PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedApril 13, 2020
DocketA-2978-18T1
StatusUnpublished

This text of PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE) (PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-2978-18T1

PATERSON MEDICAL PLAZA, LLC,

Plaintiff-Respondent,

v.

LITANA DEVELOPMENT, INC.,

Defendant-Appellant. _____________________________

Argued telephonically March 25, 20201 – Decided April 13, 2020

Before Judges Fuentes, Mayer and Enright.

On appeal from the Superior Court of New Jersey, Law Division, Passaic County, Docket No. L-4395-16.

Robert Ethan Bennet argued the cause for appellant (Tesser & Cohen, attorneys; Danielle E. Cohen and Robert Ethan Bennett, on the briefs).

1 This matter was argued telephonically in accordance with the Chief Justice Rabner's March 15, 2020 Notice to the Bar. Mandelbaum Salsburg PC, attorney for respondent (Ryan M. Buehler, on the brief). 2

PER CURIAM

Defendant Litana Development, Inc. (Litana) appeals from a February 22,

2019 order denying its motion to confirm an arbitration award and March 1 and

March 8, 2019 orders compelling re-arbitration. We reverse the orders

compelling re-arbitration and remand the matter to the trial court to confirm the

arbitration award and to consider the additional relief requested in Litana's

motion to confirm the award.

Plaintiff Paterson Medical Plaza, LLC (PMP) contracted with Litana for

construction of a medical facility. Upon completion of the work, Litana claimed

PMP failed to pay for all work and services performed pursuant to the parties'

written contract and signed change orders.

2 On January 28, 2020, the day before the originally scheduled argument date, counsel for Paterson Medical Plaza, LLC advised that he could not appear because his legal services had been terminated by the client. Counsel requested an adjournment of the January 29, 2020 argument to allow the client to retain new counsel and we adjourned the matter to March 25, 2020. Because Paterson Medical Plaza, LLC is a corporation, Rule 1:21-1(c) requires any appearance in court be "through an attorney authorized to practice law in this State." Despite several inquiries by staff at the Appellate Division Clerk's Office, Paterson Medical Plaza, LLC failed to retain new counsel and therefore we consider the written arguments in the merits brief filed on behalf of Paterson Medical Plaza, LLC. A-2978-18T1 2 Litana claimed its last day of work on the project was August 9, 2016. A

few days later, PMP terminated the contract with Litana. On October 24, 2016,

Litana filed a construction lien claim against PMP's property in the amount of

$272,050.

PMP immediately filed an order to show cause and verified complaint

seeking to discharge Litana's construction lien. In the verified complaint, PMP

claimed Litana's lien amount was "willfully exaggerated." In addition to the lien

discharge, PMP sought damages for breach of contract, breach of the implied

covenant of good faith and fair dealing, lost profits, and unjust enrichment.

Litana filed an answer and counterclaim. In its counterclaim, Litana requested

damages based on breach of contract.

The trial court denied PMP's application to discharge the lien. Thereafter,

PMP filed a motion to compel arbitration. In a March 13, 2017 order, the judge

compelled the parties to arbitrate their disputes and retained jurisdiction to

enforce the arbitrator's award. 3

Arbitration hearings were held over a five-day period in 2018. PMP's

claim before the arbitrator focused solely on discharging the construction lien.

PMP argued the lien amount alleged by Litana was grossly overstated. In

3 The trial court stayed the litigation pending the arbitration. A-2978-18T1 3 arbitration, Litana sought in excess of $1 million in damages, plus interest and

attorney's fees. Litana arrived at that amount based on the parties' written

contract, signed change orders, and its alleged additional costs associated with

the project.

The arbitrator heard testimony from the parties' witnesses and reviewed

documents provided in support of their claims. Based on the testimony and

documents, the arbitrator found Litana's lien claim was not overstated and

ordered PMP to pay Litana the sum of $552,202.22.

In his April 17, 2018 single-spaced, seven-page written award, the

arbitrator determined Litana's work and services under the base contract and

signed change orders totaled $4,682,314.81. 4 The arbitrator rejected some of

Litana's claimed $808,202.22 in additional documented expenses and its claimed

additional work in the amount of $47,620. He concluded there was no writing

memorializing the $47,620 sum and therefore denied Litana's request for

payment of that amount. The arbitrator also rejected Litana's claim that it

allegedly advanced $420,000 to PMP, finding "little persuasive explanation . . .

4 This amount represents the original contract amount of $4,051,000, plus a December 31, 2013 written change order for $414,314.81, plus an October 6, 2014 written change order for $175,000, plus a September 18, 2015 written change order for $42,000. A-2978-18T1 4 as to why payments totaling $420,000 were made by Litana to PMP." The

arbitrator concluded the $420,000 sum represented "the return to PMP of unused

proceeds of the construction loan." The arbitrator "accept[ed] the testimony and

proofs presented by Litana with regard to the balance of the additional

documented expenses it claim[ed]," determining the sum of $388,202.22 was

sufficiently documented. The arbitrator calculated the total work and services

provided by Litana to PMP was valued at $5,070,517.03. 5

The arbitrator denied Litana's request for interest, attorney's fees, and

costs, finding the parties had a "good faith dispute[]" and Litana lacked

documentation related to some of the work because the parties had a

"cooperative and informal relationship."

At the arbitration, PMP did not claim it was owed any money but argued

it was entitled to set-off amounts against Litana's claims. The arbitrator rejected

certain of PMP's set-off claims based on alleged deficiencies and incomplete

work performed by Litana and explained why he rejected those set-off amounts.

The arbitrator also denied PMP's claim for lost profits as speculative.

5 The arbitrator arrived at this amount by adding the base contract and change order work, totaling $4,682,314.81, plus the additional work performed by Litana in the amount of $388,202.22.

A-2978-18T1 5 However, the arbitrator awarded PMP the following credits: $80,000 for

stucco work not completed by Litana; $34,000 for elevator repair work; $4750

for the elevator room HVAC; and $4300 for installation of the elevator room

floor. The total amount credited to PMP by the arbitrator was $123,050. The

arbitrator's credit calculation in favor of PMP far exceeded Litana's suggested

credit of $15,000 for the work it did not perform.6 The arbitrator determined

PMP paid Litana a total of $4,395,264.81.

Deducting the amount paid by PMP, and crediting PMP for defective work

and work not performed by Litana, the arbitrator concluded Litana was owed

$552,202.22.7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tretina Printing, Inc. v. Fitzpatrick & Associates, Inc.
640 A.2d 788 (Supreme Court of New Jersey, 1994)
New Jersey Turnpike Authority v. Local 196, I.F.P.T.E.
920 A.2d 88 (Supreme Court of New Jersey, 2007)
Fawzy v. Fawzy
973 A.2d 347 (Supreme Court of New Jersey, 2009)
Korshalla v. Liberty Mutual Insurance Company
381 A.2d 88 (New Jersey Superior Court App Division, 1977)
Barcon Associates, Inc. v. Tri-County Asphalt Corp.
430 A.2d 214 (Supreme Court of New Jersey, 1981)
Manger v. Manger
9 A.3d 1081 (New Jersey Superior Court App Division, 2010)
Augustine W. Badiali v. New Jersey Manufacturers Insurance Group (071931)
107 A.3d 1281 (Supreme Court of New Jersey, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
PATERSON MEDICAL PLAZA, LLC, VS. LITANA DEVELOPMENT, INC. (L-4395-16, PASSAIC COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/paterson-medical-plaza-llc-vs-litana-development-inc-l-4395-16-njsuperctappdiv-2020.