Parker v. Hegler, Unpublished Decision (12-11-2006)

2006 Ohio 6495
CourtOhio Court of Appeals
DecidedDecember 11, 2006
DocketCase No. 2006-L-062.
StatusUnpublished
Cited by1 cases

This text of 2006 Ohio 6495 (Parker v. Hegler, Unpublished Decision (12-11-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker v. Hegler, Unpublished Decision (12-11-2006), 2006 Ohio 6495 (Ohio Ct. App. 2006).

Opinions

OPINION
{¶ 1} Appellants, Steve Parker and Terri Parker (collectively referred to as "the Parkers"), appeal from a judgment of the Lake County Common Pleas Court that awarded them judgment in the amount of $29,002.31 for damages sustained to their property. On review, we reverse the judgment of the trial court and remand this matter to the trial court.

{¶ 2} The Parkers own lakefront property at 37371 Lakeshore Boulevard, Eastlake, Ohio. Their property is adjacent to residential property owned by Gary and Lou Ann Hegler (collectively referred to as "the Heglers") at 37337 Lakeshore Boulevard, Eastlake, Ohio. The Heglers' parcel is immediately to the west of the Parkers' parcel. The Parkers' property and the Heglers' property each have approximately 100 feet of frontage on Lake Erie. The yard elevations for both parcels are approximately 25 to 30 feet above the normal lake level.

{¶ 3} In 2000, the Heglers undertook a road construction project, wherein they excavated on their property and constructed a road to the lake. The road was constructed in a northerly direction from the Heglers' house and, on the easterly side, extended approximately ten feet from the Parkers' property line. The Heglers constructed a retaining wall system extending the entire length of the roadway. At the base of the roadway, on the beachfront, the Heglers installed a series of concrete blocks that were each three cubic feet in order to offer some protection against shoreline erosion.

{¶ 4} In June 2003, the Parkers sued the Heglers for damages, because the construction of the road by the Heglers caused their property to be unstable and to suffer erosion. The Parkers' complaint prayed for compensatory and punitive damages for their loss.

{¶ 5} The Heglers filed their answer, which denied that they were negligent in the excavation and construction of the roadway as well as in the subsequent construction of the retaining wall.

{¶ 6} The case proceeded to a bench trial.

{¶ 7} At the conclusion of the trial, the trial court requested the parties to submit proposed findings of fact and conclusions of law.

{¶ 8} The trial court issued preliminary findings of fact and conclusions of law, in which it found that the Heglers were strictly liable for two separate acts. The first act was as follows:

{¶ 9} "[T]he Heglers excavation of the roadway loosened or destabilized the slope on the Parker property by removing side pressure, or lateral support, along the roadway. Further, the steel beam and concrete panel wall is not sufficiently designed to prevent failure and does not offer adequate support to the Parker property."

{¶ 10} Secondly, the trial court found that:

{¶ 11} "[T]he three-foot-cubed concrete blocks placed at the bottom of the roadway by the Heglers have created an 'end condition,' which has altered the natural wave action along the shoreline. * * * The end condition has further resulted in an accelerated erosion of the slope. The damage to the Parker property extends from the northwest corner of the property at least 40 feet to the east."

{¶ 12} The trial court made additional findings that the Parkers had expended $9,002.31 in engineering and consulting fees to determine the nature and extent of the damage from the excavation.

{¶ 13} The trial court then considered the costs to remediate the Parkers' property.

{¶ 14} The trial court found that it would cost $160,000 to remediate the Parkers' property, but that, if such amount were invested, the fair market value of the property would exceed the fair market value before the damage was done.

{¶ 15} Based upon the above findings of fact, the trial court concluded that "the remediation costs ($160,000) are unreasonably high and will involve significant economic waste if implemented." The trial court approved of the measure of damages adopted in Ohio Collieries Co.v. Cocke.1 In that case, the Supreme Court of Ohio held:

{¶ 16} "In an action for damages by reason of loss of subjacent support caused by the removal of pillars, ribs, and stumps in a coal mine, the owner of the surface is entitled to recover, if the injury is of a permanent or irreparable nature, the difference in the market value of the property as a whole, including improvements thereon, before and after the injury. If the restoration can be made, the measure of damages is the reasonable cost of restoration, plus the reasonable value of the loss of the use of the property between the time of the injury and the restoration, unless such cost of restoration exceeds the difference in the market value of the property as a whole before and after the injury, in which case the difference in the market value before and after the injury becomes the measure."2

{¶ 17} The trial court noted that the damage to the Parkers' property was permanent.

{¶ 18} Neither party presented evidence at the trial as to the fair market value of the Parkers' property before and after the damage. Therefore, the trial court reset the matter for further hearing to ascertain the fair market values as of those respective times.

{¶ 19} At the hearing on the fair market value of the Parkers' property, the trial court heard testimony from two professional appraisers. The trial court accepted the lesser value of the Parkers' property for the relevant time periods. The trial court determined the fair market value to be $220,000 before the property damage, and $200,000 after the property damage, for a total diminution in the value of the property of $20,000. Having found that the remediation costs of $160,000 were "unreasonably high," the court concluded as follows: "the cost of repair is not reasonable under the circumstances, the appropriate measure of damages is diminution in value." The trial court then awarded judgment to the Parkers in the amount of $20,000 for the diminution in the value of their property, together with consulting and engineering fees in the amount of $9,002.31, for a total judgment of $29,002.31. In doing so, the trial court cited to a case more recent than the Ohio Collieries case for the proposition that:

{¶ 20} "The general rule [of the Ohio Collieries case] * * * is not an arbitrary or exact formula to be applied in every case without regard to whether its application would compensate the injured party fully for losses which are the proximate result of the wrongdoer's conduct."3

{¶ 21} However, the trial court was of the opinion that the cases that departed from the general rule of Ohio Collieries, and allowed remediation costs over and above the diminution in value, were cases where the remediation costs were reasonable in amount. Here, according to the trial court, the remediation costs were unreasonable, and, therefore, could not be allowed.

{¶ 22} The Parkers filed a timely appeal to this court, asserting two assignments of error. The first assignment of error is as follows:

{¶ 23}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parker v. Hegler, 2008-L-009 (7-25-2008)
2008 Ohio 3739 (Ohio Court of Appeals, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 6495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-v-hegler-unpublished-decision-12-11-2006-ohioctapp-2006.