Parkhurst Mall Corp. v. Taneyhill, Unpublished Decision (1-26-2007)

2007 Ohio 340
CourtOhio Court of Appeals
DecidedJanuary 26, 2007
DocketNo. 2006-T-0082.
StatusUnpublished
Cited by2 cases

This text of 2007 Ohio 340 (Parkhurst Mall Corp. v. Taneyhill, Unpublished Decision (1-26-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parkhurst Mall Corp. v. Taneyhill, Unpublished Decision (1-26-2007), 2007 Ohio 340 (Ohio Ct. App. 2007).

Opinion

OPINION
{¶ 1} Appellant, Parkhurst Mall Corporation ("Parkhurst"), appeals the judgment of the Trumbull County Court of Common Pleas.

{¶ 2} The record indicates that this case began as an administrative appeal from the city of Warren ("city") building department's December 2, 2002 demolition order of a shopping plaza owned by Parkhurst. Appellee, Christopher A. Taneyhill ("TaneyhiN"), interim building official for the city, issued the adjudication order of demolition declaring the vacant buildings unsafe pursuant to Section 115 of the 2002 Ohio Building Code. Parkhurst appealed the city's demolition order to the Ohio Board of Building Appeals ("OBBA"). On February 13, 2003, the OBBA conducted a hearing on the matter. On February 19, 2003, the OBBA issued its decision affirming the city's demolition order. On March 3, 2003, Parkhurst filed an appeal of that decision with the Trumbull County Court of Common Pleas.

{¶ 3} Since no stay or injunction had been issued pending appeal, the city elected to commence demolition of the plaza in May 2004. After demolition of a portion of the plaza, Parkhurst filed a motion for a temporary restraining order. Thereafter, the parties agreed to submit the matter to the court's magistrate to determine whether an agreement could be reached that Parkhurst would complete necessary rehabilitation to the property within a reasonable time period. As a result of the negotiations, the parties entered into a settlement agreement. The agreement was adopted and filed by the court on August 5, 2004, under the caption "Judgment Entry (Settlement)." The entry was signed by the trial judge, and the attorneys for Parkhurst, TaneyhiN, and the OBBA.

{¶ 4} The agreed entry provides in pertinent part as follows: Parkhurst agreed to restore a section of the plaza formerly occupied as an Ames Store to a "condition suitable for the leasing or sale * ** [.]" Specifically, Parkhurst agreed to submit detailed construction documents for the rehabilitation project, restore all building utilities and fire protection, and complete demolition on the remaining sections of the plaza that were not part of the renovation project. All work was required to be "substantially performed" within six months from August 5, 2004. The agreement further stated that "[pjrovided that [Parkhurst] complies with this agreement, the [city] is restrained and enjoined from taking further action to demolish the structure, so long that it is maintained as agreed upon in the settlement." The agreement set forth that the parties acknowledged that city would be liable to the demolition contractor, Boccia, under the demolition contract for the demolition that had been earlier initiated by the city. Parkhurst agreed to "defend, indemnify and hold harmless [city] for any and all claims, demands and actions arising out of said contract, including * * * attorney fees." It further provided that, "[a]ll claims, except as provided herein, in this action are settled and dismissed with prejudice."

{¶ 5} On January 19, 2005, the city filed a motion to vacate the settlement, dissolve injunction, and enforce the order of demolition of the remaining portion of the plaza.1 At a hearing held on April 29, 2005, the court granted Parkhurst an additional ninety days to perform work required under the settlement agreement.

{¶ 6} In March 2006, the court, sua sponte, asked all parties to meet with the court at the site of the plaza property to view what work had been performed. Subsequently, an evidentiary hearing on the city's motion was held on November 16, 2005, May 9, and May 10, 2006, to determine whether Parkhurst had breached the settlement by failing to substantially perform under the terms of the agreement. By a judgment entry filed June 7, 2006, the court held that "[t]he injunction * * * is dissolved and [Parkhurst] is found to be in substantial breach of the [agreement of August 5, 2004." The court further affirmed the decision of the OBBA, and awarded the city judgment "against [p]laintiff Donald Guarnieri as signator to the August 5, 2004 agreement in the amount of $78, 986.48 * * * the amount owed Boccia Construction for work done."

{¶ 7} It is from this judgment that Parkhurst has filed a timely appeal asserting the following ten assignments of error:

{¶ 8} "[1] The trial court improperly granted [judgment ] against an attorney for the corporation rather [than] the corporation.

{¶ 9} "[2.] The trial court improperly ruled in favor of defendant when delay was the result of [defendant's] conduct.

{¶ 1O} "[3.] The trial court [erred] in finding the city employee a proper party to file action without first being tested and passing exam and had no capacity to file the action in the initial stages.

{¶ 11} "[4.] The finding of the trial court for judgment of an account was not based on any probative evidence.

{¶ 12} "[5.] Indemnification of a party requires that the court to first, find the debtor to be liable for payment and indemnified party [indebted].

{¶ 13} "[6.] Trial [court] [erred] in not having `de novo' trial enforcing an agreement between the parties when `[substantial] performance' had been accomplished by plaintiff.

{¶ 14} "[7.] The state board under which a hearing occurred is [an] unconstitutional body consisting of non-elected members with testing and/or familiarity with tar structure which was tested and found, at [owner's] expense, to be structurally sound.

{¶ 15} "[8.] The court [erred] in [bifurcating] a hearing on the status of work, evidence; and applicable law.

{¶ 16} "[9.] The court [used] evidence in the file not connected to the property in question in arriving at a finding from evidence prior to May 7, 2006.

{¶ 17} "[10.] The trial court mixed and co-mingled [its] [remedies] and decisions between agreement and `de novo' stages to the [detriment] of plaintiff."

{¶ 18} For purposes of our analysis, we will consolidate certain assignments of error and address others out of the order in which they are presented.

{¶ 19} At the outset we note that Parkhurst's third, seventh, and tenth assignments of error relate to the city's demolition order and the decision of the OBBA. In Continental W. Condominium Unit Owners Assn. v.Howard E. Ferguson, Inc. (1996), 74 Ohio St.3d 501, 502, the Supreme Court of Court held "[i]t is axiomatic that a settlement agreement is a contract designed to terminate a claim by preventing or ending litigation and that such agreements are valid and enforceable by either party." See, also, Keck v. Health Care Retirement Corp. ofAmerica, 11th Dist. No. 99-L-105, 2000 Ohio App. LEXIS 5915, at 7. A settlement agreement may reserve jurisdiction in the court to enforce the settlement terms even if the case was dismissed. Grange Mutual Cas.Co. v. Paterson, 11th Dist. No. 98-A-0086, 1999 Ohio App. LEXIS 5512, at 7.

{¶ 20} In its settlement judgment entry, the court expressly retained jurisdiction of the settlement agreement and all other claims were dismissed with prejudice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilmington Savs. Fund Soc. v. Medvec Properties, L.L.C.
2019 Ohio 4133 (Ohio Court of Appeals, 2019)
Parkhurst Mall Corp. v. Taneyhill, 2007-T-0061 (2-22-2008)
2008 Ohio 728 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parkhurst-mall-corp-v-taneyhill-unpublished-decision-1-26-2007-ohioctapp-2007.