Partello v. State

1 Ill. Ct. Cl. 309, 1903 Ill. Ct. Cl. LEXIS 7
Court of Claims of Illinois·Decided March 20, 1903·Published

Opinion

William Z. Partello claims from the State the sum of $28,000.00.

The claim is in the nature of an action of assumpsit growing out of a written contract made on August 31, 1892, by him with the Board of Managers of the Illinois State Reformatory at Pontiac, Illinois, to furnish all labor and material required to erect and fully complete three buildings, viz: a cell house with attached school and lavatory building, a solitary and medical examination building combined, and a trade school building.

The plans and specifications upon which the contract was let were referred to in and made a part of the contract, and the material was to be furnished and the work done strictly according to the same.

Article II of the contract provided that the material used be of the best quality and the work executed in the most workmanlike manner, both material and work to be to the entire satisfaction of said Board.

Article III provided that the entire work should be fully completed on or before the 1st day of August, A. D. 1893. That if through the fault of the Board of Managers the work was delayed, it also provides that the contractor be allowed one additional day to the time above stated for each and every day said work was delayed by the fault of the Board of Managers, strikes or other causes over which the contractor had no control.

Also that if the contractor without being so prevented failed to comply with the terms of said contract which relate to the time within which the work was to be completed, then and in that event, he was to forfeit the sum of $25.00 per day for each and every day thereafter until the work was completed; and that such sum be deducted from any money due him and if that amount was not due, then he was to pay the deficiency.

Article IV provided that should the contractor fail to prosecute the work with such diligence as in the judgment of the Board would insure the completion of the work within the time specified in the contract, or fail to comply with any of the terms thereof, and thereby in the judgment Of the Board hazard the satisfactory completion of the work, as stipulated, and after giving the contractor ten days notice in writing, and upon his failure to prosecute the work within said ten days, then the Board was authorized and empowered to take possession of the machinery, tools and material of the contractor and supply whatever was necessary and complete the work and deduct the cost thereof from any money due the contractor and if sufficient sum was not due him, then in that event he was to pay the deficiency.

Article V provided that all work exhibited in or provided to be done by the plans and drawings and not mentioned in the specifications or vice versa, be performed as if same were fully mentioned in such, without extra charge.

Article VI relates to alterations by addition or omissions on the work and amount and manner of payment for same.

Article. VII provided for the use of labor of inmates of the reformatory on the work and the payment therefor.

Article VIII provided that the Board shall appoint an architect and superintendent to have charge of the work but that the final acceptance thereof shall rest with the Board, and that the acts of such architect shall be merely advisory.

Article IX provided that the contract price of said buildings complete be $105,384.00. Payments to be made as follows: Ninety per cent of the value of the work executed to the satisfaction of the Board, to be paid in monthly installments as the work progressed, the said value to be ascertained by the architect according to the terms of the specifications, which specifications provide that “such monthly payments shall be based upon the estimated value of the quantity of such work and computed from the contract unit of value.”

Ten per cent to be retained until the completion of the entire work and the approval and acceptance thereof by the Board, and in case of non-fulfillment of the contract by the contractor, this amount was to be forfeited, such forfeiture not to relieve him from liability to the Board for any damages sustained by reason of any breach of the contract.

Article X provided that the contractor shall save and , keep harmless the Board of Managers from all claims, loss or damage arising from the negligence of the contractor, and to properly protect the work until completed and accepted.

Article XI provided that the contractor shall with two good and sufficient sureties execute a bond to the Board for $52,500.00 for the faithful performance of the contract and that the contract should not be assigned with* out the written consent of the Board.

The claimant alleges in his statement of claim herein filed:

First: That after the execution of said contract he proceeded under the terms thereof with said work with all due diligence and furnished material necessary to the progress of said work.
Second: That instead of being paid in monthly installments, ninety per cent of the value of the work, labor and material performed and furnished under said contract, he was paid only about forty per cent thereof, and that by reason of not receiving ninety per cent, he was delayed and hindered in the progress of said work.
Third: That on or about the 27th day of April, 1893, without right or authority, under the terms of said contract, the said Board of Managers undertook to cancel the contract and prevent him from proceeding with said work.
Fourth: That at the time said action was taken by said Managers there was due him for extra work allowed by the architect and superintendent of said work the sum of $1,838.00 and a further sum of $15,419.76 for work and material put into the said building.
Fifth: That at the time the said contract was can-celled, there was material left upon the grounds of the said Reformatory at Pontiac, belonging to the claimant, which was afterward appropriated and used in the said building by the said Managers, amounting to the sum of $12,580.00 and for which the claimant has never been paid.
Sixth: That in June, 1893, one George McIntosh, made an offer to said Board of Managers to complete the work covered by the contract of claimant for $89,000.00 and in addition thereto, to pay the claimant the sum due him for work and material then done and furnished under said contract; also to take, use and pay for the material belonging to claimant, and then on the ground at said reformatory, and that at the request of said McIntosh and the said Board of Managers, the claimant consented thereto; and that thereafter on the 8th day of July, A. D. 1893, the contract was let to said McIntosh, who thereupon duly entered into a contract with said Board of Managers to complete the work called for by the contract, made by the claimant. That afterwards without the knowledge or consent of claimant, said Board released said McIntosh from said contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Partello v. State, 1 Ill. Ct. Cl. 309, 1903 Ill. Ct. Cl. LEXIS 7 (Ill. Super. Ct. 1903).

1 Ill. Ct. Cl. 309 (Partello v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.