Patrick Rascher Nichols v. Mitch Reynolds

CourtCourt of Appeals of Wisconsin
DecidedDecember 23, 2020
Docket2020AP000374
StatusUnpublished

This text of Patrick Rascher Nichols v. Mitch Reynolds (Patrick Rascher Nichols v. Mitch Reynolds) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patrick Rascher Nichols v. Mitch Reynolds, (Wis. Ct. App. 2020).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. December 23, 2020 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2020AP374 Cir. Ct. No. 2019SC2102

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

PATRICK RASCHER NICHOLS,

PLAINTIFF-APPELLANT,

V.

MITCH REYNOLDS AND ANNA KRAUSE,

DEFENDANTS-RESPONDENTS.

APPEAL from an order of the circuit court for La Crosse County: RAMONA A. GONZALEZ, Judge. Affirmed.

¶1 BLANCHARD, J.1 Patrick Nichols (the contractor) appeals an order of the circuit court dismissing this small claims action against Mitch

1 This appeal is decided by one judge pursuant to WIS. STAT. § 752.31(2)(a) (2017-18). All references to the Wisconsin Statutes are to the 2017-18 version unless otherwise noted. No. 2020AP374

Reynolds and Anna Krause (the homeowners). The contractor was pro se in both the circuit court and now on appeal; the homeowners were pro se in the circuit court and have not filed a brief on appeal. At the end of a trial, the court dismissed the action on the ground that the contractor failed to show that the homeowners had a legal obligation to pay the contractor the $3,261.50 that he claimed they owed him for labor and materials, over and above the $4,182.50 down payment that they had already made on a total written contract price of $8,365.00. I affirm for the following reasons.2

¶2 In June 2018, the contractor and the homeowners signed a contract, using a form created by the contractor’s painting and restoration business. The homeowners were to pay $8,365.00—half as a down payment and the “remainder upon completion”—and the contractor was to power wash, prepare for painting, and then paint portions of a house and a garage.

¶3 In November 2019, the contractor filed the complaint to initiate this action, giving the following brief statement of facts:

I am owed money for work that was done beyond the scope of contract and was agreed upon both verbally as well as through text message. I was unable to complete the job due to the fact that [the homeowners] refused to sign off on the extra work added which puts them in breach of the contract.

2 As this court explained to the parties in a December 11, 2020 order, I could summarily reverse on procedural grounds, given the failure of the homeowners to file a brief on appeal. But I conclude that judicial interests, including the interest of justice, are not served by summary reversal of the order, because I conclude that the contractor does not demonstrate that the order is defective. In sum, the contractor fails to present coherent, supported arguments on appeal that he was not given a fair hearing by the circuit court or that the court’s decision was defective.

2 No. 2020AP374

¶4 In an amended answer, the homeowners made allegations that included the following. In April 2019, they gave the contractor the down payment called for in the June 2018 contract. Shortly after that, the contractor began work. The contractor and the homeowners engaged in a series of communications in which the contractor said that he needed to be paid various amount more than $8,365.00 for the work, prompting the homeowners to raise questions and seek additional details. In June 2019, after demanding what he identified as a non- negotiable additional $3,098.00—which would bring the total cost to $11,463.00 —the contractor ceased work before the project described in the June 2018 contract was completed. In a counterclaim, the homeowners sought $1,411.50, which they submitted was “the additional amount” that they needed to pay someone else “to finish our house beyond what we would have paid [the contractor] had [the contractor] followed the terms of his contract for the same work.”

¶5 At trial, the contractor took sometimes difficult to follow positions, despite what the record reflects were many patient efforts by the circuit court to assist him by asking pertinent questions using readily understandable language. The contractor’s position can be boiled down to the following. After the parties entered in the June 2018 contract, through a series of text messages and conversations they agreed that, above and beyond the obligations described in the June 2018 contract, the homeowners would pay the contractor $40 an hour for work that ended up totaling 181 hours. This, according to the contractor, obligated the homeowners to pay him $7,240, in addition to $204 for materials, from which the down payment of $4,182.50 should be deducted, for a total remaining indebtedness of $3,261.50. The contractor further contended that the extra work was required because the homeowners wanted him to use a power drill with a wire

3 No. 2020AP374

wheel attachment to strip old paint, which added to the work load, even though the homeowners unreasonably refused to sign a new contract to cover the “add-ons” generated by use of the wire wheel.

¶6 However, when the circuit court asked the contractor whether the parties had an agreement as to how many hours of work he would perform outside the written contract, the contractor acknowledged that they had no agreement on this topic. When the court attempted to get a better understanding of what sort of new agreement between the parties the contractor was attempting to describe, his response was to assert that the homeowners were in “breach of the contract because they wouldn’t sign off on these add-ons that we had done.” This assertion of a breach of contract appeared to confuse the circuit court and that confusion seems understandable. The contractor on multiple occasions failed to explain how it was a “breach” for the homeowners to decline to “sign off” on any work beyond that described in the June 2018 contract or what he claimed should have been the consequence of a breach. However, after much back and forth with the court, the contractor eventually added this much: once the homeowners in his view breached the June 2018 contract by failing to sign off on “add-ons,” he was entitled to $3,261.50 under the doctrine of unjust enrichment.

¶7 I note that recovery for unjust enrichment would be based on the inequity of allowing the homeowners to retain benefits without paying for them, measured by the benefits that the contractor conferred on the homeowners, and on a possibly related note a claim for quantum meruit would be based on an implied contract to pay reasonable compensation for services rendered, which would be measured here by the reasonable value of the contractor’s services. See Ramsey v. Ellis, 168 Wis. 2d 779, 785, 484 N.W.2d 331 (1992) (describing and distinguishing unjust enrichment and quantum meruit). But, naturally, the

4 No. 2020AP374

contractor could not recover for unjust enrichment, or on a claim for quantum meruit, absent an accounting of what benefits he provided that were not paid for or a detailed explanation why the compensation he seeks is reasonable. See id. An additional problem for the contractor is that a claim of unjust enrichment cannot survive if the parties have entered into a contract, see Continental Cas. v. Wisconsin Patients Comp. Fund, 164 Wis. 2d 110, 118, 473 N.W.2d 584 (Ct. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramsey v. Ellis
484 N.W.2d 331 (Wisconsin Supreme Court, 1992)
Continental Casualty Co. v. Wisconsin Patients Compensation Fund
473 N.W.2d 584 (Court of Appeals of Wisconsin, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Patrick Rascher Nichols v. Mitch Reynolds, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patrick-rascher-nichols-v-mitch-reynolds-wisctapp-2020.