Parker's Mechanical Contr. Inc. v. Eastpoint Water & Sewer Dist.

367 So. 2d 665, 1979 Fla. App. LEXIS 14152
CourtDistrict Court of Appeal of Florida
DecidedFebruary 1, 1979
DocketKK-122
StatusPublished
Cited by11 cases

This text of 367 So. 2d 665 (Parker's Mechanical Contr. Inc. v. Eastpoint Water & Sewer Dist.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker's Mechanical Contr. Inc. v. Eastpoint Water & Sewer Dist., 367 So. 2d 665, 1979 Fla. App. LEXIS 14152 (Fla. Ct. App. 1979).

Opinion

367 So.2d 665 (1979)

PARKER's MECHANICAL CONTRACTOR'S, INC., and Airvac, Appellants,
v.
EASTPOINT WATER AND SEWER DISTRICT et al., Appellees.

No. KK-122.

District Court of Appeal of Florida, First District.

February 1, 1979.
Rehearing Denied March 12, 1979.

*666 Dale E. Rice, Crestview, and Watkins & Watkins, Apalachicolo, for appellants.

Edgar Lee Elzie, Jr., East Point, for appellee Eastpoint.

MASON, ERNEST E., Associate Judge.

This is an appeal from a final judgment of the Circuit Court of Franklin County wherein the trial court held that appellant, Parker's Mechanical Contractor's, Inc., was *667 entitled to the sum of $122,686.73, principal amount, without prejudgment interest on such amount, against appellee, Eastpoint Water and Sewer District; and also held that the appellant, Airvac, was entitled to the sum of $14,636.36 against Technical Marketing, Inc., one of the appellees herein, but denied prejudgment interest on said amount.

Although Technical Marketing, Inc., was made a party appellee herein by Airvac who joined in the appeal of Parker's Mechanical Contractor's, Inc., we have not been favored by any brief filed herein by it and will decide the cause as to it based upon the point raised by Airvac and the law applicable to such issue as we find it to be from Airvac's brief and our own research.

The facts giving rise to this suit are as follows: Parker's Mechanical Contractor's, Inc. (hereinafter referred to as "Parker") was awarded a contract by Eastpoint Water and Sewer District (hereinafter referred to as the "District") to install a new vacuum collection system in Franklin County. Before letting the contract, the District realized that the type of vaults and vault covers it had planned to require were prohibitively expensive and thus the District engineers compromised on a substitute type of vault and cover. Technical Marketing, Inc. (hereinafter referred to as "Technical"), a subcontractor of Parker to furnish the vaults and covers for the project, demonstrated to the District engineers a cheaper type of vault and cover manufactured by Sonoco Products Company, a third-party defendant below, and an appellee herein (hereinafter referred to as "Sonoco"). All agreed to substitute the Sonoco product for the more expensive Ford Assembly originally planned to be used. But shortly after installation, the Sonoco covers began to break down. Parker recommended that all 250 covers be returned to Technical who had furnished them on the job, but the District engineers rejected the suggestion and decided to replace only 30 of the Sonoco covers and to continue to use the remaining 220.

This litigation began on June 4, 1976, when Airvac filed suit against the District, Parker and Technical to foreclose a mechanic's lien on the undisbursed monies contained in a fund retained by the District. Airvac's claim arose out of some valves it sold to Technical for use in the Parker-District contract job and for which it claimed there was a balance due it in the sum of $14,636.14. It was determined at the trial that the claim for a mechanic's lien was filed too late under the Mechanic's Lien Statute, and the court awarded Airvac only a monetary judgment and only against Technical to whom it had sold the valves.

In answer to Airvac's claim, each of the defendants filed general answers and cross-claims. The District filed a cross-claim against Parker and Technical alleging defective covers and pumps. Parker filed a cross-claim against the District for $122,686 for payment under the contract for work performed. Technical filed a cross-claim against Parker for $16,791, alleged to be due it under its subcontract. Also Technical filed a third-party complaint against Sonoco because of the alleged defective covers.

A pretrial conference was held and the trial court entered an order decreeing that Airvac was owed $14,636 for the valves it furnished for the project and declared that it would provide for the method and manner of payment of that claim in the final judgment. In the pretrial order the court further decreed that Parker was entitled to $122,686.73 from the District, subject to any setoffs established at the trial because of the District's cross-claim against Parker. In such pretrial order, the court stated that the parties agreed that the District owed Parker a balance under the original contract in the sum of $122,686.73, "subject to any setoffs which may be established at the trial of this cause by reason of (a) improper color coding throughout the system, (b) water and sewer pumps which did not meet contract specifications and (c) defective vault and manhole covers." (Underscoring and parentheses added.)

Further, the court stated in paragraph 3 of the pretrial order as follows:

*668 "3. The issues concerning defective color coding and water pumps are between Eastpoint Water and Parker's Mechanical. The issues on the allegedly defective manhole covers will involve the question of whether the manhole covers manufactured by Sonoco and furnished by Technical Marketing Corporation were not in accordance with specifications. If the manhole covers are found inadequate on the claim of Eastpoint Water and Sewer, the trial will then become whether this is the responsibility of the contractor, the supplier or the manufacturer. The question of inadequate manhole covers will be resolved subsequent to the issues on color codes and water and sewer pumps."

None of the parties took exception or objected to these pretrial findings of the trial court.

Trial was had before the court without jury, and after the evidence was heard, the court granted Parker's motion for directed verdict as to the pump claim, holding that the pumps had a design defect that was not Parker's fault, but denied Parker's motion for directed verdict as to the vault covers. Then the court entered final judgment in favor of Parker in the amount of $122,686.73 against the District, which was the full principal amount claimed by Parker in its cross-claim against the District which was filed October 13, 1976, but the court denied Parker's claim for prejudgment interest on the ground that the amount of Parker's claim was not liquidated but was uncertain at the time of Parker's final billing on June 21, 1976. It is from this denial of prejudgment interest that Parker appeals.

The point on the appeal of Parker is whether the court erred in denying Parker prejudgment interest on the ground that its bill was not liquidated and certain.

In this connection the record discloses that the general contract between Parker and the District provided that the District was obligated to make payment to Parker of the balance due on the contract price within 30 days of completion and acceptance of the work by the District and that in the event of the District's failure to make such payment within said time, interest at the maximum legal rate would be added to said balance to run from the end of said 30-day period and to continue until payment is received by Parker.

The contract also provided that Parker would save the District harmless from all claims growing out of the lawful demands of subcontractors, laborers and materialmen, and upon the demand of the District would furnish to it satisfactory proof that all such claims have been paid, discharged, or waived; that if Parker failed to do so, the District may withhold from Parker's unpaid compensation a sum of money deemed reasonably sufficient to pay all such lawful claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chadwick v. Corbin
476 So. 2d 1366 (District Court of Appeal of Florida, 1985)
Dade County v. American Re-Ins. Co.
467 So. 2d 414 (District Court of Appeal of Florida, 1985)
Warren v. Old Dominion Ins. Co.
465 So. 2d 1376 (District Court of Appeal of Florida, 1985)
United States v. Commercial Construction Corp.
741 F.2d 326 (Eleventh Circuit, 1984)
United States v. Commercial Construction Corporation
741 F.2d 326 (Eleventh Circuit, 1984)
Chicago Insurance Co. v. Argonaut Insurance Co.
451 So. 2d 876 (District Court of Appeal of Florida, 1984)
Brooks v. SCHOOL BD. OF BREVARD CTY.
419 So. 2d 659 (District Court of Appeal of Florida, 1982)
Posner v. Flink
393 So. 2d 1140 (District Court of Appeal of Florida, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
367 So. 2d 665, 1979 Fla. App. LEXIS 14152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parkers-mechanical-contr-inc-v-eastpoint-water-sewer-dist-fladistctapp-1979.