FANNING, Justice.
Plaintiff-appellee Delk sued defendants-appellants, Oren Parmeter and wife, alleging an express oral contract was entered into between plaintiff and defendants to construct certain improvements upon defendants’ residence and alleging that defendants agreed to pay plaintiff the cost of said improvements and a contractor’s fee of $2,500.00. Upon trial it was plaintiffs’ contention that such contract was entered into, was performed by plaintiff as promised in the contract, and that defendants thereby owed plaintiff a contractor’s fee of $2,500.00, less $500.00, which the evidence showed had been previously paid, leaving a balance of $2,000.00 due and owing, that plaintiff demanded payment thereof and such demand was refused by defendants. Defendants contended to the effect [942]*942that there was not an express contract between the parties, that the amount of the contractors’ fee was in dispute, that a $591.-91 check dated August 9, 1966, paid by defendants to plaintiff, was in full settlement of the dispute and constituted an accord and satisfaction.
Trial was to the court with the aid of a jury. The jury in response to special issues submitted found to the effect: (Issue 1) that plaintiff Delk and defendant Parmeter entered into an agreement on or about December, 1965, whereby Delk was to perform certain services for a contractor’s fee of $2,500.00; (Issue 2) that Delk performed such services for which he was to receive said contractor’s fee; (Issue 3) that there was not a bona fide dispute between Delk and Parmeter immediately prior to August 9, 1966, of the exact amount due Delk by Parmeter on the contractor’s fee. (Conditionally submitted Issue 4 inquired as to whether Parmeter on or about August 9, 1966, tendered to Delk a check for $591.91 in full payment of the amount, if any, then due as a contractor’s fee; however Issue 4 was not answered by the jury by reason of the jury’s negative answer to Issue 3).
Judgment was entered for plaintiff against defendants for $2,000.00 and costs. Defendants-appellants have appealed.
Appellants, among other contentions, contend to the effect that there was “no evidence” to support the jury’s findings and the judgment of the court. In reviewing these matters it is fundamental that the appellate court only considers that evidence which when viewed in its most favorable light tends to support such findings and judgment, and must disregard all evidence that would lead to a contrary conclusion. Lindley v. Lindley, 384 S.W.2d 676, 679 (Tex.Sup.1964).
Therefore with respect to the “no evidence” questions, and stating the evidence in its most favorable light in support of the jury’s findings and judgment of the court, we make the following statement of the case:
Appellants entered into an express oral contract with appellee, a contractor, to make certain repairs upon their residence. Appellee made the improvements with certain additions and changes agreed to by the parties and fulfilled his original contract and additional charges as agreed to by the parties. As the work progressed, appellee sent six itemized bills to appellants, dated from Dec. 28, 1965, to July 27, 1966, aggregating a total sum of $26,955.60. On these bills appellants paid a total of $24,-363.69. The final bill of July 27, 1966, was for $2,591.91 and one item of this bill reads as follows: “Contractors Fee (Less previous $500.00 advance) $2,000.00.” (Note. The bill of Jan. 12, 1966, for $1,698.60, contained an item “contractor’s advance . . . $500.00”, which $500.00 item and the remainder of said bill of Jan. 12, 1966, was paid by appellants on Jan. 18, 1966).
Appellee testified to the effect that under the contract he was working on a “cost plus” basis and that as his compensation he was to receive a $2,500.00 contractor’s fee; that $500.00 thereof was paid in January, 1966, and he submitted a bill for the $2,000.00 balance due on the contractor’s fee in the final bill of July 27, 1966, for $2,591.91. Appellee further testified to the effect that all the other items in the bills submitted, with the exception of the $500.00 contractor’s advance (which was paid) and the $2,000.00 unpaid balance on the contractor’s fee, were for labor and materials for the construction of the improvements as shown by the itemized bills.
The above referred to final bill of July 27, 1966, in the sum of $2,591.91 was sent to appellants; on August 9, 1966, Mr. Parme-ter executed a check for $591.91, payable to appellee, and on the back of the check appeared this notation: “Payment in Full”.
According to the testimony of appellee and his bookkeeper, Mr. Westenhaver, the check for $591.91 was not acceptable as payment in full as a balance of $2,000.00 [943]*943was still due and owing. After letters hereinafter referred to were written, ap-pellee’s bookkeeper, Mr. Westenhaver, on November 1, 1966, wrote the words “for cost only” on the back of the check after the words already on the back of the check of “Payment in Full” and the $591.91 check was deposited and paid on or about Nov. 23, 1966.
According to the effect of testimony of appellee and Mr. Westenhaver, prior to Aug. 9, 1966, there was no dispute between appellants and appellee as to the payment of the contractor’s fee balance of $2,000.00 ($500.00 of the $2,500.00 having already been paid by appellants), nor was there any dispute between appellants and appellee as to any item prior to Aug. 9, 1966. According to the testimony of appellee and West-enhaver the dispute first arose after the $591.91 check was given. Appellee further testified as to events subsequent to August 9, 1966, in part, as found below.1 The tes[944]*944timony of appellee is clearly to the effect that the final statement was submitted, then the check of Aug. 9, 1966 in question was given, and that Mr. Parmeter refused to pay the balance of $2,000.00 then due, and that the dispute arose for the first time after said August 9, 1966, check was given and Mr. Parmeter’s refusal to pay the $2,-000.00 balance due on the $2,500.00 contractor’s fee.
Appellee’s bookkeeper, Mr. Westenhaver corroborated appellee’s testimony in many respects and with respect to there being no bona fide dispute between appellants and appellee prior to August 9, 1966. We quote in part from this testimony as found below.2
Appellants also contend to the effect that under the undisputed evidence that there was a genuine dispute between the parties and that the tendering of the $591.91 check, marked “Payment in Full” on the back, and appellee’s cashing of the check and retention of the $591.91 constituted an accord and satisfaction, and that accordingly ap-pellee was not entitled to a $2,000.00 judgment, and that the trial court erred in overruling defendants-appellants’ motion for instructed verdict.
In case of liquidated claims, where the full amount of the claim is not paid and no additional or substituted consideration is shown, no accord and satisfaction results. 1 Tex.Jur.2d, Accord and Satisfaction, Sec. 13, p. 218. Also the mere payment and acceptance of a sum of money less than the amount of an undisputed indebtedness due, in full satisfaction of the debt, does not, for want of consideration, constitute an accord and satisfaction, and does not bar the creditor’s suit to recover the balance. In this connection see Buchanan & Carvel et al. v. Etie, 191 S.W.2d 706
Free access — add to your briefcase to read the full text and ask questions with AI
FANNING, Justice.
Plaintiff-appellee Delk sued defendants-appellants, Oren Parmeter and wife, alleging an express oral contract was entered into between plaintiff and defendants to construct certain improvements upon defendants’ residence and alleging that defendants agreed to pay plaintiff the cost of said improvements and a contractor’s fee of $2,500.00. Upon trial it was plaintiffs’ contention that such contract was entered into, was performed by plaintiff as promised in the contract, and that defendants thereby owed plaintiff a contractor’s fee of $2,500.00, less $500.00, which the evidence showed had been previously paid, leaving a balance of $2,000.00 due and owing, that plaintiff demanded payment thereof and such demand was refused by defendants. Defendants contended to the effect [942]*942that there was not an express contract between the parties, that the amount of the contractors’ fee was in dispute, that a $591.-91 check dated August 9, 1966, paid by defendants to plaintiff, was in full settlement of the dispute and constituted an accord and satisfaction.
Trial was to the court with the aid of a jury. The jury in response to special issues submitted found to the effect: (Issue 1) that plaintiff Delk and defendant Parmeter entered into an agreement on or about December, 1965, whereby Delk was to perform certain services for a contractor’s fee of $2,500.00; (Issue 2) that Delk performed such services for which he was to receive said contractor’s fee; (Issue 3) that there was not a bona fide dispute between Delk and Parmeter immediately prior to August 9, 1966, of the exact amount due Delk by Parmeter on the contractor’s fee. (Conditionally submitted Issue 4 inquired as to whether Parmeter on or about August 9, 1966, tendered to Delk a check for $591.91 in full payment of the amount, if any, then due as a contractor’s fee; however Issue 4 was not answered by the jury by reason of the jury’s negative answer to Issue 3).
Judgment was entered for plaintiff against defendants for $2,000.00 and costs. Defendants-appellants have appealed.
Appellants, among other contentions, contend to the effect that there was “no evidence” to support the jury’s findings and the judgment of the court. In reviewing these matters it is fundamental that the appellate court only considers that evidence which when viewed in its most favorable light tends to support such findings and judgment, and must disregard all evidence that would lead to a contrary conclusion. Lindley v. Lindley, 384 S.W.2d 676, 679 (Tex.Sup.1964).
Therefore with respect to the “no evidence” questions, and stating the evidence in its most favorable light in support of the jury’s findings and judgment of the court, we make the following statement of the case:
Appellants entered into an express oral contract with appellee, a contractor, to make certain repairs upon their residence. Appellee made the improvements with certain additions and changes agreed to by the parties and fulfilled his original contract and additional charges as agreed to by the parties. As the work progressed, appellee sent six itemized bills to appellants, dated from Dec. 28, 1965, to July 27, 1966, aggregating a total sum of $26,955.60. On these bills appellants paid a total of $24,-363.69. The final bill of July 27, 1966, was for $2,591.91 and one item of this bill reads as follows: “Contractors Fee (Less previous $500.00 advance) $2,000.00.” (Note. The bill of Jan. 12, 1966, for $1,698.60, contained an item “contractor’s advance . . . $500.00”, which $500.00 item and the remainder of said bill of Jan. 12, 1966, was paid by appellants on Jan. 18, 1966).
Appellee testified to the effect that under the contract he was working on a “cost plus” basis and that as his compensation he was to receive a $2,500.00 contractor’s fee; that $500.00 thereof was paid in January, 1966, and he submitted a bill for the $2,000.00 balance due on the contractor’s fee in the final bill of July 27, 1966, for $2,591.91. Appellee further testified to the effect that all the other items in the bills submitted, with the exception of the $500.00 contractor’s advance (which was paid) and the $2,000.00 unpaid balance on the contractor’s fee, were for labor and materials for the construction of the improvements as shown by the itemized bills.
The above referred to final bill of July 27, 1966, in the sum of $2,591.91 was sent to appellants; on August 9, 1966, Mr. Parme-ter executed a check for $591.91, payable to appellee, and on the back of the check appeared this notation: “Payment in Full”.
According to the testimony of appellee and his bookkeeper, Mr. Westenhaver, the check for $591.91 was not acceptable as payment in full as a balance of $2,000.00 [943]*943was still due and owing. After letters hereinafter referred to were written, ap-pellee’s bookkeeper, Mr. Westenhaver, on November 1, 1966, wrote the words “for cost only” on the back of the check after the words already on the back of the check of “Payment in Full” and the $591.91 check was deposited and paid on or about Nov. 23, 1966.
According to the effect of testimony of appellee and Mr. Westenhaver, prior to Aug. 9, 1966, there was no dispute between appellants and appellee as to the payment of the contractor’s fee balance of $2,000.00 ($500.00 of the $2,500.00 having already been paid by appellants), nor was there any dispute between appellants and appellee as to any item prior to Aug. 9, 1966. According to the testimony of appellee and West-enhaver the dispute first arose after the $591.91 check was given. Appellee further testified as to events subsequent to August 9, 1966, in part, as found below.1 The tes[944]*944timony of appellee is clearly to the effect that the final statement was submitted, then the check of Aug. 9, 1966 in question was given, and that Mr. Parmeter refused to pay the balance of $2,000.00 then due, and that the dispute arose for the first time after said August 9, 1966, check was given and Mr. Parmeter’s refusal to pay the $2,-000.00 balance due on the $2,500.00 contractor’s fee.
Appellee’s bookkeeper, Mr. Westenhaver corroborated appellee’s testimony in many respects and with respect to there being no bona fide dispute between appellants and appellee prior to August 9, 1966. We quote in part from this testimony as found below.2
Appellants also contend to the effect that under the undisputed evidence that there was a genuine dispute between the parties and that the tendering of the $591.91 check, marked “Payment in Full” on the back, and appellee’s cashing of the check and retention of the $591.91 constituted an accord and satisfaction, and that accordingly ap-pellee was not entitled to a $2,000.00 judgment, and that the trial court erred in overruling defendants-appellants’ motion for instructed verdict.
In case of liquidated claims, where the full amount of the claim is not paid and no additional or substituted consideration is shown, no accord and satisfaction results. 1 Tex.Jur.2d, Accord and Satisfaction, Sec. 13, p. 218. Also the mere payment and acceptance of a sum of money less than the amount of an undisputed indebtedness due, in full satisfaction of the debt, does not, for want of consideration, constitute an accord and satisfaction, and does not bar the creditor’s suit to recover the balance. In this connection see Buchanan & Carvel et al. v. Etie, 191 S.W.2d 706 (Tex.Civ.App.1945, wr. ref., n. r. e.), wherein it was stated in part as follows:
“On August 28, 1943, the company mailed to appellee its check for $2,074.74, which was the amount of the one-tenth retained by it. This check was marked ‘Balance on account Bryan Air Field Job, Bryan, Texas.’ Also printed on the check was, ‘This check is in full settlement of account as shown hereon.’ When the check was cashed and returned, this latter statement had been scratched out. This check was received by appellee about September 1, 1943, when he placed thereon in typewriter the following: 'Endorsement of this check does not constitute the payment in full, but is endorsed only for the amount shown on the other side of this check.’ The check was then endorsed by W. R. Etie and cashed. When the company learned of the limited endorsement by Etie it notified him to return the proceeds of the check at [945]*945once, or accept them as a payment in full. Etie made no reply to this demand.
“Appellants contend that the above facts show an accord and satisfaction. We do not agree. There is at least one element missing, that of consideration. An accord and satisfaction is regarded as an independent and separate contract and must be supported by a consideration. The payment to Etie of the $2,074.74 was only the payment of a sum already acknowledged to be due him and which did not cover any of the items sued for herein. Such a payment cannot be the consideration for an accord and satisfaction. The jury, upon sufficient evidence, found that the payment made to Etie did not cover any part of the items recovered upon in this suit. Hines v. Massachusetts Mutual Life Ins. Co., Tex.Civ.App., 174 S.W.2d 94; Woodmen of the World Life Ins. Society v. Smauley, Tex.Civ.App., 153 S.W.2d 608; Business Men’s Assurance Co. v. Bradley, Tex.Civ.App., 275 S.W. 622; National Mutual Benefit Ass’n v. Butler, Tex.Civ.App., 72 S.W.2d 659; Silvers Box Corp. v. Boynton Lumber Co., Tex.Civ.App., 297 S.W. 1059; Chicago Fraternal Life Ins. Ass’n v. Herring, Tex.Civ.App., 104 S.W.2d 901; Home Benevolent Society v. Keeter, Tex.Civ.App., 82 S.W.2d 1084; Ortiz [Oil] Co. v. Luttes, Tex.Civ.App., 141 S.W.2d 1050; Alexander v. Stock Yards National Bank, Tex.Civ.App., 154 S.W.2d 997; Machicek et ux v. Renger, Tex.Civ.App., 185 S.W.2d 486; Turner v. Pugh, Tex.Civ.App., 187 S.W.2d 598.”
We hold that there was ample evidence of probative force and that the same was sufficient to support the jury’s findings to special issues 1, 2 and 3.
We further hold that since there was ample evidence of probative force to support the finding of the jury to the effect that no bona fide dispute existed between the plaintiff and defendants immediately prior to August 9, 1966, that the plaintiff’s cashing of defendant Parmeter’s check in an amount less than the liquidated debt, in the manner and under the circumstances as shown by the record in this case, did not operate as and did not constitute an accord and satisfaction, and that plaintiff-appellee was entitled to recover judgment for the $2,000.00 balance due on his contractor’s fee.
We further hold that the trial court correctly overruled defendant’s motions for instructed verdict and for new trial.
All of appellants’ points are overruled. The judgment of the trial court is affirmed.
Affirmed.