Parque Towers Developers, LLC v. Rebecca Christina Vallias

CourtDistrict Court of Appeal of Florida
DecidedJanuary 17, 2024
Docket2021-1366
StatusPublished

This text of Parque Towers Developers, LLC v. Rebecca Christina Vallias (Parque Towers Developers, LLC v. Rebecca Christina Vallias) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parque Towers Developers, LLC v. Rebecca Christina Vallias, (Fla. Ct. App. 2024).

Opinion

Third District Court of Appeal State of Florida

Opinion filed January 17, 2024. Not final until disposition of timely filed motion for rehearing.

________________

Nos. 3D21-1365, 3D21-1366, 3D21-1367, 3D21-1368, 3D21-1369 Lower Tribunal Nos. 18-16927, 19-2809, 19-6496, 19-8894, 19-9992 ________________

Parque Towers Developers, LLC, Appellant/Cross-Appellee,

vs.

Pilac Management, Ltd., et al., Appellees/Cross-Appellants.

Appeals from the Circuit Court for Miami-Dade County, William Thomas, Judge.

Law Offices of Robert P. Frankel, P.A., and Robert P. Frankel (Plantation); Lauri Waldman Ross, P.A., and Lauri Waldman Ross, for appellant/cross-appellee.

Reiner & Reiner, P.A., and David P. Reiner, II, for appellees/cross- appellants.

Before HENDON, GORDO and BOKOR, JJ.

BOKOR, J. These consolidated cross-appeals stem from a judgment entered after

a bench trial finding Parque Towers Developers, LLC, a condominium

developer and the appellant and cross-appellee, liable for breach of contract

after allegedly failing to timely complete construction of five units as required

by purchase agreements entered with the Purchasers, the appellees and

cross-appellants. Parque Towers appeals, claiming that the trial court erred

by interpreting the purchase agreements to require the units be completed

by the date of December 31, 2017, or by rejecting its affirmative defense that

a force majeure exception applied. The Purchasers cross-appeal,

challenging the trial court’s denial of their contemporaneous claims for fraud

in the inducement under the Condominium Act due to allegedly deceptive

representations about the square footage of the units. We find that the fraud

claims were properly rejected, but that the trial court should also have denied

relief under the breach of contract claims because the agreements did not

create an affirmative obligation for the developer to complete the units by a

date certain or otherwise make time of the essence.

BACKGROUND

All five Purchasers entered into functionally identical purchase

agreements for pre-construction condominium units with Parque Towers, the

owner/developer. The agreements contain no date certain for completion of

2 the units, but rather include a clause that “Seller estimates it will substantially

complete construction of the Unit, in the manner specified in this Agreement,

by December 31, 2017, subject to extensions resulting from ‘Force Majeure’

(the ‘Outside Date’).” Another provision states that “[w]henever this

Agreement requires Seller to complete or substantially complete an item of

construction, that item will be understood to be complete or substantially

complete when so completed or substantially completed in Seller’s opinion.”

Parque Towers repeated its estimation of a December 31, 2017, completion

date in various updates and notices provided to the Purchasers throughout

the construction process, though it never expressly represented that the

units would be completed by any date certain.

The agreements also provide that “Purchaser understands that Seller

has the right to schedule the date, time and place for closing, which in no

event shall be scheduled later than one (1) year following the Outside Date”

(referring to the estimated completion date, subject to any extensions) and

which can only occur after the seller has received a certificate of occupancy

for the units and provided the purchasers with 10 days’ notice of the closing

date. 1 Upon being furnished with these notices, the Purchasers become

1 The agreement between Parque Towers and Josh and Michelle Kurzban included an addendum modifying the closing date to require closing be held

3 obligated to close on the units. If either party defaults under the agreement,

the nonbreaching party must provide notice and a 20-day cure period. The

agreement also includes a clause stating that time is of the essence as to

the Purchasers’ obligations only.

After several construction delays, allegedly due to hurricane and

permitting issues, Parque Towers completed the units and noticed the

purchasers of closing dates in early 2019. The Purchasers claimed default

and subsequently brought the underlying suits for breach of contract,

alleging that Parque Towers breached the purchase agreements by failing

to deliver the completed units by December 31, 2017. Four of the five

complaints also sought recission of the agreements due to fraudulent

inducement under section 718.506(1), Florida Statutes, claiming that Parque

Towers deceptively represented the units as being 2,500 square feet when

the actual units delivered were under 2,000 square feet. 2 The cases were

consolidated, and after a nonjury trial, the trial court denied the statutory

claims due to the non-reliance provisions in the agreements, but found that

Parque Towers had been obligated to deliver the completed units by

no more than 60 days after the developer’s receipt of a certificate of occupancy. 2 Parque Towers also brought its own counterclaims for breach of contract, which are not at issue on this appeal.

4 December 31, 2017, and failed to prove that a force majeure exception

applied, and thus entered final judgment awarding the Purchasers the value

of their purchase deposits, plus attorneys’ fees and costs. These appeals

followed.

ANALYSIS

We review a judgment entered after a nonjury trial to ensure the trial

court’s factual findings are supported by competent, substantial evidence.

See, e.g., Sg 2901, LLC v. Complimenti, Inc., 323 So. 3d 804, 806 (Fla. 3d

DCA 2021). The trial court’s interpretation of a contract is a matter of law

reviewed de novo. See, e.g., Charbonier Food Servs., LLC v. 121 Alhambra

Tower, LLC, 206 So. 3d 755, 758 (Fla. 3d DCA 2016). Where a contract is

clear and unambiguous, the plain language of the contract controls as the

best expression of the parties’ intent. Id.

Here, the agreements did not require Parque Towers to complete the

units by December 31, 2017, or otherwise make time of the essence as to

the seller’s obligations. The only completion date referenced in the

agreements is specifically described as an “estimate” for when the units will

be “substantially complete” according to Parque Towers’ own opinion, and

Parque Towers ultimately did finish the units and schedule the closings

within the time required by the agreements and upon proper notice. Aside

5 from the square footage, the Purchasers do not otherwise allege that the

units themselves do not comport with the purchase agreements. Moreover,

while the Purchasers all eventually notified Parque Towers that they

considered its failure to deliver the units by December 31, 2017, to be a

default under the agreement, none of them claimed default or sought to

enforce the agreements until April 2018 at the earliest, long after the original

estimated date and after they had been informed that the estimated

completion date had been changed. Thus, irrespective of the evidence

supporting Parque Towers’ claims of delays due to force majeure, the trial

court could not find Parque Towers in breach of a completion date that was

purely estimated. See Am. Somax Ventures, Inc. v. Touma, 547 So. 2d

1266, 1268 (Fla.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry v. Ecker
415 So. 2d 137 (District Court of Appeal of Florida, 1982)
Cox v. CSX Intermodal, Inc.
732 So. 2d 1092 (District Court of Appeal of Florida, 1999)
Dorchester Development, Inc. v. Burk
439 So. 2d 1032 (District Court of Appeal of Florida, 1983)
Mac-Gray Services, Inc. v. DeGeorge
913 So. 2d 630 (District Court of Appeal of Florida, 2005)
American Somax Ventures v. Touma
547 So. 2d 1266 (District Court of Appeal of Florida, 1989)
Billington v. Ginn-LA Pine Island, Ltd.
192 So. 3d 77 (District Court of Appeal of Florida, 2016)
Oceanic Villas, Inc. v. Godson, Et Ux.
4 So. 2d 689 (Supreme Court of Florida, 1941)
Charbonier Food Services, LLC v. 121 Alhambra Tower, LLC
206 So. 3d 755 (District Court of Appeal of Florida, 2016)
Caronte Enterprises, Inc. v. Berlin
668 So. 2d 233 (District Court of Appeal of Florida, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Parque Towers Developers, LLC v. Rebecca Christina Vallias, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parque-towers-developers-llc-v-rebecca-christina-vallias-fladistctapp-2024.