Parmeter v. Delk

433 S.W.2d 941, 1968 Tex. App. LEXIS 2668
CourtCourt of Appeals of Texas
DecidedSeptember 24, 1968
DocketNo. 7906
StatusPublished
Cited by1 cases

This text of 433 S.W.2d 941 (Parmeter v. Delk) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parmeter v. Delk, 433 S.W.2d 941, 1968 Tex. App. LEXIS 2668 (Tex. Ct. App. 1968).

Opinion

FANNING, Justice.

Plaintiff-appellee Delk sued defendants-appellants, Oren Parmeter and wife, alleging an express oral contract was entered into between plaintiff and defendants to construct certain improvements upon defendants’ residence and alleging that defendants agreed to pay plaintiff the cost of said improvements and a contractor’s fee of $2,500.00. Upon trial it was plaintiffs’ contention that such contract was entered into, was performed by plaintiff as promised in the contract, and that defendants thereby owed plaintiff a contractor’s fee of $2,500.00, less $500.00, which the evidence showed had been previously paid, leaving a balance of $2,000.00 due and owing, that plaintiff demanded payment thereof and such demand was refused by defendants. Defendants contended to the effect [942]*942that there was not an express contract between the parties, that the amount of the contractors’ fee was in dispute, that a $591.-91 check dated August 9, 1966, paid by defendants to plaintiff, was in full settlement of the dispute and constituted an accord and satisfaction.

Trial was to the court with the aid of a jury. The jury in response to special issues submitted found to the effect: (Issue 1) that plaintiff Delk and defendant Parmeter entered into an agreement on or about December, 1965, whereby Delk was to perform certain services for a contractor’s fee of $2,500.00; (Issue 2) that Delk performed such services for which he was to receive said contractor’s fee; (Issue 3) that there was not a bona fide dispute between Delk and Parmeter immediately prior to August 9, 1966, of the exact amount due Delk by Parmeter on the contractor’s fee. (Conditionally submitted Issue 4 inquired as to whether Parmeter on or about August 9, 1966, tendered to Delk a check for $591.91 in full payment of the amount, if any, then due as a contractor’s fee; however Issue 4 was not answered by the jury by reason of the jury’s negative answer to Issue 3).

Judgment was entered for plaintiff against defendants for $2,000.00 and costs. Defendants-appellants have appealed.

Appellants, among other contentions, contend to the effect that there was “no evidence” to support the jury’s findings and the judgment of the court. In reviewing these matters it is fundamental that the appellate court only considers that evidence which when viewed in its most favorable light tends to support such findings and judgment, and must disregard all evidence that would lead to a contrary conclusion. Lindley v. Lindley, 384 S.W.2d 676, 679 (Tex.Sup.1964).

Therefore with respect to the “no evidence” questions, and stating the evidence in its most favorable light in support of the jury’s findings and judgment of the court, we make the following statement of the case:

Appellants entered into an express oral contract with appellee, a contractor, to make certain repairs upon their residence. Appellee made the improvements with certain additions and changes agreed to by the parties and fulfilled his original contract and additional charges as agreed to by the parties. As the work progressed, appellee sent six itemized bills to appellants, dated from Dec. 28, 1965, to July 27, 1966, aggregating a total sum of $26,955.60. On these bills appellants paid a total of $24,-363.69. The final bill of July 27, 1966, was for $2,591.91 and one item of this bill reads as follows: “Contractors Fee (Less previous $500.00 advance) $2,000.00.” (Note. The bill of Jan. 12, 1966, for $1,698.60, contained an item “contractor’s advance . . . $500.00”, which $500.00 item and the remainder of said bill of Jan. 12, 1966, was paid by appellants on Jan. 18, 1966).

Appellee testified to the effect that under the contract he was working on a “cost plus” basis and that as his compensation he was to receive a $2,500.00 contractor’s fee; that $500.00 thereof was paid in January, 1966, and he submitted a bill for the $2,000.00 balance due on the contractor’s fee in the final bill of July 27, 1966, for $2,591.91. Appellee further testified to the effect that all the other items in the bills submitted, with the exception of the $500.00 contractor’s advance (which was paid) and the $2,000.00 unpaid balance on the contractor’s fee, were for labor and materials for the construction of the improvements as shown by the itemized bills.

The above referred to final bill of July 27, 1966, in the sum of $2,591.91 was sent to appellants; on August 9, 1966, Mr. Parme-ter executed a check for $591.91, payable to appellee, and on the back of the check appeared this notation: “Payment in Full”.

According to the testimony of appellee and his bookkeeper, Mr. Westenhaver, the check for $591.91 was not acceptable as payment in full as a balance of $2,000.00 [943]*943was still due and owing. After letters hereinafter referred to were written, ap-pellee’s bookkeeper, Mr. Westenhaver, on November 1, 1966, wrote the words “for cost only” on the back of the check after the words already on the back of the check of “Payment in Full” and the $591.91 check was deposited and paid on or about Nov. 23, 1966.

According to the effect of testimony of appellee and Mr. Westenhaver, prior to Aug. 9, 1966, there was no dispute between appellants and appellee as to the payment of the contractor’s fee balance of $2,000.00 ($500.00 of the $2,500.00 having already been paid by appellants), nor was there any dispute between appellants and appellee as to any item prior to Aug. 9, 1966. According to the testimony of appellee and West-enhaver the dispute first arose after the $591.91 check was given. Appellee further testified as to events subsequent to August 9, 1966, in part, as found below.1 The tes[944]*944timony of appellee is clearly to the effect that the final statement was submitted, then the check of Aug. 9, 1966 in question was given, and that Mr. Parmeter refused to pay the balance of $2,000.00 then due, and that the dispute arose for the first time after said August 9, 1966, check was given and Mr. Parmeter’s refusal to pay the $2,-000.00 balance due on the $2,500.00 contractor’s fee.

Appellee’s bookkeeper, Mr. Westenhaver corroborated appellee’s testimony in many respects and with respect to there being no bona fide dispute between appellants and appellee prior to August 9, 1966. We quote in part from this testimony as found below.2

Appellants also contend to the effect that under the undisputed evidence that there was a genuine dispute between the parties and that the tendering of the $591.91 check, marked “Payment in Full” on the back, and appellee’s cashing of the check and retention of the $591.91 constituted an accord and satisfaction, and that accordingly ap-pellee was not entitled to a $2,000.00 judgment, and that the trial court erred in overruling defendants-appellants’ motion for instructed verdict.

In case of liquidated claims, where the full amount of the claim is not paid and no additional or substituted consideration is shown, no accord and satisfaction results. 1 Tex.Jur.2d, Accord and Satisfaction, Sec. 13, p. 218. Also the mere payment and acceptance of a sum of money less than the amount of an undisputed indebtedness due, in full satisfaction of the debt, does not, for want of consideration, constitute an accord and satisfaction, and does not bar the creditor’s suit to recover the balance. In this connection see Buchanan & Carvel et al. v. Etie, 191 S.W.2d 706

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rhea v. Smith
462 S.W.2d 78 (Court of Appeals of Texas, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
433 S.W.2d 941, 1968 Tex. App. LEXIS 2668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parmeter-v-delk-texapp-1968.