Patrick Connelly, Inc. v. Hugh Montague & Son Co.

4 A.2d 779, 17 N.J. Misc. 36, 1939 N.J. Misc. LEXIS 3
Hudson County Circuit Court, N.J.·Decided January 30, 1939·Published

Opinion

Brown, C. O. J.

The defendant city of Bayonne moves to strike the complaint in the above entitled cause on the ground that the Court of Chancery has exclusive jurisdiction to determine the matters alleged in the complaint and that this court is without jurisdiction. In its complaint the plaintiff alleges that on June 29th, 1938, the defendant Hugh Montague & Son Co., Inc., as a general contractor, entered into a contract with the city of Bayonne for the construction of a transit shed at the Bayonne terminal. On June 17th, 1938, the plaintiff, as a subcontractor, entered into a contract with the defendant general contractor for piling work to be furnished under the terms of the contract with the city. The [37] plaintiff alleges it furnished some or the material and performed part of the work and was prevented by the general contractor from finishing the remainder. Damages are claimed for the work done and the losses incurred by the alleged interruption of the work by the general contractor. On Juiy 28th, 1938, the plaintiff served and filed with the city in accordance with the provisions of the Municipal Mechanics’ Lieu law (R. 8. 2:60-180), a notice of lien claim upon the funds held by the city. On August 15th, 1938, the general contractor and the Maryland Casualty Company entered into a bond with the city according to the provisions of R. S. 2:60-186, which bond was approved by the chief law officer and the financial officer of the city with whom it was filed. In the bond was recited the filing of the notice of the plaintiff’s lien claim with the city and the bond contained the following condition:

“How, Therefore, the condition of the above obligation is such that if the said Hugh Montague & Son Co., Inc., shall pay such sum as may be decreed to be due Patrick Connelly, Inc., under said claim, then this obligation shall be void, otherwise to remain in full force and virtue.”

The complaint alleges that after the filing of the bond the city paid to the general contractor the funds upon which the plaintiff had filed a notice of lien claim and that the city “is therefore indebted to the plaintiff in the sum of $5,24.4.71” for which the plaintiff brings its suit. Under R. S. 2 :60-184 of the Municipal Mechanics’ Lien law the lien, when filed in accordance with that law, becomes “an absolute lien to the full value of the labor performed or materials furnished” upon the moneys duo or to grow due under the contract made by the city with the general contractor and in the control of the city. By section 2:60-186, of the same act, it is provided in part: “The funds to which a lien has attached * * * may bo released and paid to the contractor by the financial officer of the public agency upon the filing with such officer of a bond in double the sums of all claims filed under the provisions of this article against the contractor or the funds due or to grow due thereunder, and conditioned for the payment of [38] such sum as may he decreed to be due under such claim.” This section of the Municipal Mechanics’ Lien law plainly releases the moneys to which the lien was attached upon the filing of the bond. It does not discharge the lien. It authorizes the city to release the moneys due or to grow due to the general contractor upon the filing of the bond. The lien continues for procedural as well as all other purposes. The act also provides for the enforcement of the lien and the manner in which it may be discharged. Section 2:60-206 of the act provides in detail how the lien may be discharged and nowhere does the act provide for a discharge of the lien by the filing of a bond under section 2:60-186. It may be discharged by a certificate to that effect from the claimant; by lapse of time unless further time is allowed by an order of the Court of Chancery; by satisfaction of a decree in an action to enforce the lien or claim or by final decree of the Court of Chancery in an action to enforce the lien. The law courts are not mentioned in the Municipal Mechanics’ Lien act as a forum through which a discharge of the lien may be effected. The Court of Chancery is specifically granted jurisdiction by the act to discharge both the ‘lien” or “claim” and the act evidently contemplates the-distinction as it refers to both lien and claim. The plaintiff’s lien claim is allowed because of the statute. ' Such suits as the statute contemplates are unknown to the common law. Likewise the'remedy, if it exists, must be found within the provisions of the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Patrick Connelly, Inc. v. Hugh Montague & Son Co., 4 A.2d 779, 17 N.J. Misc. 36, 1939 N.J. Misc. LEXIS 3 (N.J. Ct. App. 1939).

4 A.2d 779 (Patrick Connelly, Inc. v. Hugh Montague & Son Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Heller v. City of Plainfield
194 A. 260 (Supreme Court of New Jersey, 1937)
Harley v. . Plant
104 N.E. 946 (New York Court of Appeals, 1914)
Philadelphia Saving Fund Society v. Disston
198 A. 212 (Pennsylvania Court of Common Pleas, 1937)
John Agnew Co. v. Board of Education
89 A. 1046 (New Jersey Court of Chancery, 1914)
Mount Pleasant Cemetery Co. v. Erie Railroad
65 A. 192 (Supreme Court of New Jersey, 1906)
Delafield Construction Co. v. Sayre
38 A. 666 (Supreme Court of New Jersey, 1897)