Parris Roofing & Sheetmetal Co. v. SCR Electric, Inc.

CourtCourt of Appeals of Tennessee
DecidedFebruary 27, 2007
DocketE2006-0263-COA-R3-CV
StatusPublished

This text of Parris Roofing & Sheetmetal Co. v. SCR Electric, Inc. (Parris Roofing & Sheetmetal Co. v. SCR Electric, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parris Roofing & Sheetmetal Co. v. SCR Electric, Inc., (Tenn. Ct. App. 2007).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE November 7, 2006 Session

PARRIS ROOFING & SHEETMETAL CO. v. SCR ELECTRIC, INC.

Appeal from the Chancery Court for Hamilton County No. 03-1024 W. Frank Brown, III, Chancellor

No. E2006-0263-COA-R3-CV - FILED FEBRUARY 27, 2007

Parris Roofing & Sheetmetal Co. (“Plaintiff”) sued SCR Electric, Inc. (“Defendant”) seeking, in part, payment for work Plaintiff had done pursuant to an alleged agreement between Plaintiff and Defendant. The case was tried without a jury and the Trial Court entered an order finding and holding, inter alia, that Plaintiff and Defendant did not have an enforceable agreement, but that Plaintiff was entitled to recover $3,613.50, from Defendant in quantum meruit. Plaintiff appeals to this Court claiming that the Trial Court erred in finding that the reasonable value of the work performed was only $3,613.50. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

D. MICHAEL SWINEY , J., delivered the opinion of the court, in which HERSCHEL P. FRANKS, P.J., and SHARON G. LEE, J., joined.

Robert S. Thompson, Cleveland, Tennessee for the Appellant, Parris Roofing & Sheetmetal Co.

Erskine P. Mabee, Chattanooga, Tennessee for the Appellee, SCR Electric, Inc. OPINION

Background

Plaintiff and Defendant were subcontractors working on a renovation project at the Pleasant Grove School in Dalton, Georgia. Plaintiff had a contract with the general contractor to re- roof the school, and Defendant was handling the electrical work on the project.

A problem arose with the plans for the project and instead of routing the electrical work through the building, Defendant was forced to find another way to route the electrical work. Defendant had two options, route the electrical conduit underground by trenching, or run it over the roof. Gary Douglas Cleaver, co-owner and president of Defendant, and Henry Apple, Plaintiff’s vice-president and estimator, met on the job site to discuss the situation. As a result of this conversation, Plaintiff performed work that included installing pitch pans so that Defendant could run the electrical work across the roof.

After completion of the work, Plaintiff submitted an invoice to Defendant in the amount of $10,828.00, for “Manufacturing and Installing 45 extra pitch pockets for Pleasant Grove School.” Defendant did not pay this invoice. After telephone conversations failed to resolve the dispute, Plaintiff sued Defendant seeking payment. The case was tried without a jury.

David Randall Parris, president and owner of Plaintiff, testified at trial. Mr. Parris testified there was no written contract to cover the work at issue and that he was not involved in the conversation between Mr. Cleaver and Mr. Apple. Mr. Parris testified that pursuant to the conversation between Mr. Apple and Mr. Cleaver, Plaintiff agreed: “To temporarily waterproof the pipe supports that they were putting in the roof. And then as we got in the process of tearing off and reroofing, we had to do a permanent repair, a new application on it.” Mr. Parris explained that Defendant would make a penetration or hole in the roof and then

We had to put down a layer of mastic plastic roof cement, spread it out, put the pitch pan in, set it in this plastic roof cement and put screws in all the corners, come back and put another layer of mastic plastic roof cement around the whole thing, and then come back with another layer of this material as such (indicating), and then as it lapses on the corners you put more plastic, you know, roof cement on each corner.

Mr. Parris further explained

we would do a temporary repair on these type supports, which involved, you know, bringing it - - it had a rubber roof on it. We had to bring the rubber back in, fill in the void around the pipe if there was a void there, bring the rubber back around it, put a new piece of what we call a five-inch tape, which would be glued to the existing old rubber, and tighten it up around the pipe.…[Then] we had to go on with our

-2- roofing project, which meant tearing the old existing roof off and dispose the debris. You know, we had to work across all these conduits and so forth. Then we had to come back after we had the old roof torn off and install a new roof, which consisted of two layers of insulation and two plies of, you know, felt mopped in in hot asphalt, and then attach this white roof cap sheet.

Mr. Parris testified that installing a pitch pan is a two man operation and would generally take one man-hour to install the temporary pitch pan and three more hours to install the permanent one for a total of four man-hours per pitch pan. Plaintiff typically charges $35 per man- hour for work of this type, and Plaintiff billed Defendant for 180 man-hours at $35 per hour. Mr. Parris testified that Plaintiff did not keep records of the actual man-hours and who worked them because “[i]t was an ongoing project. The men worked on it. We’ve done this off and on for years of doing this, and we arrived at, you know, this hourly - -.” He explained that ongoing meant that the men were already on the job site doing other things and when Defendant would cut a hole in the roof they would inform Plaintiff’s men who would then go over and patch it. Mr. Parris admitted that the labor charge is not the actual time spent on each pitch pocket but rather a standard charge: “That was arrived at from 40-some-odd years of being in the business and coming up with how much it takes labor-wise to do a pitch pan.” Plaintiff has no records of the actual time spent on each pitch pocket. Mr. Parris admitted that he was on the job site “maybe once a week” and that his job foreman never told him how much time it took to actually install each pitch pocket.

Mr. Parris testified that the invoice submitted to Defendant included a $3,234 charge for materials, a 40% profit on the materials, and the labor charge for 180 hours. The invoice does not contain a breakdown of any of the charges, but rather simply states the total amount due. When asked, Mr. Parris admitted that during his deposition he testified that normally Plaintiff uses a figure of cost, plus 10 or 15%. He further admitted that he testified during his deposition that it is Plaintiff’s normal procedure when working on a cost-plus basis to provide invoices for materials and time records if a customer requests them. Plaintiff did not provide invoices for materials and time records to Defendant because, Mr. Parris testified: “They never asked for it.” Mr. Parris also admitted that after his phone conversation with Mr. Cleaver regarding the dispute about the price, he was “trying to come up with another number.”

An exhibit was introduced at trial that Plaintiff testified represented the cost calculations used to arrive at the total invoice price. The exhibit lists materials including 5 rolls of membrane, 25 buckets of roof cement, 45 pitch pans, 29 gallons of pourable sealer, aluminum fibrated coating, 1 gallon of quick primer, 2 tubes of NP-1 caulking, and 1 roll of 5" seam tape. Mr. Parris admitted that he testified during his deposition that the only material costs that his job foreman turned in for the patchwork were one gallon of quick prime, NP-1, and one roll of 5" tape. Everything else that Plaintiff listed as a material cost on the exhibit is just an estimate. Mr. Parris stated: “It’s an accurate estimate.…The part that I was emphasizing there, that’s all that he turned in. If he had turned in any more, it would have probably tripled that amount.…He didn’t turn it in, so it wasn’t on the billing.” Mr. Parris testified that hard costs included in the total invoice price included workmen’s compensation of approximately twenty-five percent per dollar, general liability

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Parris Roofing & Sheetmetal Co. v. SCR Electric, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/parris-roofing-sheetmetal-co-v-scr-electric-inc-tennctapp-2007.