Park Junction, Llc, V. Pierce County

Court of Appeals of Washington·Decided April 25, 2023·No. 56857-8·Unpublished

Opinion

Filed

Washington State

Court of Appeals

Division Two

April 25, 2023

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

PARK JUNCTION LLC, No. 56857-8-II

Respondent,

v.

PIERCE COUNTY, UNPUBLISHED OPINION Defendant,

TAHOMA AUDUBON SOCIETY; PETRINA VECCHIO, STEVE REDMAN, BETH REDMAN, CLARE DUNCAN MCCAHILL, DR. PETER WOODS MCCAHILL, GEORGE WEARN, LEIGH WEARN, BUD REHBERG, and JAMES HALMO,

Appellants.

GLASGOW, C.J.—More than 20 years ago, in 2000, the Pierce County hearing examiner approved a conditional use permit authorizing Park Junction LLC to build a large resort near Mount Rainier National Park. The permit stated that if the project did not progress “in a reasonable and consistent manner,” the county could initiate an action to revoke the permit. In 2019, the hearing examiner found that Park Junction had violated this condition, so its permit was subject to revocation. Rather than immediately revoke the permit, the hearing examiner encouraged Park Junction and Pierce County to create milestones that the company could realistically meet to come back into compliance.

Park Junction and Pierce County agreed that the first milestone would consist of building two artificial wetlands. But Park Junction missed the milestone deadline. Pierce County initiated revocation proceedings and the hearing examiner revoked Park Junction’s conditional use permit.

Park Junction then filed a Land Use Petition Act (LUPA)1 petition in superior court. The superior court remanded the case to the hearing examiner, reasoning that the record did not show whether Park Junction knew what the first milestone required or whether Park Junction should have received an extension due to COVID-19. Tahoma Audubon Society and several individual citizens appeal, arguing that revocation was proper.

We reverse the superior court and affirm the hearing examiner’s revocation of the conditional use permit.

FACTS

A. Conditional Use Permit Approval In 1994, Park Junction, a company in Elbe, applied for a permit to build a resort about 11 miles from Mount Rainier National Park. In 2000, the hearing examiner approved a conditional use permit authorizing construction of the resort. The resort was to consist of an 18-hole golf course, 270-room lodge, 500-person conference center, 300 condominiums, a retail center, and other features.

The 2000 permit imposed numerous conditions. Condition 34 stated that if “at any time after a final plan has been approved it appears that the project or phase thereof is not progressing in a reasonable and consistent manner or the project has been abandoned, action may be initiated . . . to revoke the approval.” Clerk’s Papers (CP) at 2171 (emphasis added). Condition 35 stated

1 Chapter 36.70C RCW.

that the hearing examiner would hold a review hearing every three years to “review the status of the development, as well as its consistency with the . . . conditions.” Id.

Tahoma Audubon Society, an environmental conservation organization in Pierce County, appealed both the 2000 decision and the decision on reconsideration to superior court and subsequently to this court. We upheld the hearing examiner’s decisions in 2005. Tahoma Audubon Soc’y v. Park Junction Partners, 128 Wn. App. 671, 686, 116 P.3d 1046 (2005). B. Park Junction’s Progress from 2005 to 2019 The hearing examiner held the first review hearing in 2012. The hearing examiner noted that while “the first tri-annual review hearing should have occurred around . . . 2008,” it did not take place because of “worsening economic conditions,” as well as a “serious injury to one of [Park Junction’s] principals.” CP at 2184-85. The hearing examiner concluded that from 1994 to 2007, Park Junction “made significant progress in obtaining permits and plan approvals” for the resort, but “the economic recession and lack of funding prohibited” Park Junction from doing any work at the site other than logging trees. CP at 2191. The hearing examiner decided that Park Junction had generally complied with the conditions of approval, directing staff to set the matter for another review hearing in six to nine months.

The hearing examiner held a second review hearing in 2014. This hearing was delayed due to the death of a principal who was “the chief moving force behind the project.” CP at 2207. The hearing examiner found that although “little, if any, progress” had been made between the first review hearing and several weeks before this hearing, Park Junction “was essentially unable to proceed due to circumstances beyond its control.” CP at 2208. The deceased principal had been a 50 percent owner of Park Junction and they “had a complicated estate.” Id. The hearing examiner

decided that, considering the principal’s death and the continuing recession, Park Junction “made reasonable progress on completion of the project.” CP at 2212. But the hearing examiner added that “these factors are now resolved and future progress . . . should be as originally contemplated.” Id.

The hearing examiner held the third and final review hearing in late 2019. Finding that Park Junction had not abandoned the project, the hearing examiner focused on whether Park Junction had shown that the project was progressing in a reasonable and consistent manner, as required by Condition 34. The hearing examiner found that Park Junction had failed to finalize its proposed sewage plant, water facilities, or wetland protection plan. Because utilities were not available, Park Junction could not complete any development beyond the logging that had occurred in the previous decade. Thus, the hearing examiner decided that Park Junction had “not progressed in a reasonable and consistent manner and [was] subject to revocation of its [permit] pursuant to Condition 34.” CP at 2235. However, acknowledging that Park Junction had provided milestones for future progress, the hearing examiner stated that Pierce County should give Park Junction an opportunity to come back into compliance with Condition 34 by meeting the milestones. The hearing examiner concluded, “Should any delays occur on the part of the applicant in meeting milestones/commitments or in acquiring any State, Federal, or County permits, the County should institute revocation proceedings.” Id. (emphasis added). Park Junction, Pierce County, and the Tahoma Audubon Society all filed requests for reconsideration.

In January 2020, the hearing examiner clarified the milestone-setting process in a decision on reconsideration. The hearing examiner’s decision directed the parties to agree on milestones, provide them to Tahoma Audubon Society for comment, and submit the milestones and comments

to the hearing examiner.2 The decision stated that the parties could present disagreements to the hearing examiner for resolution. C. First Milestone Pierce County worked with Park Junction “on milestones that were reasonable, achievable, and acceptable” to the company. CP at 1549. In February 2020, Park Junction agreed to create two artificial demonstration wetlands to address Pierce County’s concerns about its plan to mitigate the resort’s environmental impact. Pierce County’s “concern, in large part, was over the proposal to use clay liners to seal the wetlands and provide the needed hydrology.” CP at 1550. The parties agreed on a deadline of October 30, 2020, for constructing the two demonstration wetlands.

A March 2020 drainage report prepared for Park Junction stated, “What is being proposed at this point is to grade two areas . . . that will serve as test wetlands for the final wetland mitigation,” a plan for lessening the resort’s impact on wetlands in the area. CP at 1759. The April 2020 wetland mitigation plan prepared by one of Park Junction’s consulting biologists stated, “Agreement has been reached with Pierce County . . . to construct wetland mitigation areas MA1 and MA3 in Phase 1 of the project in 2020 to demonstrate the reliability of the soil seals to create wetland hydrology.” CP at 1703.

Free access — add to your briefcase to read the full text and ask questions with AI

Park Junction, Llc, V. Pierce County, (Wash. Ct. App. 2023).

Park Junction, Llc, V. Pierce County (Park Junction, Llc, V. Pierce County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Norway Hill Preservation & Protection Ass'n v. King County Council
552 P.2d 674 (Washington Supreme Court, 1976)
WHATCOM FIRE DIST. NO. 21 v. Whatcom County
256 P.3d 295 (Washington Supreme Court, 2011)
PHOENIX DEVELOPMENT, INC. v. City of Woodinville
256 P.3d 1150 (Washington Supreme Court, 2011)
Tahoma Audubon Society v. PARK JUNCTION
116 P.3d 1046 (Court of Appeals of Washington, 2005)
City of University Place v. McGuire
30 P.3d 453 (Washington Supreme Court, 2001)
City of University Place v. McGuire
144 Wash. 2d 640 (Washington Supreme Court, 2001)
Whatcom County Fire District No. 21 v. Whatcom County
171 Wash. 2d 421 (Washington Supreme Court, 2011)
Tahoma Audubon Society v. Park Junction Partners
128 Wash. App. 671 (Court of Appeals of Washington, 2005)