Pasadena Metro Blue Line Construction Authorithy v. Pacific Bell Telephone Co.

44 Cal. Rptr. 3d 556, 140 Cal. App. 4th 658, 2006 Daily Journal DAR 7568, 2006 Cal. Daily Op. Serv. 5241, 2006 Cal. App. LEXIS 877
CourtCalifornia Court of Appeal
DecidedJune 15, 2006
DocketB181175
StatusPublished
Cited by17 cases

This text of 44 Cal. Rptr. 3d 556 (Pasadena Metro Blue Line Construction Authorithy v. Pacific Bell Telephone Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pasadena Metro Blue Line Construction Authorithy v. Pacific Bell Telephone Co., 44 Cal. Rptr. 3d 556, 140 Cal. App. 4th 658, 2006 Daily Journal DAR 7568, 2006 Cal. Daily Op. Serv. 5241, 2006 Cal. App. LEXIS 877 (Cal. Ct. App. 2006).

Opinion

Opinion

RUBIN, J.

Plaintiff Pasadena Metro Blue Line Construction Authority (the Authority) appeals from the summary judgment entered for defendants Southern California Edison Co. (Edison), Southern California Gas Co. (SCG), and Pacific Bell Telephone Co. (PacBell), which determined that those companies did not have to reimburse the Authority for the cost of relocating their utility lines as part of the Authority’s construction of a light rail public transit line. We affirm.

ISSUE PRESENTED

The Los Angeles County Metropolitan Transportation Authority (MTA) operates a light rail public transit system throughout the greater Los Angeles area, comprised of various lines that are designated by color names: Red Line, Green Line, and Blue Line. MTA was supposed to build an extension of *661 its Blue Line from Los Angeles Union Station to Pasadena. 1 Due to legal and budget problems, the MTA suspended that project. The Legislature then stepped in and created a new entity—the Authority—“for the purpose of awarding and overseeing all design and construction contracts for completion of the project.” (Pub. Util. Code, § 132405; see id., §§ 132400-132450.) 2

Under state law, when utility lines must be moved as part of an MTA public transit project, the MTA “shall, by prior agreement,” reimburse the utility for those relocation expenses. (§ 30631, subd. (b).) The MTA had entered into such agreements with various utility companies in connection with building other segments of its light rail commuter train system. Edison, SCO, and PacBell (the utility companies) all had utilities in the project’s path that had to be moved during construction of the Gold Line. After the Authority stepped in to finish the project, it originally budgeted funds to pay the utility companies’ relocation costs, but eventually notified them that it would pay those costs under protest, and seek to recover them later. According to tihe Authority, because section 30631 is, by its terms, applicable to the MTA, and because the Authority is a separate entity, that statute does not apply to it. The Authority sued the utility companies to recover those costs, and later brought a summary judgment motion. That motion was denied on the ground that section 30631 applied even though the Authority was completing the project. On appeal, the Authority contends the trial court erred. We conclude that the trial court was correct. 3

FACTS AND PROCEDURAL HISTORY

We begin with an overview of the transfer of power from the MTA to the Authority. The Legislature gave the Authority a broad grant of powers, including, but not limited to, all powers necessary to plan, develop, own, and build the Gold Line. (§ 132410, subd. (a).) Among these were the power to accept grants, fees, and allocations from the state, local agencies, and private entities (§ 132410, subd. (a)(1)), and the power to relocate utilities as necessary for the project. (§ 132410, subd. (a)(6).) The MTA was required to enter into an agreement with the Authority to hold in trust with the Authority “all real and personal property, and any other assets accumulated in the *662 planning, design, and construction of the project. . . .” (§ 132425.) The MTA was required to transfer to the Authority the unencumbered balance of all local funds programmed for completion of the Gold Line and the Authority was eligible to receive state funds for the project. (§ 132430, subds. (a), (b).) The Authority was required to enter into a memorandum of understanding with the MTA to address the MTA’s ability to review any significant changes in the project’s scope. (§ 132435.) Upon completion of the project, the Authority would dissolve and the MTA would assume responsibility for operating the Gold Line. (§ 132450.)

Pursuant to these provisions, the Authority and the MTA entered into two agreements; a master cooperative agreement (master agreement), and a governmental purpose property trust agreement (trust agreement). The master agreement included a project schedule for the Authority that listed “Third Party Agreement—Utility Relocations” among the project tasks to be completed by the Authority. One section required the Authority to prepare various development contracts, including cooperative agreements with “utilities and the MTA . . . .” The trust agreement noted that the Legislature required “that funds from the funding program be used to pay all costs and expenses related to the completion of the Project.” Therefore, all assets, and real and personal property of the MTA would be held in trust by the Authority for the MTA, and the Authority was required to hold all project funds in the name of the trust. The trust agreement also required the Authority to comply with all laws applicable to the project.

In an application to the Public Utilities Commission (PUC), the Authority said that, pursuant to sections 132425 and 132430, the MTA had transferred to the Authority “all real and personal property, and other assets, as. well as the unencumbered balance of all local funds accumulated for completion of the project.” In another PUC application, the Authority said that the “cost of construction and maintenance of the project, until acceptance of the project by [the MTA] shall be borne by the authority in accordance with the [master agreement]. After that time, the project would be operated by the MTA.”

When the MTA built its earlier rail lines, it entered into cooperative agreements with various utility companies, under which the MTA agreed to pay the costs of utility relocation. When the Authority took over, its budget included money for the same expenses. Later, however, the Authority told the utility companies that it was exempt from section 30631, and relocated their utilities at its expense under protest, promising to seek recovery of those costs at a later time. It is undisputed that the Authority paid $153,224.96 to SCG, $132,599.47 to Edison, and $380,024.83 to PacBell for the cost of utility relocation. The Authority also claimed to have spent another $521,780.78 to have a third party relocate other PacBell facilities.

*663 The Authority sued the utility companies for reimbursement of those costs, contending that the utility companies were obligated to pay them under both sections 6297 and 7901, and the common law. The complaint also included a claim for unjust enrichment, two common counts, and a cause of action for declaratory relief. The Authority then brought separate, but nearly identical, summary judgment motions against each utility. They responded with separate oppositions, but only PacBell’s raised section 30631 as a defense. The trial court found that section 30631 applied because the Authority was acting on the MTA’s behalf. Judgment for the utility companies was then entered.

STANDARD OF REVIEW

Summary judgment is granted when a moving party establishes the right to the entry of judgment as a matter of law. (Code Civ. Proc., § 437c, subd. (c).) In reviewing an order granting summary judgment, we must assume the role of the trial court and redetermine the merits of the motion. In doing so, we must strictly scrutinize the moving party’s papers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMC West Corp. v. Town Center Courtyard CA4/1
California Court of Appeal, 2020
Hubbard v. Coastal Commission
California Court of Appeal, 2019
Hubbard v. Coastal Comm'n
250 Cal. Rptr. 3d 397 (California Court of Appeals, 5th District, 2019)
Madrigal v. California Victim Compensation & Government Claims Board
6 Cal. App. 5th 1108 (California Court of Appeal, 2016)
Kalnel Gardens, LLC v. City of Los Angeles
3 Cal. App. 5th 927 (California Court of Appeal, 2016)
People v. Tingcungco
237 Cal. App. 4th 249 (California Court of Appeal, 2015)
Doe v. Roman Catholic Bishop of San Diego
178 Cal. App. 4th 1382 (California Court of Appeal, 2009)
Opinion No. (2009)
California Attorney General Reports, 2009
P.S. v. San Bernardino City Unified School District
174 Cal. App. 4th 953 (California Court of Appeal, 2009)
Crespo v. WFS Financial Inc.
580 F. Supp. 2d 614 (N.D. Ohio, 2008)
Travis v. Board of Trustees of California State University
73 Cal. Rptr. 3d 854 (California Court of Appeal, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
44 Cal. Rptr. 3d 556, 140 Cal. App. 4th 658, 2006 Daily Journal DAR 7568, 2006 Cal. Daily Op. Serv. 5241, 2006 Cal. App. LEXIS 877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pasadena-metro-blue-line-construction-authorithy-v-pacific-bell-telephone-calctapp-2006.