Parker v. Northwestern Investment Co.

255 P. 307, 44 Idaho 68, 1927 Ida. LEXIS 59
CourtIdaho Supreme Court
DecidedMarch 28, 1927
DocketNo. 4455.
StatusPublished
Cited by9 cases

This text of 255 P. 307 (Parker v. Northwestern Investment Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker v. Northwestern Investment Co., 255 P. 307, 44 Idaho 68, 1927 Ida. LEXIS 59 (Idaho 1927).

Opinion

*71 GIVENS, J.

Appellants Pleasants, husband and wife, were the owners of certain land which they contracted to sell to the appellant Northwestern Investment Company under an escrow agreement. Roy Parker and W. C. Bosley, respondents, after consulting with Mr. Pleasants as to the standing of the Northwestern Investment Company, entered into a contract with the Northwestern Investment Company for grading and leveling the streets of the land sold by the Pleasants to the Northwestern Investment Company which had been platted into lots and blocks. Respondent, Joseph A. Rivett, was employed by Parker and Bosley to do some of the grading and leveling. Rivett not being paid, within the time allowed by law, filed his claim of lien against the land and commenced foreclosure. Parker and Bosley were thereafter notified to quit the job and filed their claims of lien and commenced foreclosure. The Pleasants alone appeared and demurred to the Parker-Bosley complaint and ;hereafter answered to both complaints. The actions were ionsolidated and tried by the court without a jury and judgment was rendered in favor of respondents in both actions and this appeal taken.

The main question involved is whether respondents were entitled to liens upon the lands, superior to and enforceable against the rights of appellants.

It is appellants’ contention under C. S., see. 7343 (providing that any person who, at the request of the owner of any lot in any incorporated city or town, grades, fills in or otherwise improves the same, or the street in front of or adjoining the same has a lien on such lot for the work done or material furnished), since appellants hold the record title and the Northwestern Investment Company had only a contract for the purchase of the land and respondents performed the work at the request of the Northwestern Investment Company, that respondents are not entitled to liens against appellants because it was not shown that appellants requested them to do the work.

*72 Paragraph four of the contract between the Pleasants and the Northwestern Investment Company, covering the work which was done by the respondents, provided as follows:

“The party of the second part declares its intention to place the lots represented by said plat on sale under certain restrictions and under contracts of sale providing for certain improvements, of not less than $20,000 on the project, the character of which shall be later determined by it. The parties of the first part represent that they own certain other contiguous ground now platted into lots and blocks, and agree that the lots therein shall not be sold by them except as subject to the same building restrictions, and restrictions as to negroes, chinamen, etc., as used by the party of the second part in selling its lots, and also that they will not sell their lots at less than $400 for a 50 foot front exclusive of improvements, during the time that the second parties are engaged in selling its lots or collecting therefor, or for a period of three years.”

C. S., sec. 7343, provides that to authorize a lien, the work must have been done at the request of the owner. The complaint alleged in paragraph 7 that:

“That at the date of said agreement and during the time said work was performed, the said defendants, Frances A. Pleasants and William A. Pleasants, were the persons in whose name the record title to said property was vested, and that the said Frances A. Pleasants and William A. Pleasants, had contracted and agreed to sell said premises to the said defendant, Northwestern Investment Company, and in said agreement had consented and agreed that said work and labor might be performed as aforesaid, and in said contract authorized the said Northwestern Investment Company to have the said streets leveled and improved as aforesaid; that during said time the said Northwestern Investment Company was the owner and reputed owner of said premises and caused said work and labor to be performed as aforesaid.”

It was not disputed that the title to the property was in the Pleasants and that they had agreed to sell the premises to the Northwestern Investment Company and that *73 they had consented, as appears in paragraph four of the contract, that improvements might be placed upon the land. The nature of the improvements was not stated in the contract and it was expressly reserved that the Northwestern Investment Company should later determine what they should be. Likewise, there is no question that the Northwestern Investment Company was not the owner of the land, no payments excepting the initial 'payment having been made by it, and even if it had been the reputed owner that would not avail respondent, because the reputed owner, as such, would have no right to do anything which would give a lien upon the premises. (Santa Cruz Rock Pavement Co. v. Lyon, 117 Cal. 212, 54 Am. St. 174, 48 Pac. 1097.)

If by the word “authorized” in paragraph seven of the complaint the pleader meant that the Northwestern Investment Company was the agent of appellants to do the work or that the Northwestern Investment Company was obligated to do this work, such meaning is contrary to the terms and nature of the contract which was one of sale, and the contract itself did not provide specifically that the improvements would be made by the Northwestern Investment Company, it being stated that the Northwestern Investment Company declared its intention to place the lots on sale under certain restrictions, presumably from the context, building or residence restrictions, and under ‘ ‘ contracts of sale providing for certain improvements, of not less than $20,000 on the project.” The language used is not free from doubt as to whether these improvements were to be made by the Northwestern Investment Company, or by the purchasers of the individual lots. Granting that these improvements were to be made by the Northwestern Investment Company, it was not obligated so to do; it merely expressed its intention to do so, from the context of the contract having appellants’ permission. No time limit was specified within which these improvements should be made and their nature was left entirely to the discretion of the Northwestern Investment Company.

*74 The contention that these improvements furnished the consideration for the stipulation by appellants that they would observe the same building and sale restrictions in disposing of their property which lay adjacent to that sold to the Northwestern Investment Company is not tenable, because if the Northwestern Investment Company had made its payments to appellants and had sold no lots or made no improvements there would have 'been no obligation resting upon it to make the improvements mentioned nor could appellants have forced the Northwestern Investment Company to make such improvements.

The complaint does not allege that the improvements made were of any value to appellants nor does it allege that they are estopped to resist the imposition of a lien upon their property. Numerous authorities may be found which hold that where the owner has consented to the construction of improvements the owner will be bound. It will be found, however, that such cases are based upon a statute different from ours and where request or permission

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steffa v. Steffa
Idaho Court of Appeals, 2019
Idaho Lumber, Inc. v. Buck
710 P.2d 647 (Idaho Court of Appeals, 1985)
Fulton v. Duro
687 P.2d 1367 (Idaho Court of Appeals, 1984)
Christensen v. Idaho Land Developers, Inc.
660 P.2d 70 (Idaho Court of Appeals, 1983)
Poynter v. Fargo
281 P. 1111 (Idaho Supreme Court, 1929)
Gem State Lumber Co. v. Union Grain & Elevator Co.
278 P. 775 (Idaho Supreme Court, 1929)
Boise Payette Lumber Co. v. Sharp
264 P. 665 (Idaho Supreme Court, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
255 P. 307, 44 Idaho 68, 1927 Ida. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-v-northwestern-investment-co-idaho-1927.