Park Center III Ltd. Partnership v. Pennsylvania Manufacturers' Ass'n

30 F. App'x 64
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 22, 2002
Docket01-1649, 01-1668
StatusUnpublished
Cited by2 cases

This text of 30 F. App'x 64 (Park Center III Ltd. Partnership v. Pennsylvania Manufacturers' Ass'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Park Center III Ltd. Partnership v. Pennsylvania Manufacturers' Ass'n, 30 F. App'x 64 (4th Cir. 2002).

Opinion

OPINION

PER CURIAM.

Park Center III Limited Partnership and other entities (collectively Park Center) brought this diversity action against the Pennsylvania Manufacturers’ Association Insurance Company (PMA) seeking recovery on an insurance policy issued to Park Center by PMA. The insurance policy covered a four-building apartment complex in Alexandria, Virginia (the Project), owned by the various Park Center entities. The Project was under construction on September 16, 1999, when Hurricane Floyd struck the greater Washington, D.C., metropolitan area, including Alexan *66 dría, causing extensive damage. PMA denied coverage for Park Center’s claimed losses, asserting that the items damaged by Floyd had already deteriorated and needed replacement prior to Floyd. Park Center sued in federal court seeking coverage for its damaged property as well as attorneys’ fees and costs. Following a three-day bench trial the district court held that the policy provided coverage to Park Center for most of its claimed losses but denied its claim for attorneys’ fees. PMA appeals certain aspects of the district court’s judgment, and Park Center cross-appeals the court’s denial of attorneys’ fees. We affirm the district court’s judgment for the most part, but we remand for a recalculation of Park Center’s damages for replacing the two layers of gypsum sheathing with one layer of gypsum and one layer of Tyvec.

I.

The PMA policy insuring the Project is an “all risk” policy covering all physical losses to the covered property except losses specifically excluded. Policy § A.3. The parties agree that Hurricane Floyd was a fortuitous event not excluded by the policy.

The apartment buildings were constructed of a light gauge steel frame covered with two layers of gypsum panels, which were in turn to be covered with an exterior cladding. Gypsum panels cannot be left uncovered during the construction process for long periods of time because they do not withstand extended exposure to weather conditions. The parties dispute precisely how long gypsum panels may be exposed before they deteriorate to the point that they must be replaced. PMA presented evidence of a national standard recommending that gypsum panels not be exposed to the elements for more than 30 days. Park Center presented evidence that this 30-day limit is at best a rough benchmark that is routinely violated in the D.C. metropolitan area and that the conditions of particular gypsum panels depend on the actual weather conditions during the time of exposure. Park Center also presented evidence that the summer of 1999 was an exceptionally dry summer in the northern Virginia area.

When Floyd passed through the area on September 16, 1999, the gypsum panels had not yet been covered by the exterior cladding and had been exposed to the elements for 90 days or longer. Several months before the hurricane, Erkiletain Construction Corporation, the original general contractor on the Project, had determined that the gypsum panels on one of the buildings had deteriorated to the point that they needed to be replaced. Erkiletain’s subcontractor replaced most of the panels, but then, at the direction of its surety, stopped working. As a result, all work was halted on the Project as of June 1999. At this point, Park Center decided to replace Erkiletain with another general contractor, Clark Construction Company. Clark’s employees inspected the site and determined that the gypsum panels on all of the buildings could be used with only minor repairs. On September 15, 1999, with Floyd gathering steam off the Florida coast and spinning its way northward towards Alexandria, Clark and Park Center signed their contract.

The next day, September 16, 1999, Hurricane Floyd passed through Alexandria. While Floyd’s trip inland over North Carolina had diminished its force, it nonetheless hammered the Project with heavy rains and winds up to 55 m.p.h. Following the storm, the Project showed extensive damage, including collapsed roof trusses on one building, damage to an electric switchgear, and waterlogged plywood. In addition, almost all of the gypsum sheathing was saturated and falling *67 apart. Following Floyd, the City of Alexandria directed Park Center to remove the damaged sheathing from the Project. PMA’s representative, Jim Hardy, visited the site on September 29, 1999, and acknowledged that the gypsum sheathing had to be removed and replaced.

Prior to Floyd the builders had determined that many of the plywood panels used in one part of the construction site had become waterlogged and needed to be replaced. Following Floyd, all of the plywood needed to be replaced. In its claim Park Center estimated that 20 to 25 percent of the plywood was not damaged prior to Floyd, and only that percentage was included in its claim.

Also, prior to Floyd the buildings of the Project had been heated as soon as they were entirely enclosed in gypsum panels. The internal water pipes of those buildings had then been filled with water on the assumption that they would be protected from the freezing temperatures of the upcoming winter. When the builders had to remove and replace the sheathing after Floyd, the buildings could no longer be heated. To prevent pipe breakage, the builders tried to drain the interior pipes of all water before removing the sheathing and exposing the pipes to the cold. The pipes were not designed to be drained, however, and a number of pipes contained valves that, unbeknownst to the builders, retained water. In the spring, after the panels had been replaced and the pipes had been refilled, the builders discovered that the pipes had frozen at several points and needed repair.

Park Center filed an insurance claim requesting coverage for the damage to the trusses, the electrical switchgear, the plywood, the gypsum sheathing, and the pipes. Park Center also sought coverage for damages from delays on the Project due to Floyd. PMA denied all elements of the claim, asserting that most of the relevant property had already deteriorated and needed replacement prior to Floyd and that the rest of the damage was excluded by the policy.

The district court, applying Virginia law, held that the policy provided coverage for most of Park Center’s claims. The parties do not contest the district court’s choice of Virginia law. Nor does PMA contest every aspect of the coverage determination. We discuss only those parts of the district court’s order that are the subject of appeal.

The parties presented extensive evidence to the district court on the condition of the gypsum panels prior to Floyd. The evidence consisted of numerous pre and post-Floyd photographs of the Project and the testimony of various persons who had examined the Project at some point prior to Floyd. Based on its evaluation of this evidence, the court determined that while a small portion of the gypsum sheathing was damaged and needed some repair pri- or to Floyd, the vast majority of the paneling was usable until the additional damage caused by Floyd. The court also found that given the extent of the damage caused by Floyd, it was cheaper to replace the gypsum sheathing in its entirety rather than to conduct spot repairs. Accordingly, the court awarded the entire cost of replacing the two layers of gypsum sheathing to Park Center.

In addition, the district court held that the policy provided coverage for the burst pipes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
30 F. App'x 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/park-center-iii-ltd-partnership-v-pennsylvania-manufacturers-assn-ca4-2002.