Parker v. McGilway

7 La. 192
Supreme Court of Louisiana·Decided April 15, 1844·Published·Cited by 2 cases

Opinion

Garland, J.

The plaintiff alleges, that in the month of June, 1841, he entered into a contract with McGilway, to build two dwelling houses in Dauphine street, of a certain height and dimensions, which were to be completed in a workmanlike manner, on or before the 15th of October in the same year; for which he was to pay the sum of $15,000, in different instalments. The [193] first, of $3000, he avers that he has paid. The others, he alleges he is not liable to pay, as the contract has not been complied with, and the said McGilway is unable to perform it, and has neglected or refused to do so. He avers, that he has called upon him to give up the contract, so that he may employ some other person to complete the houses, but that McGilway refuses either to do so, or to complete the undertaking. He, therefore, prays, that a writ may be issued, to put him in possession of the premises ; that the contract may be annulled; and that he may recover $10,000 damages. He also prays, that as John Walker and Lawrence Gurvey are the sureties of McGilway, for the faithful compliance with his contract, they may be made parties, and that he may have judgment against them. He further avers, that it has been supposed that he owes the second instalment of $2800, which is not true ; and that he has in consequence been sued, in conjunction with McGilway, for materials furnished him by Newton Richards, and Forstall, Roman & Go. He therefore prays, that they also may be made parties, and their claims, as against him, dismissed.

The defendant, McGilway, after a general denial of such allegations as are not specially admitted, answers, that he did enter into the contract annexed to the petition, and was going on to execute it, and had made considerable progress in so doing, when he was interrupted by the plaintiff, who ordered him and his workmen away from the premises, threatening to imprison them, and endeavored to take possession thereof, and finally obtained an injunction to arrest his proceedings, which he got dissolved after much trouble and delay; and that he otherwise interrupted him in his efforts to complete the contract. He further avers, that by the conduct of the plaintiff, and his misrepresentations as to the unwillingness and inability of the defendant to comply with the contract, he (defendant) has suffered heavy damages, by loss of credit, and has also lost a large amount of the profits he expected to make. He further alleges, that he has done a great deal more work on the buildings than the plaintiff has paid him for, in consequence of all which, he is entitled to claim of him the sum of $15,000, which he does by a demand in reconvention.

The two sureties of the defendant answered by a general de[194] nial; and claim to be discharged in consequence of the course pursued by the plaintiff towards McGilway, whose grounds of defence they adopt. Roman, Forstall & Co. aver, that they have a judgment against McGilway for materials and supplies furnished to enable him to construct the buildings, which cannot be affected or annulled by this proceeding. The other defendant, Richards, filed no answer at all.

The building contract was given in evidence. It details specially the work to be executed, and states, that the undertaker is to furnish the materials of every description, do all the work, and have the whole establishment completed on or before the 15th of October, 1841, ready for delivery ; and if not then ready, McGilway stipulates to pay a rent of $200 per mouth, until the houses are completed, and also binds himself in a penalty of $10,000, to comply with all his obligations. There are many stipulations not necessary to mention, but the houses were to have a depth of forly-one feet in the clear, and the two first stories to be thirteen feet in height between the floor and joists : the price to be $15,000, payable in several instalments; and there is a clause which stipulates, that in case of difficulty between the parties, or if from any cause the progress of the buildings be threatened with delay, the plaintiff shall have the faculty of taking immediate possession of them and continuing the work, without prejudice to the eventual rights of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Parker v. McGilway, 7 La. 192 (La. 1844).

7 La. 192 (Parker v. McGilway) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pratt v. Craft
70 La. Ann. 130 (Supreme Court of Louisiana, 1867)
Davis v. Spurlock
3 La. Ann. 208 (Supreme Court of Louisiana, 1848)