Park Presbyterian Church of Italy v. Wm. Cameron & Co.

38 S.W.2d 901, 1931 Tex. App. LEXIS 483
CourtCourt of Appeals of Texas
DecidedApril 16, 1931
DocketNo. 1050.
StatusPublished
Cited by4 cases

This text of 38 S.W.2d 901 (Park Presbyterian Church of Italy v. Wm. Cameron & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Park Presbyterian Church of Italy v. Wm. Cameron & Co., 38 S.W.2d 901, 1931 Tex. App. LEXIS 483 (Tex. Ct. App. 1931).

Opinion

BARCUS, J.

This suit was instituted by appellee, Wm. Cameron & Co., Inc., hereinafter called Cameron & Co., against the Park Presbyterian Church of Italy, hereinafter called churcfi, and Owens-Nash Construction Company, hereinafter called contractor, and the Southern Surety Company, hereinafter called surety.

In January, 1926, Owens-Nash Construction Company made a contract with the church to erect a building for it at an agreed price of $16,745, and executed a bond with the Southern Surety Company, as surety, conditioned that the contractor would complete the building and pay for all labor and material used in its construction and deliver same clear of all liens to the church. The contract between the church and the contractor, which was made a part of the bond,’ provided that: “All payments (under the contract) shall be paid by the owner to the contractors as follows: all labor and wage expenses shall be paid weekly on certificate of the contractor, endorsed by the engineer. All material and other charges except labor and wages to be paid within ten days after presentation of statement certified by the contractor ' and endorsed by .the engineer. Upon completion of the work and final acceptance .by the engineer, the contractor shall present evidence satisfactory to the engineer and owner that there are no claims or liens against the work. Within ten days after presentation of the above evidence of no claims or \ liens, the owner shall pay all remaining funds due to the contractor upon the engineer’s certificate.”

Willis Livingston was the local agent and representative of Cameron & Co., and as such sold and delivered the lumber to the contractors for said job. He was a member of the church and the treasurer of the building fund for the church. He was selected by all parties as the engineer in charge of the building. He occupied all three of said positions and relationships with the full knowledge and consent of the parties, and no one raised any question or intimation that he was in anyway unfaithful to the trust committed to his care by the respective parties, or that he did anything in connection with the entire transaction that was not entirely satisfactory to all parties.

The contractors, about the 5th of May, abandoned the contract, and the church, under the terms of the contract, notified the surety company thereof, and then proceeded to complete the building at a cost of $1,493.-9S above the contract price. Cameron & Co. filed its lien against the property of the church -for $2,298.10, the unpaid balance due it by the contractor on said job, and filed this suit on its debt against the church and the surety company, and,asked for a foreclosure of its materialman’s lien.

The church, by its answer, contended that Cameron & Co. had no materialman’s lien, and that it was not personally liable for said debt’. By . cross-action the church sought judgment against the surety company for the amount it had spent above the contract price to complete the building and for the amount *902 that Cameron & Co. might establish against the church or its property, and against the contractor for the amount it expended over the contract price and amount of Cameron & Co.’s claim.

The surety- company, by its answer, contended that Cameron & Co. was not entitled to a personal judgment against it under the terms of the bond, and that Cameron & Co. had not' fixed any materialman’s lien; and, further, that it was entirely released from the bond because the church, and the contractor had materially changed, the' terms of the contract in that the church had paid to the contractor three items totaling $850, which had not been paid to said contractor for either labor- or material put into the church building, and that said amount was paid without the presentation of a statement for labor or material therefor, certified by the contractor and indorsed by the engineer.

There were some interveners who were disposed of by the judgment, but they are not involved in this appeal.

The cause was tried to the court and resulted in judgment being entered for Cameron & Co. against the contractor for $2,298.-10 and for a foreclosure of its materialman’s lien on the property of the church, and judgment for the church against Owens-Nash Construction Company for $3,792.08, and judgment for the church against the surety company for $3,342.08, and for the surety company against the Owens-Nash Construction Company for $3,342.08. The surety company and the church have appealed from the judgment as rendered.

It is the contention of each of the appellants that Cameron & Co. did not taire the necessary statutory requirements to fix a materialman’'s lien against the property of the church, as required by articles 5452 and 5453 of the Revised Statutes. As we understand, their main contention being that Cameron & Co. did not, as provided by subdivision 3 of article 5453, give written, notice to the church, as owner of the building being constructed, or to its agent, of each and every item furnished and the amount unpaid. There seems to be no contention but that the account was properly itemized and filed with the county clerk in the manner and for the time as provided by said article. The testimony relative to the transaction is given almost exclusively by Mr. Livingston, who, as above stated, was the agent of Cameron & Co., selling the material, the engineer on the work, supervising same for the church, and a member of the building committee and treasurer thereof who paid out the funds, the checks therefor to be countersigned by Mr. George, the chairman of the building committee for the church. The complete itemized list of the material furnished was attached to the pleading as filed by Cameron & Co., consisting of several hundred different items extending from the 1st of January to the 5th of May. Mr. Livingston testified that said account was 'correct', accurate, and stated the true facts. Said account shows that Cameron & Co. furnished a total of $6,839.15, the major portion thereof being furnished prior to April 15th. He further testified that, as each bill of material was furnished, two copies thereof were made, one was retained by him as agent of Cameron & Co., one was given to the contractors, and that the contractors would then cheek over the items and approve same and then return the bills to him as the engineer in charge of the church building and as the representative of the church, and that he would then keep said bills as approved by the contractor in the church file. The itemized bills showing the material furnished and prices charged therefor having been approved by the contractor and delivered to Livingston as the engineer on the job and as the representative of the church, and same having been by Livingston, as the representative of the church, received and filed with the church papers in connection. with said contract, thereby constituted written notice to the church, as owner, as required by subdivision 3, of article 5453 of the Revised Statutes. We think the testimony supports the implied findings of the trial court that Cameron & Co. complied with all the statutory requirements to fix its materialman’s lien and supports the amount for which judgment was rendered in favor of Cameron & Co. First National Bank v. Lyon-Gray Lumber Co. (Tex. Civ. App.) 194 S. W. 1146; Id., 110 Tex. 162, 217 S. W. 133.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Park Presbyterian Church of Italy v. William Cameron & Co.
58 S.W.2d 63 (Texas Commission of Appeals, 1933)
Fidelity Union Casualty Co. v. State
54 S.W.2d 1079 (Court of Appeals of Texas, 1932)
American Surety Co. of N.Y. v. Noe
53 S.W.2d 178 (Court of Appeals of Kentucky (pre-1976), 1932)

Cite This Page — Counsel Stack

Bluebook (online)
38 S.W.2d 901, 1931 Tex. App. LEXIS 483, Counsel Stack Legal Research, https://law.counselstack.com/opinion/park-presbyterian-church-of-italy-v-wm-cameron-co-texapp-1931.