuit court of McDowell county resulted in a verdict and judgment in favor of the plaintiff, to review which this writ of error is prosecuted.

It appears that on the 30th of July, 1912, the defendant entered into a contract with one W. H. Hyde by which the said Hyde- agreed to sink and construct two shafts, including concrete lining, as well as certain other work in connection therewith, at Weirwood, in Payette county, for certain prices therein named, the said Hyde to furnish all labor, material, tools and equipment for the doing of said work. The specifications, which were made a part of the contract, provided -that the work to be done included all concrete masonry around the top of the shafts, all excavating timbering, concrete lining, placing of guides, water rings, building stairway, and such other work as may be directly or indirectly connected with the sinking of the said shafts. It is further provided that the plans and specifications are intended to co-operate and to be taken together, so that any work shown on the plans and not mentioned in the specifications, or vice-versa, shall be executed the same as though set forth on the plans or mentioned in the specifications, that is to say, the contractor undertook to do all of the work mentioned either in the specifications or shown on the plans, and not only such work as was shown by both. The contract provided certain, prices for the work to be done, including the price of five dollars per cubic yard for entry [179]*179driving. This item is mentioned for the reason that it covers ' the character of work involved here. The contract further provided that the contractor should complete the work within six months, and the same should be paid for upon monthly estimates, ninety per cent, to be paid to the contractor as the work progressed, and ten per cent, of such estimates to be retained until the work was completed. The contractor entered upon the work in the year 1912, and completed the same in the fall of 1914, consuming two years in the performance of the contract, instead of six months, as provided therein. Ho advantage, however, was taken of this by the defendant. Upon the completion of the work a final estimate was made and settlement had with the contractor. In March, 1913, while the work was in progress, the contractor wrote a letter to the defendant informing it that certain of the machinery, a list thereof being attached to the letter, winch he was using in the performance of said work, belonged to -plaintiff’s decedent; that the coni tractor had the use of the same as long as he was using it in the work at Weirwood. This was the only notice the defendant ever had that plaintiff’s decedent had any interest in the machinery or equipment being used by the contractor. The plaintiff contends that about this time, t-o-wit, in March, 1913, the defendant and the said Hyde changed the arrangement under which said work was being done, and that thereafter the defendant paid the contractor Hyde the full amount of his pay rolls and other bills while doing the work, regardless of whether the estimates for any particular month amounted to as much as the contractor’s expenses or not, and that because of this arrangement the contractor became simply an employe of the defendant here. Plaintiff, therefore, claims that for the use of the machinery after that time the’defendant is liable. He further says that, if the above contention is not tenable, this machinery was used in the performance of work in addition to the work provided to be done by the contract, and that for the use of the same in doing such work for the defendant he is entitled to the reasonable value thereof. There is also a claim made for certain items of personal property which it is claimed wrere appropriated by the defendant. All of these [180]*180were waived, however, except one item which will be hereafter mentioned. The court below found that plaintiffs first contention, to the effect that the contract had been virtually abandoned, and the contractor become simply an employe of the defendant, was not sustained by the proof, but allowed a recovery on the verdict of the jury for the use of the machinery in doing the work, which the jury found was outside of the contract, amounting to more than seven thousand dollars. This action of the court is. assigned as error by the defendant, and the plaintiff assigns as cross error the action of the court in refusing to allow him to recover on the basis of his contention first stated above. The contention of the defendant is that the contract between it and Hyde included all of the work done by Iivde, and that whatever the law may be as to the right of the plaintiff to recover for the use of the machinery, in case it had been unauthomedly used by Hyde, he has no basis for recovery under the showing made here. The basis for the plaintiff’s claim on this account is that in addition to doing the work referred to in the contract Hyde excavated for the defendant a space for a pump house at the base of the shafts, and also drove some lateral entries from the shafts, with a view to the mine development, which plaintiff claims was not within the terms of the contract. As before stated, this work was completed in the fall of 1914, and neither the plaintiff nor his decedent made any claim against the defendant for the use of this machinery until the bringing of this suit four years later, after the death of Hyde, to whom the machinery had been hired. It appears that plaintiff’s decedent was to receive from Hyde for the use of the machinery forty-five per cent, of the profits Hyde made on the work. Presumptively he has received this amount, although he does not say in his evidence whether he has or not. As before stated, the contract provides that the plans .and the specifications are to be taken together, and any work shown either by the specifications or upon the plans is to be done as if the same were shown by both documents. The specifications say nothing about excavating for the pump house, nor do they make any provision for entry driving, except that it is significant that a price of five dollars [181]*181per cubic yard is provided in the specifications fox such work, but the plans, which are introduced in evidence, show the pump house, and show the entries, and the defendant insists that Hyde was as much under obligation to do this work when shown only by the plans as if it had been shown both by the specifications and the plans. Por all of the work that Hyde did he was paid in accordance with the terms of the contract. Por driving these entries, which the plaintiff claims was not within the provisions of the contract, he was paid at the rate provided in tire contract. The parties to this contract construed it themselves, and fixed their obligations to each other under it, and it might he well said that even though the same were ambiguous third parties have no right to place upon it a different construction from that given to it by the parties who made it. But the contract is not ambiguous. Clearly all of the work done by Hyde is provided for by the terms of. the contract. While it is not mentioned in the specifications, this entry work is shown upon the plans, and by the terms of the contract Hyde was under the same obligation to perform it as he would have been had it been shown both by the plans and specifications. It is argued that Hyde did not excavate all of the entries shown on the plans.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schnitzer v. Panhandle Lumber Co.
128 P.2d 501 (Washington Supreme Court, 1942)
Hubbard v. Schofield
125 S.E. 221 (West Virginia Supreme Court, 1924)
State v. Sauls
124 S.E. 670 (West Virginia Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
104 S.E. 491, 87 W. Va. 177, 1920 W. Va. LEXIS 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patterson-v-new-river-pocahontas-consolidated-coal-co-wva-1920.