Andrews, C. J.
The plaintiff’s cause of action was founded on the order contained in a letter from the defendants, as follows: —
“ Cobalt, Dec. 21st, 1893.
“ R. L. Parker, Esq.,
“ Dear Sir: Please cut out and have ready for spring shipment the following order:
“ 3,000 Horse R. R. ties, hewed 7 ft. long, 5 in. thick, and 5 in. face, @ .14 each, to be 2/3 chestnut and 1/3 oak.
“ 1,500 8 ft. chestnut posts @ 8 cts.
“ 2,000 10 ft. “ “ @ 10 cts.
“1,500 12 ft. “ “ @15 cts.
“ These to be of live timber, and to be from 4 to 6 in. at top end.
“400 cords clear oak wood @ $3.75.
“ 100 “ chestnut “ @ $2.50.
[548]*548“ 3,000 ft. 8 ft. 4 X 4 chestnut.
“ 3,000 ft. 10 ft. “
“ 4,000 ft. 12 ft. “ “ @ 18.00
“ All of the above order to be delivered over the rail of a vessel.
“Yours truly,
“ John Selden & Son.”
The complaint, after mentioning the order and alleging that the plaintiff received and accepted it, says: “ (3) Defendants did not take said wood and timber as agreed, but neglected and refused to take or pay for the same, except as is hereinafter stated. (4) Defendants did not take any of said timber or wood until a long time after the same was ordered to be ready, and what they have taken has been taken in small quantities and at long intervals between July of 1894 and July of 1895. (5) The following wood mentioned in said order has never been taken or paid for by the defendants, to wit: 1,200 horse ties, 300 cords of oak wood, 100 cords of chestnut wood, 4,000 feet of 4 by 4 chestnut sticks. (6) Plaintiff has been to great trouble and expense in cutting and carting said wood, and a large amount of horse ties and oak wood, which had been placed on the dock at the request of the defendants, ready for shipment, was, in consequence of the neglect of the defendants to send a vessel for the same for several months thereafter, carried away by the high tides and wholly lost; and defendants have called for the shipment of the different loads of wood taken by them at inconvenient times, many months after they should have taken the same, and thereby caused great expense to the plaintiff.”
The answer of the defendants admits the sending the said order and its acceptance by the plaintiff; and then goes on to say: “ (3) As to paragraphs three and four the defendants answer and say that they did not refuse to take the wood and timber as agreed, and that they took all thereof that the plaintiff had ready for spring shipment in compliance with said order, and paid the plaintiff therefor; but [549]*549that the plaintiff failed to have ready for spring shipment a large quantity of the wood and timber called for in said order. . . . (4) As to paragraph five the defendants answer and say that they did not take any of the wood therein mentioned, because the plaintiff did not have it ready for shipment as called for in said order. (5) Paragraph six is denied.”
These pleadings reduced the controversy of the parties substantially to this: What period of time was included within the expression “spring shipment”? The court found the issue for the defendants, and the plaintiff appeals.
The finding of facts is as follows: “ 1. Immediately after the acceptance of the order by the plaintiff, he began to cut the wood and timber therein mentioned, and before spring opened had a large quantity of the posts, ties, and wood piled upon the wharf at Guilford, so as to be ready for delivery upon boats when sent for the same. 2. On April 2d, 1894, the defendants sent the plaintiff two letters of that date.
Free access — add to your briefcase to read the full text and ask questions with AI
Andrews, C. J.
The plaintiff’s cause of action was founded on the order contained in a letter from the defendants, as follows: —
“ Cobalt, Dec. 21st, 1893.
“ R. L. Parker, Esq.,
“ Dear Sir: Please cut out and have ready for spring shipment the following order:
“ 3,000 Horse R. R. ties, hewed 7 ft. long, 5 in. thick, and 5 in. face, @ .14 each, to be 2/3 chestnut and 1/3 oak.
“ 1,500 8 ft. chestnut posts @ 8 cts.
“ 2,000 10 ft. “ “ @ 10 cts.
“1,500 12 ft. “ “ @15 cts.
“ These to be of live timber, and to be from 4 to 6 in. at top end.
“400 cords clear oak wood @ $3.75.
“ 100 “ chestnut “ @ $2.50.
[548]*548“ 3,000 ft. 8 ft. 4 X 4 chestnut.
“ 3,000 ft. 10 ft. “
“ 4,000 ft. 12 ft. “ “ @ 18.00
“ All of the above order to be delivered over the rail of a vessel.
“Yours truly,
“ John Selden & Son.”
The complaint, after mentioning the order and alleging that the plaintiff received and accepted it, says: “ (3) Defendants did not take said wood and timber as agreed, but neglected and refused to take or pay for the same, except as is hereinafter stated. (4) Defendants did not take any of said timber or wood until a long time after the same was ordered to be ready, and what they have taken has been taken in small quantities and at long intervals between July of 1894 and July of 1895. (5) The following wood mentioned in said order has never been taken or paid for by the defendants, to wit: 1,200 horse ties, 300 cords of oak wood, 100 cords of chestnut wood, 4,000 feet of 4 by 4 chestnut sticks. (6) Plaintiff has been to great trouble and expense in cutting and carting said wood, and a large amount of horse ties and oak wood, which had been placed on the dock at the request of the defendants, ready for shipment, was, in consequence of the neglect of the defendants to send a vessel for the same for several months thereafter, carried away by the high tides and wholly lost; and defendants have called for the shipment of the different loads of wood taken by them at inconvenient times, many months after they should have taken the same, and thereby caused great expense to the plaintiff.”
The answer of the defendants admits the sending the said order and its acceptance by the plaintiff; and then goes on to say: “ (3) As to paragraphs three and four the defendants answer and say that they did not refuse to take the wood and timber as agreed, and that they took all thereof that the plaintiff had ready for spring shipment in compliance with said order, and paid the plaintiff therefor; but [549]*549that the plaintiff failed to have ready for spring shipment a large quantity of the wood and timber called for in said order. . . . (4) As to paragraph five the defendants answer and say that they did not take any of the wood therein mentioned, because the plaintiff did not have it ready for shipment as called for in said order. (5) Paragraph six is denied.”
These pleadings reduced the controversy of the parties substantially to this: What period of time was included within the expression “spring shipment”? The court found the issue for the defendants, and the plaintiff appeals.
The finding of facts is as follows: “ 1. Immediately after the acceptance of the order by the plaintiff, he began to cut the wood and timber therein mentioned, and before spring opened had a large quantity of the posts, ties, and wood piled upon the wharf at Guilford, so as to be ready for delivery upon boats when sent for the same. 2. On April 2d, 1894, the defendants sent the plaintiff two letters of that date.
The order fixed no time or times when the wood and timber was to be delivered to the defendants and paid for by them. It was therefore deliverable over the rail of such vessel as the defendant, on reasonable notice, should send to receive it. The title, therefore, remained, so long as the wood was on the dock, in the plaintiff. And so the loss of that which was carried away by the tide fell on him. This happened about the 11th day of April, 1894. There is no averment in the complaint that the defendants were remiss in sending a vessel at that time.
Every other item in respect to which the plaintiff claimed to recover damages, was for something which happened after July 1st, 1894. If the period for “spring shipment” named in the order, did not extend beyond the 1st day of July, 1894, the defendants could not be made liable for these items under [552]*552the order. It was for this reason that the plaintiff claimed that by “ spring shipment ” in the order, was meant a period extending through the summer of 1894. This expression might be held to mean just what the calendar names as the spring months, viz, March, April and May; or there might be given to it a somewhat more popular meaning, as the period when vegetation begins to put forth, extending in this latitude from about the middle of March to about the middle of June. But there is no meaning which can be given to it which, as matter of law, could make it extend beyond the 1st of July.
It was undoubtedly competent for the plaintiff to show by evidence that this expression had in this business the meaning which he claimed for it; Smith v. Phipps, 65 Conn. 302; or that it was used by the parties in this contract with that meaning. In re Curtis-Castle Arbitration, 64 Conn. 501. The plaintiff offered no evidence to prove either of these conditions, and offered no evidence to show that it had such meaning.
The plaintiff did offer evidence which he claimed would prove that the parties—defendants and plaintiff—had by their conduct extended the period of “spring shipment” so as to include the whole season of 1894. This evidence was objected to and ruled out. We think this ruling was correct. It sought to' prove a contract different from the one alleged. The contract alleged was in writing; this was an attempt to prove a parol one. The contract alleged could not extend beyond the 1st of July, 1894. The one sought to be proved extended from July, 1894, to July, 1895. It appears then, that for all the Wood and timber which the plaintiff furnished to the defendants pursuant to the contract he has alleged, he has been paid.
There is no error.
In this opinion the other judges concurred; except Hameesley, J., who dissented.
Cobalt, Conn., Apr. 2d, 1894.
Ralph Pabkeb, Esq. Dear Sir: Boat will be in Guilford Wednesday or Thursday to load posts. Can you get us 1,000 ft. of white oak, sawed through and through 12 ft. long, li and 2 in. thick. This must be butt cuts and nice lumber. Want it to go on this boat.
Tours truly, John H. Selden & Son.
P. S.—How much water is there at Guilford ?