Parker v. Newmark Homes, Inc.

2013 Ohio 4402
CourtOhio Court of Appeals
DecidedOctober 4, 2013
Docket25686
StatusPublished
Cited by2 cases

This text of 2013 Ohio 4402 (Parker v. Newmark Homes, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker v. Newmark Homes, Inc., 2013 Ohio 4402 (Ohio Ct. App. 2013).

Opinion

[Cite as Parker v. Newmark Homes, Inc., 2013-Ohio-4402.]

IN THE COURT OF APPEALS OF OHIO SECOND APPELLATE DISTRICT MONTGOMERY COUNTY

HUNTER D. PARKER

Plaintiff-Appellant

v.

NEWMARK HOMES, INC.

Defendant-Appellee

Appellate Case No. 25686

Trial Court Case No. 2012-CVF-00358

(Civil Appeal from Municipal Court) ( ...........

OPINION

Rendered on the 4th day of October, 2013.

...........

CHAD E. BURTON, Atty. Reg. No. 0078014, 70 Birch Alley, Suite 240, Beavercreek, Ohio 45440 Attorney for Plaintiff-Appellant

PAUL M. COURTNEY, Atty. Reg. No. 0020085, 3333 Stonequarry Road, Dayton, Ohio 45414 Attorney for Defendant-Appellee

.............

WELBAUM, J. 2

{¶ 1} Plaintiff-Appellant, Hunter Parker, appeals from a judgment rendered in favor

of Defendant-Appellee, Newmark Homes, Inc., following a bench trial. Parker contends that the

trial court erred in ruling that he failed to file his action within the applicable statute of

limitations.

{¶ 2} We conclude that the trial court did not err in holding that Parker failed to

comply with the applicable statute of limitations. The record contains competent, credible

evidence indicating that Parker knew of the defect giving rise to his cause of action more than six

years before the action was filed. The action, therefore, was untimely under either R.C.

2305.09(D) or R.C. 2305.07. Accordingly, the judgment of the trial court will be affirmed.

I. Facts and Course of Proceedings

{¶ 3} In February 2011, Parker filed a complaint against Newmark Homes, Inc.

(Newmark), alleging that Newmark had failed to properly construct a retaining wall located on

Parker’s property. The action was dismissed without prejudice and was then refiled in February

2012. Parker’s complaint contained claims for breach of contract and failure to perform

construction and installation of the retaining wall in a workmanlike fashion.

{¶ 4} Ultimately, a bench trial was held before a magistrate, who heard testimony

from Parker and from Greg Barney, the President and owner of Newmark. The magistrate also

admitted the deposition testimony of a witness, Russ Harris, who had been subpoenaed, but had

failed to appear for trial.

{¶ 5} The testimony indicated that Newmark had constructed a home for Parker and

his wife in 2002. The house was located at 770 Deer Creek Dr., Vandalia, Ohio, and Parker was 3

satisfied with the home’s construction. However, the lot was not level, and Newmark agreed to

construct a retaining wall at the back of the property. The wall was to be 4'8" high and 90' long,

and the wall was to be constructed with Keystone Intermediate blocks. The foundation of the

wall was to be compacted gravel, with a backfill of limestone “57s” up to one foot in depth

behind the wall.

{¶ 6} After installing the retaining wall, Newmark invoiced Parker $6,788 on July 1,

2002, and Parker paid Newmark that amount. Subsequently, in 2004, Parker concluded that the

wall was beginning to bulge and look a bit unstable on the west half, so he asked Greg Barney to

come out and look at the wall. Barney agreed to repair the wall, and did not charge Parker for

the repair. Barney brought out his own equipment – a track hoe and a Bobcat – and also hired

Harris Seed & Sod to provide laborers. Harris had previously installed the sod when Parker’s

home was constructed.

{¶ 7} In 2004, about 50 feet of the wall was torn down. There was a dispute in

testimony regarding precisely how much work was done. Russ Harris, the owner of Harris Seed

& Sod, testified via deposition that when part of the original wall was removed in 2004, the base

of the wall did not contain as much base as he would have used. Harris also stated that the

drainage tile was not draining properly, that less 57s were used than he would normally use, and

that there was mud mixed in with the 57s, which could affect the ability of water to percolate.

According to Harris, they tore the wall down to the base, took out all the base and block, put a

new base in, put drainage tile behind the wall for drainage, added more 57s and gravel for extra

drainage, and built the wall back up.

{¶ 8} Barney testified that they unstacked the blocks in the wall, but did not get into 4

the base. They re-stacked the base, reinserted the drain tile and backfill, and restored the yard.

Barney paid Harris $845 for labor, and had other expense that was not significant, including

about $100 to $200 for a load of gravel and a section of pipe.

{¶ 9} Several years later, in 2010, Parker asked Harris for a quote to repair the eastern

part of the wall, which was leaning away from the yard, instead of toward the yard. Parker did

not call Newmark or Barney about the problem. Both Parker and Harris testified that Parker

asked Harris to contact Barney, and that Harris did so before beginning work. According to

Harris, Barney stated that he was not responsible for repairing the wall because it was outside the

warranty time on the house. In contrast, Barney testified that no one contacted him before the

repairs were made.

{¶ 10} In early August 2010, Harris invoiced Parker in the amount of $7,800 for

repairing the wall. This price included $1,500 for tearing down the old wall, $4,500 for

rebuilding the wall, $800 for Bobcat and track hoe charges, and $100 for installing new tile

behind the retaining wall and drilling into a concrete pipe. $900 of this amount was for new

caps, which were not part of the repair. Parker also incurred about $597 in charges for replacing

the landscaping.

{¶ 11} The work for this repair was similar to what had been done in 2004. Harris

was able to reuse the original blocks that had been installed in 2002, and did not have to purchase

more block.

{¶ 12} On August 5, 2010, Parker left a voice mail with Barney, requesting payment

for repairs that had been made to the wall. On August 9, 2010, Parker sent Barney a letter,

requesting $6,900 for the cost of having the eastern part of the wall rebuilt. In the letter, Parker 5

stated that:

When the wall was repaired/re-built in 2005, also by Harris Sod & Seed,

several deficiencies were discovered including: insufficient base (less than 4

inches); improper drainage (no drain or no way for the drain to empty); no

Geogrid (recommended/required on all walls with a height above 4 feet) and dirty

or insufficient gravel backfill. Only one half of the wall was repaired/rebuilt at

that time.

The east side of the wall (east of the culvert/drain pipe) was quickly

becoming unstable. It was bulging out approximately 2 feet and the top layer was

severely tilted. It was not a question of if it would fail only when it would fail.

The top course of block was above or slightly beyond the bottom course of block.

I took pictures of the work as it was being completed and also of the wall

prior to the start of the tear-down and re-building of the wall. As you might

guess the following was discovered during this process: there was no Geogrid

behind the wall; the gravel back fill was a mixture of mud and gravel (not

allowing for proper drainage) and there was no drain tile in this portion of the

wall. These were the primary reasons for the failing of the wall and fairly

consistent with the issues uncovered during the tear down and rebuilding of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Bates
2025 Ohio 1679 (Ohio Court of Appeals, 2025)
Anderson v. Clark
2021 Ohio 1210 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2013 Ohio 4402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-v-newmark-homes-inc-ohioctapp-2013.