Parker Brothers Well Drilling Inc. v. Pine Grove Mobile Home Parks & Sales Inc.

47 Pa. D. & C.3d 401, 1986 Pa. Dist. & Cnty. Dec. LEXIS 31
CourtPennsylvania Court of Common Pleas, Mercer County
DecidedFebruary 4, 1986
Docketno. 595 C.D. 1985
StatusPublished

This text of 47 Pa. D. & C.3d 401 (Parker Brothers Well Drilling Inc. v. Pine Grove Mobile Home Parks & Sales Inc.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Mercer County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Parker Brothers Well Drilling Inc. v. Pine Grove Mobile Home Parks & Sales Inc., 47 Pa. D. & C.3d 401, 1986 Pa. Dist. & Cnty. Dec. LEXIS 31 (Pa. Super. Ct. 1986).

Opinion

FRAMPTON, J.,

This matter comes before the court on defendant’s preliminary objections in the nature of a motion to strike plaintiff’s complaint to reduce a mechanics’ lien claim to judgment.

On August 24, 1984, plaintiff filed a mechanics’ lien against defendant at No. 70 M.L. 1984 in the amount of $14,999.72, for the installation on the [402]*402premises of defendant in Coolspring Township, Mercer County, Pa., a water purification and distribution system in the building located on the premises and the drilling of wells to be connected directly to the building by water lines. Notice of the filing of said mechanics’ lien was served upon defendant on September 6, 1984.

On June 17, 1985, plaintiff filed a complaint at No. 595 C.D. 1985 to reduce to judgment the mechanic’s lien claim filed at No. 70 M.L. 1984. On July 31, 1985, defendant filed the preliminary objections presently before the court at both No. 595 C.D. 1985 and at No. 70 M.L. 1984.

The defendant recites five reasons for the motion to strike. However, only three of those reasons were briefed and argued by defendant, and counsel for defendant agreed at the time of the oral argument in this case that only the issues briefed and argued should be considered by the court. Therefore, the court shall consider the following issues raised by defendant.

(1) Is the mechanics’ lien defective in that the type of work and material alleged to be done and performed does not give rise to or create a mechanics’ lien?

(2) Is the mechanics’ lien defective for failure to set forth specifically the kind and character of labor and material?

(3) Is the mechanics’ lien defective for failure to set forth the date of completion of claimant’s work?

Plaintiff by way of his brief raised the claim that the preliminary objections were not timely filed.

DISCUSSION

Were the preliminary objections to the mechanics’ lien claim and complaint timely filed?

[403]*403Preliminary objections axe available at two stages; first, to the claim under the Mechanics’ Lien Law and second, to the complaint after the action is brought under the Rules of Civil Procedure. Schwartz and Baker v. Racing Inc., 25 Monroe Leg. Rep. 125 (1967).

The Mechanics’ Lien Law of 1963, August 24, 1963, P.L. 1175, Art I, section 101 et seq. (49 P.S. §1101 et seq.) provides for the filing of preliminary objections in section 505 (49 P.S. §1505):

“Any party may preliminarily object to a claim upon a showing of exemption or immunity of the property from lien, or for lack of conformity with this act. The court shall determine all preliminary objections. If an issue of fact is raised in such objections, the court may take evidence by deposition or otherwise. If the filing of an amended claim is allowed, the court shall fix the time within which it shall be filed. Failure to file an objection preliminarily shall not constitute a waiver of the right to raise the same as a defense in subsequent proceedings.”

In addition, defendant may file preliminary objections to the complaint with respect to errors at the claim stage, unless they have been raised and adjudicated at that stage. I. H. Crouse & Sons Inc. v. White, 6 D. & C. 3d 231, (1978).

The Mechanics’ Lien Act of 1963 imposes no time limitation upon the filing of preliminary objections. Hoffman Lumber Company v. Geesey, 35 D. & C. 2d 200, (1965) except after the entry of security to discharge the claim, Johnson Bros. v. Smythe, 63 Pitts. Leg. J. 441 (1915); or after an answer on the merits, Thorn v. Shields, 8 Dist. Rep. 129. None of the noted exceptions occurred in this case.

Therefore, the court finds that preliminary objections were timely filed in this case both as to the me[404]*404chanics’ lien claim itself and to the complaint.

Is the mechanics’ lien defective in that the type of work and material alleged to be done and performed does not give rise to or create a mechanics’ lien?

Defendant, Pine Grove Mobile Home Park Inc., argues that the work performed in the instant case is not a proper subject for a mechanics’ lien because it does not fall within the language of section 301 of the Mechanics’ Lien Law of 1963 (49 P.S. §1301), which provides:

“Every improvement and the estate or title of the owner in the property shall be subject to a lien, to be perfected as herein provided, for the payment of all debts due by the owner to the contractor or by the contractor to any of his subcontractors for labor or materials furnished in the erection or construction, or the alteration or repair of the improvement, provided that the amount of the claim, other than amounts determined by a apportionment under section 306(b) of this act, shall exceed $500.”

The lien in this case as filed at No. 70 M.L. 1984 describes the work as “the installation of a central water receiving and distribution system in the building. This includes the installation of purification and distribution system in the building and the drilling of wells to draw water from, connected directly to the building by water lines.” The building referred to is a single story brick building located on land referred to as Pine Grove Mobile Home Park which is the subject of the within lien.

The act defines “erection, construction, alteration or repair” as including:

“(a) Demolition, removal of improvements, excavation, grading, filling, paving and landscaping, when such work is incidental to the erection, construction, alteration or repair;

[405]*405“(b) Initial fitting up and equipping of the improvement with fixtures, machinery and equipment suitable to the purposes for which the erection, construction, alteration or repair was intended; and

“(c) Furnishing, excavating for, laying, relaying, stringing and restringing rails, ties, pipes, poles and wires ... in order to supply services to the improvement.” Section 201(12) [49 P.S. §1201(12)].”

In addition, “alteration and repair” is defined by the act as:

“Any alteration or repair of an existing improvement which does not constitute erection or construction as defined herein.” Section 201 (11) [49 P.S. §1201(11)].”

The well drfiling and water system installation appears to come within the plain meaning of the statute as to the alteration and repair to an existing structure and the laying of “pipes” to supply services to the improvement. Moreover, case law, while not directly on point as to the improvements in this case, supports this interpretation from holdings in similar cases. A mechanics’ lien for the construction of a driveway and sewage system was allowed in Morrissey Construction Co. v. Cross Realty Co., 42 D. & C. 2nd 535, (1967). Also a mechanics’ lien was permitted for the construction of a trench for a sewer line in Grimes v. Barnes, 85 Montgomery 305 (1965). In addition the digging of a ditch and the laying of drainage pipes from a dwelling house to a cesspool which was necessary to make the dwelling habitable and to afford necessary drainage for waste material from the house have been held sufficient to give rise to a lien. Haas v. Wagner, 78 D. & C. 478 (1951).

The drilling of a well and water system installation to an existing building clearly comes within the [406]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marchak v. McClure
108 A.2d 77 (Superior Court of Pennsylvania, 1954)
Cowan v. Pennsylvania Plate Glass Co.
38 A. 1081 (Supreme Court of Pennsylvania, 1898)
Zeigler Lumber & Supply Co. v. Golden Triangle Development Co.
326 A.2d 524 (Superior Court of Pennsylvania, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
47 Pa. D. & C.3d 401, 1986 Pa. Dist. & Cnty. Dec. LEXIS 31, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parker-brothers-well-drilling-inc-v-pine-grove-mobile-home-parks-sales-pactcomplmercer-1986.