Parsons Evergreene, LLC

CourtArmed Services Board of Contract Appeals
DecidedJanuary 23, 2019
DocketASBCA No. 58634
StatusPublished

This text of Parsons Evergreene, LLC (Parsons Evergreene, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parsons Evergreene, LLC, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Parsons Evergreene, LLC ) ASBCA No. 58634 ) Under Contract No. FA8903-04-D-8703 )

APPEARANCES FOR THE APPELLANT: Douglas S. Oles, Esq. James F. Nagle, Esq. Adam K. Lasky, Esq. Howard W. Roth III, Esq. Oles Morrison Rinker & Baker, LLP Seattle, WA

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Lori R. Shapiro, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE CLARKE ON APPELLANT'S MOTION FOR RECONSIDERATION

The Board issued its decision in this appeal on September 5, 2018. Parsons Evergreene (PE) received the decision on September 10, 2018, and timely filed its motion for reconsideration on October 10, 2018. PE requests reconsideration of the Board's decision concerning Structural Brick, Triarch and Claim Preparation/REA Modification Costs (app. mot. at 1). We will deal with each separately. We have jurisdiction pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. We deny the motion.

DISCUSSION

Standard/or Reconsideration

Parsons Evergreene (PE) must demonstrate a compelling reason for the Board to modify its decision. JF. Taylor, Inc., ASBCA Nos. 56105, 56322, 12-2 BCA ,i 35,125. The standard we apply for reconsideration is "[t]o prevail on reconsideration, the moving party must generally establish that the underlying decision contained mistakes in our findings of facts or errors of law or that newly discovered evidence warrants vacating our decision." DODS, Inc., ASBCA No. 57667, 13 BCA ,J 35,203 at 172,711. Motions for reconsideration are not intended to provide a party with an opportunity to reargue issues previously raised and denied. Cl2, Inc., ASBCA No. 56257, 15-1 BCA ,i 35,829 at 175,194. Structural Brick Claim

Contentions of the Parties

PE contends that the Board made a mistake of fact and error of la,v when it failed to use Mr. Tengler's estimate of the cost PE would have avoided had it been allmved to use its single-wall structural brick design rather than the double-wall (8-inch CMU 1 block and 4-inch brick veneer). Parsons Evergeene, LLC. ASBCA No. 58634. 18-1 BCA ~ 37.137 at 180. 734. finding 6. More specifically PE writes:

[TJhe Board has made a mistake in fact where it finds: .. we are unable to calculate the amount PE is entitled to .. for the added costs due to Government rejection of the "Structural Brick .. Design. Moreover. the Board has made an error of law by applying a legal standard that rejects use of an estimate in circumstances that effectively require reliance on an estimate.

(App. mot. at 10) PE seeks $2,195.588 (id. at 15).

In its opposition the Air Force (AF) presents a table with a side-by-side comparison of sections in PE's motion and PE's post-hearing brief (gov·t resp. at 13-14). The AF argues that this comparison proves that the structural brick argument in PE· s motion is ··an attempt to re litigate the issues already heard and decided by the Board'' (id. at 13 ). The AF also contends that PE "fails to cite any testimony or evidence that ,vas overlooked in the Board's Opinion." Additionally there was .. no legal error in denying the costs claimed by Appellant based on the Estimate:· (Id. at 15)

PE's argument misses the point we clearly made in our decision. PE apparently believes the Board found entitlement for the total increased cost of having to build to the double-wall design rather than the structural-brick design. That is not what we held. We held ...The AF is responsible for the additional design and construction costs incurred to change the Baker 35% design to resist progressive collapse.'' Parsons. 18-1 BCA ~ 37.137 at 180,794. The entirety of PE's basis for reconsideration is PE's mischaracterization of the Board's structural brick decisions.

The decision dealt with structural brick in two parts - design and construction. We found the AF liable for the additional costs PE incurred to design changes required to make the Baker 35% design resist progressive collapse. 18-1 BCA ~ 37,137 at 180.794.

1 Concrete masonry unit. 2 PE explained in its post-hearing brief that it .. completed its 100% design within its bid budget .. and that its design impact claim was for an ·'overrun ... Id. at 180. 794. The Board understood this overrun was directly related to modifications to the design to resist progressive collapse. 2 We awarded PE $722.176 for the additional design effort relating to progressive collapse. Id. at 180. 795.

The second part of the structural brick decision \Vas for the actual cost of construction of the design changes needed to make the VQ resist progressive collapse. We held that the AF was liable for these construction costs but that we could not calculate a quantum amount and consequently awarded nothing. 18-1 BCA ': 37.137 at 180.812-13. PE attacks our holding stating that we committed both factual and legal error because we did not adopt Mr. Tengler's estimate of the cost PE would have avoided had it been allmvcd to use its single-\vall structural brick design rather than the double wall. Contrary to PE·s argument. we have no problem with the use of estimates. however. Mr. Tengler·s estimate was the \Vrong estimate. Mr. Tengler's estimate \Vas for the total cost savings PE would have realized had it been allowed to use the structural brick design. This estimate was not for the cost of constructing the modifications necessary to make the VQ resist progressive collapse, which is what we needed. Looking at Mr. Tengler's estimate. it is titled, "Structural Brick in Lieu of Double Wvthe . Svstcm . - Total Cost Savings.'· We see ~

that $1,192.725 of the $1,906.401 estimate (63%) was "Decreased Cost of Structural Brick vs CMU + Facebrick.'. (R4, tab 3154) We do not see how the cost of facebrick veneer over the CMU wall has anything to do \vith progressive collapse. Importantly. if it does. PE failed to meet its burden of proof tying the two together. We paraphrase what we said in our decision: there is no logical relationship between Mr. Tengler's estimate of total cost savings and the increased cost of construction solely attributed to what was needed to modify the VQ to resist progressive collapse. 18-1 BCA ~ 37.137 at 180.812. We also disagree that it was impossible for PE to either estimate the cost to construct the design changes, based on drawing changes, or, better yet, track the actual costs of construction limited to the changes needed to resist progressive collapse. We deny PE's motion for reconsideration relating to structural brick.

Triarch Claim

PE argues that the information needed to determine quantum is in the record. PE points out that its VQ painting subcontract with KRN had a value of $357.000 and that reducing that amount by a $48.400 credit would result in a quantum amount of $308.600 (app. mot. at 17). PE contends that the Board erred by not considering these facts. PE also argues that under the circumstances "it would seem reasonable to add a further

2 Had we interpreted this portion of the claim otherwise, we may not have awarded PE these design costs. 3 allowance for PE's management and staff time on this issue.'' (Id.) PE seeks $440,137 (id. at 18).

The AF argues that PE in its motion for reconsideration "presents an entirely new argument that was not previously presented prior to the close of the record, or even prior to the Board's Opinion'' (gov·t resp. at 19).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smithkline Beecham Corp. v. Apotex [Corrected Date]
439 F.3d 1312 (Federal Circuit, 2006)
United States v. James C. Dunkel
927 F.2d 955 (Seventh Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Parsons Evergreene, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parsons-evergreene-llc-asbca-2019.