Park Junction, Llc, V. Pierce County

CourtCourt of Appeals of Washington
DecidedApril 25, 2023
Docket56857-8
StatusUnpublished

This text of Park Junction, Llc, V. Pierce County (Park Junction, Llc, V. Pierce County) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Park Junction, Llc, V. Pierce County, (Wash. Ct. App. 2023).

Opinion

Filed Washington State Court of Appeals Division Two

April 25, 2023 IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II PARK JUNCTION LLC, No. 56857-8-II

Respondent,

v.

PIERCE COUNTY, UNPUBLISHED OPINION

Defendant,

TAHOMA AUDUBON SOCIETY; PETRINA VECCHIO, STEVE REDMAN, BETH REDMAN, CLARE DUNCAN MCCAHILL, DR. PETER WOODS MCCAHILL, GEORGE WEARN, LEIGH WEARN, BUD REHBERG, and JAMES HALMO,

Appellants.

GLASGOW, C.J.—More than 20 years ago, in 2000, the Pierce County hearing examiner

approved a conditional use permit authorizing Park Junction LLC to build a large resort near

Mount Rainier National Park. The permit stated that if the project did not progress “in a reasonable

and consistent manner,” the county could initiate an action to revoke the permit. In 2019, the

hearing examiner found that Park Junction had violated this condition, so its permit was subject to

revocation. Rather than immediately revoke the permit, the hearing examiner encouraged Park

Junction and Pierce County to create milestones that the company could realistically meet to come

back into compliance. No. 56857-8-II

Park Junction and Pierce County agreed that the first milestone would consist of building

two artificial wetlands. But Park Junction missed the milestone deadline. Pierce County initiated

revocation proceedings and the hearing examiner revoked Park Junction’s conditional use permit.

Park Junction then filed a Land Use Petition Act (LUPA)1 petition in superior court. The

superior court remanded the case to the hearing examiner, reasoning that the record did not show

whether Park Junction knew what the first milestone required or whether Park Junction should

have received an extension due to COVID-19. Tahoma Audubon Society and several individual

citizens appeal, arguing that revocation was proper.

We reverse the superior court and affirm the hearing examiner’s revocation of the

conditional use permit.

FACTS

A. Conditional Use Permit Approval

In 1994, Park Junction, a company in Elbe, applied for a permit to build a resort about 11

miles from Mount Rainier National Park. In 2000, the hearing examiner approved a conditional

use permit authorizing construction of the resort. The resort was to consist of an 18-hole golf

course, 270-room lodge, 500-person conference center, 300 condominiums, a retail center, and

other features.

The 2000 permit imposed numerous conditions. Condition 34 stated that if “at any time

after a final plan has been approved it appears that the project or phase thereof is not progressing

in a reasonable and consistent manner or the project has been abandoned, action may be initiated

. . . to revoke the approval.” Clerk’s Papers (CP) at 2171 (emphasis added). Condition 35 stated

1 Chapter 36.70C RCW.

2 No. 56857-8-II

that the hearing examiner would hold a review hearing every three years to “review the status of

the development, as well as its consistency with the . . . conditions.” Id.

Tahoma Audubon Society, an environmental conservation organization in Pierce County,

appealed both the 2000 decision and the decision on reconsideration to superior court and

subsequently to this court. We upheld the hearing examiner’s decisions in 2005. Tahoma Audubon

Soc’y v. Park Junction Partners, 128 Wn. App. 671, 686, 116 P.3d 1046 (2005).

B. Park Junction’s Progress from 2005 to 2019

The hearing examiner held the first review hearing in 2012. The hearing examiner noted

that while “the first tri-annual review hearing should have occurred around . . . 2008,” it did not

take place because of “worsening economic conditions,” as well as a “serious injury to one of

[Park Junction’s] principals.” CP at 2184-85. The hearing examiner concluded that from 1994 to

2007, Park Junction “made significant progress in obtaining permits and plan approvals” for the

resort, but “the economic recession and lack of funding prohibited” Park Junction from doing any

work at the site other than logging trees. CP at 2191. The hearing examiner decided that Park

Junction had generally complied with the conditions of approval, directing staff to set the matter

for another review hearing in six to nine months.

The hearing examiner held a second review hearing in 2014. This hearing was delayed due

to the death of a principal who was “the chief moving force behind the project.” CP at 2207. The

hearing examiner found that although “little, if any, progress” had been made between the first

review hearing and several weeks before this hearing, Park Junction “was essentially unable to

proceed due to circumstances beyond its control.” CP at 2208. The deceased principal had been a

50 percent owner of Park Junction and they “had a complicated estate.” Id. The hearing examiner

3 No. 56857-8-II

decided that, considering the principal’s death and the continuing recession, Park Junction “made

reasonable progress on completion of the project.” CP at 2212. But the hearing examiner added

that “these factors are now resolved and future progress . . . should be as originally contemplated.”

Id.

The hearing examiner held the third and final review hearing in late 2019. Finding that

Park Junction had not abandoned the project, the hearing examiner focused on whether Park

Junction had shown that the project was progressing in a reasonable and consistent manner, as

required by Condition 34. The hearing examiner found that Park Junction had failed to finalize its

proposed sewage plant, water facilities, or wetland protection plan. Because utilities were not

available, Park Junction could not complete any development beyond the logging that had occurred

in the previous decade. Thus, the hearing examiner decided that Park Junction had “not progressed

in a reasonable and consistent manner and [was] subject to revocation of its [permit] pursuant to

Condition 34.” CP at 2235. However, acknowledging that Park Junction had provided milestones

for future progress, the hearing examiner stated that Pierce County should give Park Junction an

opportunity to come back into compliance with Condition 34 by meeting the milestones. The

hearing examiner concluded, “Should any delays occur on the part of the applicant in meeting

milestones/commitments or in acquiring any State, Federal, or County permits, the County should

institute revocation proceedings.” Id. (emphasis added). Park Junction, Pierce County, and the

Tahoma Audubon Society all filed requests for reconsideration.

In January 2020, the hearing examiner clarified the milestone-setting process in a decision

on reconsideration. The hearing examiner’s decision directed the parties to agree on milestones,

provide them to Tahoma Audubon Society for comment, and submit the milestones and comments

4 No. 56857-8-II

to the hearing examiner.2 The decision stated that the parties could present disagreements to the

hearing examiner for resolution.

C. First Milestone

Pierce County worked with Park Junction “on milestones that were reasonable, achievable,

and acceptable” to the company. CP at 1549. In February 2020, Park Junction agreed to create two

artificial demonstration wetlands to address Pierce County’s concerns about its plan to mitigate

the resort’s environmental impact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norway Hill Preservation & Protection Ass'n v. King County Council
552 P.2d 674 (Washington Supreme Court, 1976)
WHATCOM FIRE DIST. NO. 21 v. Whatcom County
256 P.3d 295 (Washington Supreme Court, 2011)
PHOENIX DEVELOPMENT, INC. v. City of Woodinville
256 P.3d 1150 (Washington Supreme Court, 2011)
Tahoma Audubon Society v. PARK JUNCTION
116 P.3d 1046 (Court of Appeals of Washington, 2005)
City of University Place v. McGuire
30 P.3d 453 (Washington Supreme Court, 2001)
City of University Place v. McGuire
144 Wash. 2d 640 (Washington Supreme Court, 2001)
Whatcom County Fire District No. 21 v. Whatcom County
171 Wash. 2d 421 (Washington Supreme Court, 2011)
Tahoma Audubon Society v. Park Junction Partners
128 Wash. App. 671 (Court of Appeals of Washington, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Park Junction, Llc, V. Pierce County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/park-junction-llc-v-pierce-county-washctapp-2023.