Passov v. Paris Development Corp.

563 N.E.2d 327, 55 Ohio App. 3d 202, 1988 Ohio App. LEXIS 4101
CourtOhio Court of Appeals
DecidedOctober 24, 1988
Docket54414
StatusPublished
Cited by3 cases

This text of 563 N.E.2d 327 (Passov v. Paris Development Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Passov v. Paris Development Corp., 563 N.E.2d 327, 55 Ohio App. 3d 202, 1988 Ohio App. LEXIS 4101 (Ohio Ct. App. 1988).

Opinion

Patton, J.

This appeal is brought by plaintiffs-appellants, Robert S. Passov and his wife, who assign as error the granting of summary judgment rendered in favor of defendant-appel-lee city of Pepper Pike.

In July 1981, defendant Julius Paris 1 submitted a preliminary plan to subdivide certain property in Pepper Pike. The preliminary plan showed sanitary sewers placed in accordance with the applicable law. Pepper Pike City Council passed Ordinance No. 1981-39 approving the final plat on October 21, 1981, subject to the provisions of Pepper Pike Codified Ordinance 1105.04 which required the developer to furnish performance guarantees for the construction of improvements not completed at the time of approval. To that end, Paris Development Corporation entered into an agreement dated November 2,1981 with the Ohio Savings Association and *203 the city of Pepper Pike whereby the sum of $65,000 would be kept in an account pending completion of the improvements, namely the sanitary sewer. The agreement was to last eighteen months from date of signing. The agreement provided that in the event of a default by Paris, Ohio Savings Association could succeed to Paris’s rights and, at its option, complete the construction of the improvements. The agreement further provided that should Ohio Savings Association elect not to complete the improvements, the city would have the right to utilize the proceeds to complete the improvements.

Appellants purchased a lot in the subdivision and sought to commence construction of a house. The purchase agreement specifically referred to the November 2, 1981 performance guarantee and made transfer of title conditional upon completion of the improvements. Paris did not complete the improvements, and the performance guarantee expired on May 2, 1983, with neither Ohio Savings Association nor the city choosing to exercise its right to complete the improvements.

In 1984, Paris and appellants apparently agreed to install a septic system. An application for a septic system was submitted to Cuyahoga County and accepted. However, Paris and appellant could not agree upon which party would pay the cost of the system, and appellants filed suit on September 30, 1986.

The complaint, as it relates to this appeal, alleged that the city was negligent in not enforcing the November 2, 1981 performance guarantee; that the city participated in a breach of contract with Paris, to which appellants were third party beneficiaries; and conspiracy to breach the contract.

I

As an initial matter, Pepper Pike contends that this appeal was not timely filed in accordance with the thirty-day filing period set forth in App. R. 4(A). Following discovery, both parties filed motions for summary judgment. The trial court granted summary judgment in Pepper Pike’s favor on May 22, 1987. However, since other defendants remained, that was not a final appealable order. See Civ. R. 54(B). On June 11, 1987, a half-sheet journal entry was filed stating: “Settled and Dismissed with Prejudice. Costs to each party. J.E.T.B.S. Final.” (Emphasis sic.) On August 4,1987, the parties to the June 11,1987 dismissal filed a stipulation of dismissal as to certain defendants and supplemental judgment entry pursuant to Civ. R. 41(A)(1)(b). It was signed by the parties and the judge. Pepper Pike contends that this appeal should have been taken from the June 11, 1987 judgment entry and not the August 4,1987 judgment entry. We disagree.

Since there was no Civ. R. 54(B) determination of “no just reason for delay” relative to Pepper Pike’s motion for summary judgment, the date, on which the time to bring the appeal started running was contingent upon the disposition of the case for the remaining parties. On June 11, 1987, the parties agreed to a voluntary dismissal pursuant to Civ. R. 41(A)(1)(b). That rule requires the filing of a stipulation of dismissal signed by all parties who have appeared in the action or who still remain in the action at the time of dismissal. Thus, while the parties apparently agreed to the dismissal, it was not final until signed by the parties on August 21, 1987. Accordingly, the summary judgment granted in favor of Pepper Pike did not become final until that date. Since this appeal was filed within thirty days of August 21, 1987, there was no violation of App. R. 4(A).

II

Turning to the merits of the ap *204 peal, appellants contend that the trial court erred in granting summary judgment since genuine issues of material fact exist relating to Pepper Pike’s handling of the performance guarantee agreement. In particular, appellants maintain that the city was negligent in not enforcing the agreement with Paris and that it knowingly conspired to refrain from requiring Paris to install the sanitary sewers. These contentions are without merit.

In reviewing the evidence in the light most favorable to appellants, we find no genuine issues of material fact exist. The November 2, 1981 performance guarantee agreement was executed as required by Pepper Pike Codified Ordinance No. 1105.04(A):

“* * * The developer may obtain conditional approval of the plat and install the required improvements before applying for approval of the final plat, or, alternatively, he may apply for approval of the final plat and drawings and specifications of required improvements concurrently and furnish performance guarantees that he will install the improvements thereafter. * * %iy

Council’s final approval of the plat may not be granted until construction of the improvements is guaranteed. Pepper Pike Codified Ordinance 1105.04(C).

The November 2,1981 agreement 2 provided:

“4. If Paris defaults in the performance of its obligations to the City, and the Association does not elect to complete construction as provided in paragraph 3 above, the City shall have the right to utilize the proceeds of the foresaid loan to a maximum of Sixty-Five Thousand Dollars ($65,000.00), less any disbursements made by the Association hereunder to the time that notice of said default is received by the Association, for the completion of such construction in accordance with the plans and specifications, including payment of all labor and materials furnished in connection therewith.” (Emphasis added.)

Thus, the decision to complete the improvements was discretionary with the city. We need not determine whether appellants had any contractual rights under the agreement since the city was under no duty to complete the improvements in the event Paris defaulted. Even under Pepper Pike Codified Ordinance 1109.17, the city had the discretion to complete the improvements. Hence, there are no facts that establish any violation of a contractual duty to complete the improvements.

Regarding the conspiracy claims, appellants maintain that a conspiracy existed between Paris and Pepper Pike since the city engineer, Charles DeMore, also helped Paris prepare the final plat and performance guarantee. Noticeably absent in the record, however, are any facts that demonstrate the city’s participation in a conspiracy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Cincinnati Stormwater Mgt. Div.
676 N.E.2d 609 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
563 N.E.2d 327, 55 Ohio App. 3d 202, 1988 Ohio App. LEXIS 4101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/passov-v-paris-development-corp-ohioctapp-1988.