PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE)
Opinion
NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION
DOCKET NO. A-2978-18T1
PATERSON MEDICAL PLAZA, LLC,
Plaintiff-Respondent,
v. LITANA DEVELOPMENT, INC.,
Defendant-Appellant.
Argued telephonically March 25, 20201 – Decided April 13, 2020
Before Judges Fuentes, Mayer and Enright.
On appeal from the Superior Court of New Jersey, Law Division, Passaic County, Docket No. L-4395-16.
Robert Ethan Bennet argued the cause for appellant (Tesser & Cohen, attorneys; Danielle E. Cohen and Robert Ethan Bennett, on the briefs).
1 This matter was argued telephonically in accordance with the Chief Justice Rabner's March 15, 2020 Notice to the Bar.
Mandelbaum Salsburg PC, attorney for respondent (Ryan M. Buehler, on the brief). 2
PER CURIAM Defendant Litana Development, Inc. (Litana) appeals from a February 22, 2019 order denying its motion to confirm an arbitration award and March 1 and March 8, 2019 orders compelling re-arbitration. We reverse the orders compelling re-arbitration and remand the matter to the trial court to confirm the arbitration award and to consider the additional relief requested in Litana's motion to confirm the award.
Plaintiff Paterson Medical Plaza, LLC (PMP) contracted with Litana for construction of a medical facility. Upon completion of the work, Litana claimed PMP failed to pay for all work and services performed pursuant to the parties' written contract and signed change orders.
2 On January 28, 2020, the day before the originally scheduled argument date, counsel for Paterson Medical Plaza, LLC advised that he could not appear because his legal services had been terminated by the client. Counsel requested an adjournment of the January 29, 2020 argument to allow the client to retain new counsel and we adjourned the matter to March 25, 2020. Because Paterson Medical Plaza, LLC is a corporation, Rule 1:21-1(c) requires any appearance in court be "through an attorney authorized to practice law in this State." Despite several inquiries by staff at the Appellate Division Clerk's Office, Paterson Medical Plaza, LLC failed to retain new counsel and therefore we consider the written arguments in the merits brief filed on behalf of Paterson Medical Plaza, LLC.
A-2978-18T1
Litana claimed its last day of work on the project was August 9, 2016. A few days later, PMP terminated the contract with Litana. On October 24, 2016, Litana filed a construction lien claim against PMP's property in the amount of $272,050.
PMP immediately filed an order to show cause and verified complaint seeking to discharge Litana's construction lien. In the verified complaint, PMP claimed Litana's lien amount was "willfully exaggerated." In addition to the lien discharge, PMP sought damages for breach of contract, breach of the implied covenant of good faith and fair dealing, lost profits, and unjust enrichment. Litana filed an answer and counterclaim. In its counterclaim, Litana requested damages based on breach of contract.
The trial court denied PMP's application to discharge the lien. Thereafter, PMP filed a motion to compel arbitration. In a March 13, 2017 order, the judge compelled the parties to arbitrate their disputes and retained jurisdiction to enforce the arbitrator's award. 3 Arbitration hearings were held over a five-day period in 2018. PMP's claim before the arbitrator focused solely on discharging the construction lien. PMP argued the lien amount alleged by Litana was grossly overstated. In
3 The trial court stayed the litigation pending the arbitration.
A-2978-18T1
arbitration, Litana sought in excess of $1 million in damages, plus interest and attorney's fees. Litana arrived at that amount based on the parties' written contract, signed change orders, and its alleged additional costs associated with the project.
The arbitrator heard testimony from the parties' witnesses and reviewed documents provided in support of their claims. Based on the testimony and documents, the arbitrator found Litana's lien claim was not overstated and ordered PMP to pay Litana the sum of $552,202.22.
In his April 17, 2018 single-spaced, seven-page written award, the arbitrator determined Litana's work and services under the base contract and signed change orders totaled $4,682,314.81. 4 The arbitrator rejected some of Litana's claimed $808,202.22 in additional documented expenses and its claimed additional work in the amount of $47,620. He concluded there was no writing memorializing the $47,620 sum and therefore denied Litana's request for payment of that amount. The arbitrator also rejected Litana's claim that it allegedly advanced $420,000 to PMP, finding "little persuasive explanation . . .
4 This amount represents the original contract amount of $4,051,000, plus a December 31, 2013 written change order for $414,314.81, plus an October 6, 2014 written change order for $175,000, plus a September 18, 2015 written change order for $42,000.
A-2978-18T1
as to why payments totaling $420,000 were made by Litana to PMP." The arbitrator concluded the $420,000 sum represented "the return to PMP of unused proceeds of the construction loan." The arbitrator "accept[ed] the testimony and proofs presented by Litana with regard to the balance of the additional documented expenses it claim[ed]," determining the sum of $388,202.22 was sufficiently documented. The arbitrator calculated the total work and services provided by Litana to PMP was valued at $5,070,517.03. 5 The arbitrator denied Litana's request for interest, attorney's fees, and costs, finding the parties had a "good faith dispute[]" and Litana lacked documentation related to some of the work because the parties had a "cooperative and informal relationship."
At the arbitration, PMP did not claim it was owed any money but argued it was entitled to set-off amounts against Litana's claims. The arbitrator rejected certain of PMP's set-off claims based on alleged deficiencies and incomplete work performed by Litana and explained why he rejected those set-off amounts. The arbitrator also denied PMP's claim for lost profits as speculative.
5 The arbitrator arrived at this amount by adding the base contract and change order work, totaling $4,682,314.81, plus the additional work performed by Litana in the amount of $388,202.22.
A-2978-18T1
However, the arbitrator awarded PMP the following credits: $80,000 for stucco work not completed by Litana; $34,000 for elevator repair work; $4750 for the elevator room HVAC; and $4300 for installation of the elevator room floor. The total amount credited to PMP by the arbitrator was $123,050. The arbitrator's credit calculation in favor of PMP far exceeded Litana's suggested credit of $15,000 for the work it did not perform.6 The arbitrator determined PMP paid Litana a total of $4,395,264.81.
Deducting the amount paid by PMP, and crediting PMP for defective work and work not performed by Litana, the arbitrator concluded Litana was owed $552,202.22.7 Dissatisfied with the award, PMP sought a modification from the arbitrator. Based on his review of the post-arbitration submissions, the arbitrator denied PMP's request to modify the award because "[t]here [were] no 'clerical, typographical, technical, or computational errors in the [a]ward.' I see no reason
6 PMP claims the arbitrator's award failed to consider a $15,000 credit. However, the arbitrator credited PMP in an amount nearly ten times the credit amount Litana argued should be applied for incomplete work. 7 The arbitrator's ultimate award reflects his determination that $5,070,517.03 represented the work and services provided by Litana, minus PMP's payment to Litana in the amount of $4,395,264.81, minus the total credit due to PMP in the amount of $123,050.
A-2978-18T1
Free access — add to your briefcase to read the full text and ask questions with AI
PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE) (PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.