Parrot Ditch v. Ashcraft

2024 MT 272, 558 P.3d 1183, 419 Mont. 93
Montana Supreme Court·Decided November 19, 2024·No. DA 23-0712·Published

Opinion

11/19/2024

DA 23-0712 Case Number: DA 23-0712

IN THE SUPREME COURT OF THE STATE OF MONTANA

2024 MT 272

PARROT DITCH CO.,

Claimant. Objector, and Appellant,

v.

NORMAN ASHCRAFT JR.; COURTNAY O. DUCHIN; CHARLES M. MILLER; PATTY A. MILLER,

Objectors and Appellees,

RAFANELLI PARTNERS LLP,

Notice of Intent to Appear.

APPEAL FROM: Montana Water Court, Case No. 41G-0256-R-2019 Honorable Stephen R. Brown, Associate Water Judge

COUNSEL OF RECORD:

For Appellant:

Abigail R. Brown, Ross P. Keogh, Leah Trahan, Parsons Behle & Latimer, Missoula, Montana

For Appellees:

William C. Fanning, Fanning Law PLLC, Dillon, Montana

For Amicus Curiae:

Dana E. Pepper, Bina R. Peters, River and Range Law, PLLC, Bozeman, Montana

Susan B. Swimley, Attorney at Law, Bozeman, Montana Submitted on Briefs: August 21, 2024

Decided: November 19, 2024

Filed:

Vor-641•—if __________________________________________ Clerk

2 Chief Justice Mike McGrath delivered the Opinion of the Court.

¶1 Parrot Ditch Company (PDC) appeals a Water Court order denying its request for a

service area and decreeing four water rights, one of which is not at issue in this appeal.

¶2 We affirm.

¶3 We restate the issues on appeal as follows:

Issue One: Did the Water Court correctly decree PDC’s service area?

Issue Two: Did the Water Court correctly decree PDC’s Townsend and Methodist rights?

Issue Three: Did the Water Court correctly decree PDC’s Nolte right?

FACTUAL AND PROCEDURAL BACKGROUND

¶4 This dispute centers around the Parrot Ditch Company and its four water rights in

the Jefferson River. PDC delivers water to its Madison County shareholders through the

Parrot Ditch, which runs parallel to the Jefferson River in Basin 41G, generally between

Silver Star and Cardwell.

¶5 Construction on Parrot Ditch began in 1895 to supply Parrot Silver and Copper

Company’s Gaylord Smelter with water. The smelter was never built, but the ditch was

used sporadically until 1916, when PDC was organized and purchased the ditch from

Montana Power Company.

¶6 PDC was formally incorporated on July 5, 1916 “[t]o acquire, own, hold, manage,

control, operate and maintain that certain canal, reservoir and irrigation system out of the

Jefferson River now constructed and in process of construction and owned by the Parrot

3 Ranch Company,” and “[t]o distribute the water diverted through any irrigation system

owned or operated by [PDC]” to its shareholders.

¶7 PDC originally issued and maintains a total of 8,000 shares, which comprise three

types of stock: A Class, B Class, and C Class. A Class stock is company stock that does

not correlate to a specific entitlement to water; its main purpose is to bank shares that are

sold and/or deeded back to the company. B and C Class shares correspond to the amount

of water shareholders are entitled to divert and differ from one another only in relation to

whether they belong to shareholders irrigating above or below the “Doherty Overflow.”

Class B and C shares each represent one eight-thousandth interest in PDC’s water rights

and irrigation system. PDC stopped issuing shares in 1981.

¶8 Two of the water rights at issue were litigated in 1926, when PDC members filed a

complaint to adjudicate “several rights in the said Parrot Ditch in order to obtain the relief

provided for in Section 7152, Revised Codes of Montana, 1921.” Pat Carney v. Parrot

Ditch Co., Findings of Fact Conclusions of Law Judgment and Decree, No. 2271 (Mont.

Fifth Judicial Dist. Feb. 8, 1926). In addition to establishing shareholders’ respective

interests in PDC, Carney referenced priority dates and volumes for two different water

rights.1

1 “That the said Parrot Ditch Co., a corporation, and its predecessors in interest, did on the 8th day of September, 1894, appropriate Twenty Thousand (20,000) inches of water of the Jefferson River,” and “[t]hat the said Parrot Ditch Company did, through its predecessors in interest, appropriate fifteen hundred (1500) statutory inches of the waters of the said Jefferson River on the 24th day of January 1880 . . . .” Carney at 2. 4 ¶9 On March 26, 1982, PDC filed a single statement of claim for five existing rights

pursuant to the 1973 Montana Water Use Act, § 85-2-221, MCA. Four are at issue in this

appeal. The statement of claim described the place of use as 6,475 acres.

¶10 On October 17, 1989, the Water Court entered a Temporary Preliminary Decree for

Basin 41G, which included abstracts for PDC’s four Parrot Ditch claims: 41G 195628-00

(Townsend), 41G 195629-00 (Elliot-Buhl), 41G 195631-00 (Nolte), and 41G 195627-00

(Methodist). The Temporary Preliminary Decree described the place of use for the claims

as 6,560 acres.

¶11 On April 19, 1990, PDC objected to the place of use as described in the Temporary

Preliminary Decree for the Nolte claim, simply stating “acres irrigated are not accurate—

need to be updated.” PDC did not object to the flow rate.2

¶12 On June 13, 1996, the Water Court issued a master’s report in case 41G-167

addressing objections to the Townsend, Elliot-Buhl, and Nolte rights, and recommending

modifications to the period of use and point of diversion for the three claims. The Water

Court adopted the master’s report recommendations on July 11, 1996.

¶13 On January 13, 1997, PDC filed a “request to re-open objection” to the Nolte claim

and requested that the Nolte flow rate be amended from 50 cfs to 231.2 cfs.

¶14 On April 1, 1997, the Water Court issued a master’s report recommending PDC’s

maximum irrigable acreage be increased to 6,560 acres, and that the Nolte flow rate be

adjusted from 50 cfs to 231.2 cfs.

2 This fact is significant because it provides a basis for AMD’s objections to the Nolte claim, as discussed in further detail below. 5 ¶15 On July 29, 1997, the Water Court adopted the water master’s recommendation.

¶16 On September 7, 2001,3 and November 6, 2013, the Water Court adopted additional

water master’s recommendations to amend PDC’s irrigated acreage, ultimately increasing

the place of use for PDC’s four claims to 6,710.78 acres—where it remains today.

¶17 On February 15, 2018, the Water Court issued the Basin 41G Preliminary Decree

(Preliminary Decree). Several elements are the same for each of the four claims, including

6,710.78 maximum irrigable acres, place of use, and period of diversion. The flow rates

and priority dates are each unique, and the Nolte flow rate was decreed as 231.2 cfs.

¶18 Abstracts for each of the four claims provide:

COMBINED FLOW RATE FOR CLAIMS NO. 41G 195627-00, 41G 195628-00, 41G 195629-00 AND 41G 195631-00 IS LIMITED TO THE HISTORIC CAPACITY OF THE DIVERSION STRUCTURE AND THE CONVEYANCE SYSTEM. . . . THE SUM TOTAL VOLUME OF THESE WATER RIGHTS SHALL NOT EXCEED THE AMOUNT PUT TO HISTORICAL AND BENEFICIAL USE.

¶19 PDC objected to the Preliminary Decree and asked the Water Court to decree a

“service area” for its place of use and to include incidental use remarks providing that stock

use be recognized as incidental to irrigation for each of its rights. PDC also asked for

certain corrections that are not at issue here.

¶20 Objectors Norman Ashcraft Jr., Courtnay O. Duchin, Charles M. Miller, and Patty

Miller (collectively, AMD), objected to various elements of PDC’s water rights, including

3 The Water Court Order misstates this date as September 1, 2001.

Free access — add to your briefcase to read the full text and ask questions with AI

Parrot Ditch v. Ashcraft, 2024 MT 272, 558 P.3d 1183, 419 Mont. 93 (Mo. 2024).

2024 MT 272 (Parrot Ditch v. Ashcraft) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

M. v. Si Smith v. Foss
582 P.2d 329 (Montana Supreme Court, 1978)
Kessinger v. Matulevich
925 P.2d 864 (Montana Supreme Court, 1996)
Fisher v. First Citizens Bank
2000 MT 314 (Montana Supreme Court, 2000)
Pearson v. Virginia City Ranches Ass'n
2000 MT 12 (Montana Supreme Court, 2000)
Montana Trout Unlimited v. Beaverhead Water Co.
2011 MT 151 (Montana Supreme Court, 2011)
Nelson v. Brooks
2014 MT 120 (Montana Supreme Court, 2014)
Skelton Ranch, Inc. v. Pondera County Canal & Reservoir Co.
2014 MT 167 (Montana Supreme Court, 2014)
Curry v. Pondera County Canal & Reservoir Co.
2016 MT 77 (Montana Supreme Court, 2016)
Quigley v. McIntosh
103 P.2d 1067 (Montana Supreme Court, 1939)
Kelly v. Teton Prairie LLC
2016 MT 179 (Montana Supreme Court, 2016)
Quigley v. Beck
2017 MT 278 (Montana Supreme Court, 2017)
Maffit v. City of Helena
2021 MT 14 (Montana Supreme Court, 2021)
Twin Creeks v. Petrolia
2022 MT 19 (Montana Supreme Court, 2022)
Bailey v. Tintinger
122 P. 575 (Montana Supreme Court, 1912)
United States v. Barthelmess Ranch Corp.
2016 MT 348 (Montana Supreme Court, 2016)