Passaic Valley Sewerage Commissioners v. Geo. M. Brewster & Son, Inc.

161 A.2d 503, 32 N.J. 595, 1960 N.J. LEXIS 227
CourtSupreme Court of New Jersey
DecidedJune 6, 1960
StatusPublished
Cited by22 cases

This text of 161 A.2d 503 (Passaic Valley Sewerage Commissioners v. Geo. M. Brewster & Son, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Passaic Valley Sewerage Commissioners v. Geo. M. Brewster & Son, Inc., 161 A.2d 503, 32 N.J. 595, 1960 N.J. LEXIS 227 (N.J. 1960).

Opinion

The opinion of the court was delivered by

Hall, J.

The question before us is whether the trial court, under the circumstances present, properly dismissed the complaint following plaintiff’s opening statement to the jury and then denied an application to reopen.

Geo. M. Brewster & Son, Inc. (“Brewster”) was the low bidder, at $4,998,450, for certain construction work at plaintiff’s Newark Bay pumping station and was awarded the contract in the fall of 1956. The other bidders were Kuchar Brothers (“Kuchar”) at $5,092,650 and Terminal Construction Corp. (“Terminal”) at $5,125,180. Two weeks after the formal contract was executed Brewster subcontracted about 40% of the work to Kuchar. Some 20 days later Brewster entered into a joint venture for the remainder with LaPera Contracting Co., Inc. (“LaPera”), Joseph Miele Construction Co., Inc. (“Miele”), and Salvatore, in which Brewster and LaPera each had a one-quarter interest and Salvatore and Miele together, one-half. Two days thereafter a further agreement was entered into whereby Terminal received a 30% interest in the joint venture.

Brewster was not paid the two final monthly installments under the contract, including the retained percentage on the entire job, amounting to some $589,000, and sued plaintiff therefor in the Law Division, Bergen County. By the pretrial order in that suit made in June 1959, plaintiff’s answer was amended to allege that Brewster and the other five contractors named above had conspired and colluded “to adversely influence the bids submitted” and “to cause improper receipt of open bids” and that Brewster was consequently not entitled to any profit on the job. The order *599 contained no statement of factual contentions in support of this conclusion.

Within a week plaintiff instituted the instant action with an Essex County venue. Beyond setting forth the chronology of contractual events just summarized, the complaint alleged that the Ruchar subcontract was in the amount of $2,196,000 for work which Ruchar’s bid had priced at $3,214,000 and for which Brewster was to receive $3,249,000 pursuant to its successful bid and that plaintiff’s consulting engineers had, some time prior to the receipt of the bids, estimated the approximate cost of the whole job at $2,000.000. The pleading charged that all six defendants conspired, colluded and arranged before the submission of bids that the bids “were to be not unknown, one to the other,” in advance of submission and arranged by improper and unlawful means that they would not be competitive, that the subsequent subcontract and joint venture were in fulfillment of the pre-arranged design and that the profit derived as a result of the scheme “was an illegal, improper, and unconscionable profit, grossly excessive * * * and the result of the arrangement arrived upon by the collusion as aforesaid * * Damages of $2,500,000 were sought against all defendants, apparently on the theory of recovery of the alleged illegal profit.

The answers filed amounted to a general denial of any wrongdoing and also affirmatively asserted that the complaint failed sufficiently to particularize a claim of fraud and to set forth facts sufficient to constitute a cause of action. Shortly thereafter, Brewster’s motion to consolidate this suit with the contract action, for trial in Bergen County, was granted.

Obviously the gravamen of the tort complaint deeply involved the public interest and at the same time was a most serious charge to make. If it was supportable by proof, from the civil aspect alone, the taxpayers of the municipalities served by the Commission had been badly mulcted. And, from the defendants’ point of view, the accusation made *600 was equally important. If there was no basis for it, they were entitled to complete exculpation. Prom all standpoints, and especially that of plaintiff, which had the burden and represented the public interest, the case called for thorough preparation, both on the facts and law, including appropriate use of our discovery, motion and other procedures before trial. But the litigation did not take that course. Plaintiff sought no discovery of any kind. Although plaintiff’s answers to interrogatories propounded by defendants produced nothing in amplification of the general charge of collusion and defendants’ answers to the complaint had asserted it did not set forth a cause of action, no motion of any kind was made. More important, no pretrial conference was held, but instead, a few days before the trial (which came on in October 1959, a little more than two months after the last answer was filed), a consent order was entered reciting “the purpose of the parties to avoid” such a conference. The order then proceeded to amend the pretrial order in the contract suit by setting up an additional defense of improper performance by Brewster in certain particulars (with which we are not concerned) and stating plaintiff’s and defendants’ contentions in the tort action by nothing more than a parroting of the broad allegations of the complaint and answers.

The failure of the court to hold a pretrial conference (R. B. 4:29-1 (a)), the wishes of counsel to the contrary notwithstanding—and this case called for a particularly comprehensive one—cannot be overlooked. At this late date, it should be unnecessary to reiterate the vital importance and compulsory nature of the conference procedure, its purposes, benefits and effects. Cf. Schlossberg v. Jersey City Sewerage Authority, 15 N. J. 360, 369-371, 374 (1954). Thorough exploration of the detailed contentions of the parties and proper framing and explicit expression of the factual and legal issues, with appropriate amendment of the pleadings if necessary, and the possibility of determination of some of the issues in advance of trial by motion, at the *601 direction of the court if need be, might well have avoided the situation now before us for review and enabled a just and expeditious determination of the controversy long since.

Plaintiff admitted in the opening to the jury that it had no direct proof of the claimed collusive agreement and that it must rely entirely on circumstantial evidence and inferences claimed to be legitimately deducible therefrom. The complaint is ambiguous. One cannot tell whether the recitals of the closeness of the bids and the details of the subsequent subcontract and joint venture are intended as mere background or, either standing alone or in conjunction with other facts, are relied on as evidence of collusion. If the latter, questions of relevancy arise. The relevance of the prior estimate of cost made by the consulting engineers is also involved. (Material furnished us by way of consent supplement to the record casts doubts, but it is matter of defense and in any event we can be concerned only with the state of the record at the conclusion of the matter in the trial court.) It is also not clear whether the allegations of excessive and unlawful profit were set forth only to establish a quantum of damages or also as a basis for an inference of a collusive agreement if coupled with proper proof that the job could fairly have been done for a very considerably lower figure. The basis of the general charge of conspiracy or arrangement to suppress competitive bidding seems not necessarily, on the face of the complaint, to be limited to the allegations just referred to.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jane Bishop v. Public Storage
New Jersey Superior Court App Division, 2026
Joseph A. Berkowitz v. Susan J. Soper
128 A.3d 1159 (New Jersey Superior Court App Division, 2016)
Henry v. New Jersey Department of Human Services
9 A.3d 882 (Supreme Court of New Jersey, 2010)
Szczecina v. Pv Holding Corp.
997 A.2d 1079 (New Jersey Superior Court App Division, 2010)
State v. Tilghman
895 A.2d 1207 (New Jersey Superior Court App Division, 2006)
De Vito v. Katsch
157 A.D.2d 413 (Appellate Division of the Supreme Court of New York, 1990)
Bellardini v. Krikorian
537 A.2d 700 (New Jersey Superior Court App Division, 1988)
State v. Portock
501 A.2d 551 (New Jersey Superior Court App Division, 1985)
Amaru v. Stratton
506 A.2d 1225 (New Jersey Superior Court App Division, 1985)
Reilly v. SPIEGELHALTER
241 A.2d 665 (New Jersey Superior Court App Division, 1968)
Finderne Engine Co. v. Morgan Trucking Co.
237 A.2d 624 (New Jersey Superior Court App Division, 1968)
Coleman v. Edison Tp.
232 A.2d 187 (New Jersey Superior Court App Division, 1967)
Hirsch v. Schwartz
209 A.2d 635 (New Jersey Superior Court App Division, 1965)
Poland v. Parsekian
195 A.2d 660 (New Jersey Superior Court App Division, 1963)
Avedisian v. Admiral Realty Corp.
164 A.2d 188 (New Jersey Superior Court App Division, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
161 A.2d 503, 32 N.J. 595, 1960 N.J. LEXIS 227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/passaic-valley-sewerage-commissioners-v-geo-m-brewster-son-inc-nj-1960.