Parker v. Salo

30 Mass. L. Rptr. 567
CourtMassachusetts Superior Court
DecidedDecember 24, 2012
DocketNo. WOCV200902145
StatusPublished

This text of 30 Mass. L. Rptr. 567 (Parker v. Salo) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker v. Salo, 30 Mass. L. Rptr. 567 (Mass. Ct. App. 2012).

Opinion

Ferrara, John S., J.

On September 11, 2009, the plaintiffs, Gregg C. Parker (“Parker”) and Rekrap Realty, LLC (“Rekrap”), brought this action against the defendants, Wayne Salo (“Salo”) and Dixon-Salo Architects, Inc. The plaintiffs seek to recover on eight counts in contract and tort regarding services rendered to them by the defendants for the construction of a commercial building.

The defendants now move for summary judgment pursuant to Mass.R.Civ.P. 56. For the reasons set forth below, the defendants’ motion for summary judgment will be ALLOWED in part and DENIED in part.

BACKGROUND

The facts taken in the light most favorable to the non-moving party, the plaintiffs, are as follows.

Parker is an insurance and financial services agent operating as a sole proprietorship, Robert A. Parker Insurance and Financial Services and/or Rekrap. The businesses are run out of an office in Whitinsville, Massachusetts. Prior to the events detailed herein, Parker and his businesses operated from an old Victorian house on Church Street in Whitinsville. In or around 2005, Parker began exploring options for upgrading or changing his office space, including whether to relocate his offices into a new or existing building or to raze his Church Street building and replace it with a new building. Parker originally wanted simply to put a modular office building on the existing site, but learned that due to town permitting, he would need to retain an architect to do so. Parker had already obtained estimates of $522,430 and $350,000 from two modular building firms.

In July 2005, Parker contacted Salo, an architect with the firm Dixon-Salo Architects, Inc. At some point in 2005, Parker and Salo entered into some form of agreement for Salo to provide schematic design, design development, construction document, pricing, and construction services to Parker. Salo presented a written contract for such services to Parker, which Parker did not sign because he objected to certain terms in the document. Despite Parker’s failure to sign the written contract, Salo continued to perform services for Parker and Rekrap, and Parker rendered various payments for these services.

Between July 2005 and August 2006, Parker sought and obtained various zoning approvals for a new building. During this period, Parker was still exploring options other than constructing a new building on his own site. Once the zoning permissions were in place, Parker, using a bid package prepared by Salo, began soliciting construction bids based on preliminary plans prepared by Salo. Three firms were solicited and two submitted bids. The first, Elite Custom Homes, bid $656,820 as a flat lump sum bid. Salmon’s Contracting (“Salmon”) submitted a “rough” bid estimate of approximately $586,940 on a cost-plus basis, meaning that the owner pays the contractor the cost of time and materials, plus a percentage of that for profit. In this case, the percentage profit was five percent, such that had the estimate been correct, the five percent fee would have been $29,347, and the total cost to Parker $616,287. The price identified in a cost-plus bid is an estimate, subject to change based upon field conditions, change orders, additions and deletions by the owner, and other factors. Parker retained Salmon, the low bidder, and entered into the proffered contract. Parker based his decision in part on the advice of Salo, who had recommended Salmon. Salo and Salmon had a pre-existing relationship, and Salo assured Parker that the project could be completed for the cost quoted by Salmon. In accepting Salmon’s contract, Parker abandoned a chance to buy a nearby building for $500,000, as well as the chance to have Elite construct his building for the flat fee of $656,820.

At some point between the bid and December 16, 2006, when demolition of Parker’s existing building took place, Salo and/or Salmon revised the projected cost of the building to $650,000. However, Parker did [568]*568not learn of this until after the demolition, when he saw the new figure in a document sent to him by Salo. In June 2007, Parker learned the projected construction budget had grown to $780,988.88. He called for a meeting and met with Salo, Salmon, and the site contractor to discuss ways to reduce the cost of the building.

At various points during construction, Salo issued certifications for payment to the contractor. These were based on its certification that the work in question had been adequately completed. By the time the work was completed, the project had cost almost $750,000.

After the project, Salmon filed suit against Robert A. Parker Insurance and Financial Services for an unpaid balance. The insurance firm counterclaimed. The dispute, pursuant to Parker’s contract with Salmon, was submitted to binding arbitration. At some point the pleadings were amended with Parker and Rekrap being substituted for Robert A. Parker Insurance. The arbitrator awarded certain unpaid fees from Parker to Salmon, and awarded a larger offset payment from Salmon to Parker for portions of the work that were insufficiently or inadequately complete and for overbilling.

DISCUSSION

Summary judgment is appropriate if the pleadings, depositions, answers to interrogatories, and responses to requests for admissions under Rule 36, together with the affidavits show that there is no genuine issue of material fact and that the moving parly is entitled to judgment as a matter of law. Mass.R.Civ.P. 56(c); Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989); Cassesso v. Commissioner of Corr., 390 Mass. 419, 422 (1983). The moving party bears the burden of affirmatively demonstrating the absence of a triable issue and that the summary judgment record entitles the moving party to judgment as matter of law. Pederson, 404 Mass. at 16-17. The moving party may satisfy this burden either by submitting affirmative evidence that negates an essential element of the opposing party’s case, or by demonstrating that the opposing party will not reasonably be able to prove an essential element of his case. Flesner v. Technical Commc’ns Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors, 410 Mass. 706, 716 (1991).

Once the moving party establishes the absence of a triable issue, the party opposing the motion must respond and allege specific facts which would establish the existence of a genuine issue of material fact for trial. Mass.R.Civ.P. 56(e); Pederson, 404 Mass. at 17. The court reviews the evidence in the light most favorable to the nonmoving party, but does not weigh evidence, assess credibility, or find facts. Attorney Gen. v. Bailey, 386 Mass. 367, 370-71 (1982).

I.The Standing Defense

Salo and Dixon-Salo Architects, Inc., claim plaintiffs Parker and Rekrap have no standing to pursue claims against the defendants because neither plaintiff was involved in any contract or business relationship with Salo or his firm. Rather, the defendants argue, Salo and his firm were engaged in a transaction with Robert A. Parker Insurance. It is undisputed that Parker is an individual doing business as Robert A. Parker Insurance and Financial Services and/or Rekrap Realty. Further, it is undisputed that he conveyed the property that is the subject of this matter to Rekrap, in January 2007, during the period in which this transaction was ongoing. Further, all of Salo’s negotiations and business dealings regarding the subject properly were with Parker. Therefore, the plaintiffs are appropriate parties.

II.The Collateral Estoppel Defense

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry S. Bloomgarden v. Charles B. Coyer
479 F.2d 201 (D.C. Circuit, 1973)
Bailey v. Metropolitan Property & Liability Insurance
505 N.E.2d 908 (Massachusetts Appeals Court, 1987)
Druker v. Roland Wm. Jutras Associates, Inc.
348 N.E.2d 763 (Massachusetts Supreme Judicial Court, 1976)
PMP Associates, Inc. v. Globe Newspaper Co.
321 N.E.2d 915 (Massachusetts Supreme Judicial Court, 1975)
Nei v. Burley
446 N.E.2d 674 (Massachusetts Supreme Judicial Court, 1983)
Raimondo v. Town of Burlingon
319 N.E.2d 895 (Massachusetts Supreme Judicial Court, 1974)
Stock v. Fife
430 N.E.2d 845 (Massachusetts Appeals Court, 1982)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Salamon v. Terra
477 N.E.2d 1029 (Massachusetts Supreme Judicial Court, 1985)
Attorney General v. Bailey
436 N.E.2d 139 (Massachusetts Supreme Judicial Court, 1982)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Flesner v. Technical Communications Corp.
575 N.E.2d 1107 (Massachusetts Supreme Judicial Court, 1991)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Home Owners Federal Savings & Loan Ass'n v. Northwestern Fire & Marine Insurance
238 N.E.2d 55 (Massachusetts Supreme Judicial Court, 1968)
Payton v. Abbott Labs
437 N.E.2d 171 (Massachusetts Supreme Judicial Court, 1982)
Warner Insurance v. Commissioner of Insurance
548 N.E.2d 188 (Massachusetts Supreme Judicial Court, 1990)
Sullivan v. Boston Gas Co.
605 N.E.2d 805 (Massachusetts Supreme Judicial Court, 1993)
Novel Iron Works, Inc. v. Wexler Construction Co.
528 N.E.2d 142 (Massachusetts Appeals Court, 1988)
Hogan v. Riemer
619 N.E.2d 984 (Massachusetts Appeals Court, 1993)
Miles v. Aetna Casualty & Surety Co.
589 N.E.2d 314 (Massachusetts Supreme Judicial Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
30 Mass. L. Rptr. 567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-v-salo-masssuperct-2012.