Paragon Technologies, Inc. v. uwork.com, Inc.

Court of Appeals of Georgia·Decided March 29, 2013·No. A12A2449·Published

Opinion

WHOLE COURT

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed.

(Court of Appeals Rule 4 (b) and Rule 37 (b), February 21, 2008)

http://www.gaappeals.us/rules/

March 29, 2013

In the Court of Appeals of Georgia A12A2448. UWORK.COM, INC. et al. v. PARAGON TECHNOLOGIES, INC.

A12A2449. PARAGON TECHNOLOGIES, INC. v.

UWORK.COM, INC. et al.

MCMILLIAN, Judge.

Plaintiff Paragon Technologies, Inc. (“Paragon”) subcontracted with Defendant UWork.com, Inc. d/b/a Covendis Technologies (“Covendis”) to supply temporary IT consultants to the State of Georgia. These companion appeals arise out of a series of business disputes between Paragon and Covendis regarding background checks for the consultants, the payment of subcontractors hired by Paragon, and Paragon’s billing rates. In Case No. A12A2448, Covendis appeals the trial court’s order granting summary judgment to Paragon on Paragon’s breach of contract claims and on Covendis’ breach of contract and fraud counterclaims. Additionally, Covendis and

its CEO appeal the trial court’s denial of summary judgment to them on Paragon’s breach of fiduciary duty claim. In Case No. A12A2449, Paragon appeals the trial court’s order granting summary judgment to Covendis, its CEO, and one of its client care managers on Paragon’s claims for fraud and negligent misrepresentation. For the reasons discussed below, we affirm in part and reverse in part in Case No. A12A2448, and affirm in Case No. A12A2449.

Summary judgment is appropriate if the pleadings and the undisputed evidence show that there exists no genuine issue as to any material fact, and that the moving party is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). On appeal from the grant or denial of summary judgment, the appellate courts conduct a de novo review, construing all reasonable inferences in the light most favorable to the nonmoving party.

(Citations omitted.) Bank of North Ga. v. Windermere Dev., Inc., 316 Ga. App. 33, 34 (728 SE2d 714) (2012). Guided by these principles, we turn to the record in the present case.

Covendis’ Vendor Management System. In 2007, Covendis entered into a contract, subject to renewal on an annual basis, to develop and implement a web- based tool for managing temporary IT staffing for the State of Georgia. The web- based tool developed by Covendis, the “Vendor Management System” (“VMS”),

listed state agencies that were in need of independent contractors to perform IT work. All companies or persons that wanted to perform IT work for those state agencies were required to enter into “supplier agreements” with Covendis to procure work through the VMS.

Once a company entered into a supplier agreement with Covendis, it gained access to the VMS, where Covendis would post the specifications and requirements for the IT positions that the state agencies sought to fill. If a supplier wished to provide IT staff for a posted position, it would submit a proposal through the VMS containing the necessary pricing information. If the state agency accepted the proposal and the supplier staffed the position, the supplier thereafter would enter the VMS and submit its time and expenses for services rendered. Covendis then would invoice the State for the services provided by the supplier, the State would pay Covendis the amount owed in the invoice, and Covendis would remit payment to the supplier within a specified time frame.

The Supplier Agreement between Covendis and Paragon. Beginning in 2007, Paragon entered into a supplier agreement with Covendis on an annual basis to provide temporary IT staff to the State through the VMS (the “Supplier Agreement”). In addition to supplying IT staff through its own employees, Paragon entered into

agreements with a number of subcontractors to supply IT staff to the State. Under the Supplier Agreement, Paragon was required to provide Covendis with background verification reports on IT workers supplied to the State and to submit the names of its proposed subcontractors for Covendis’ review and approval.

The March Agreement. From 2007 through October 2009, the business relationship between Covendis and Paragon was predictable and stable. But beginning in October 2009, Covendis became concerned that Paragon was providing it with false background verification reports about its IT staff. After conducting an investigation and concluding that Paragon was submitting false background verifications, Covendis sent notice to Paragon in February 2010 that it was terminating the Supplier Agreement. After receiving the notice, Paragon contacted Covendis and entered into negotiations over the issue of termination. During the negotiations, Paragon continued to supply IT staff to the State.

On March 1, 2010, the parties settled their dispute over the background verifications (the “March Agreement”). The parties agreed that the provisions of the Supplier Agreement would “continue in full force and effect,” except to the extent that they conflicted with the March Agreement. Under the March Agreement, Paragon was permitted to continue serving as a supplier under the Supplier Agreement on a

probationary basis for six months. If Paragon did not materially breach the Supplier Agreement during the probationary period, its reinstatement as a supplier would become permanent through the remaining term of the Supplier Agreement.

Pursuant to the March Agreement, Paragon agreed to pay $25,000 to Covendis, to submit new background verifications for specified workers, and to pay an increased administrative fee to the State of Georgia Department of Administrative Services. Paragon also agreed to limit the total “markup” it could charge the State by implementing a “28% margin cap” on its own employees and a “35% margin cap” on workers provided by its subcontractors, effective April 1, 2010.1 The March Agreement gave Paragon until March 31, 2010 “to renegotiate and finalize all rates to follow the bill rate guidelines set.” In return, Covendis agreed to the probationary reinstatement of Paragon as a supplier and also agreed to release any claims against Paragon relating to the background verifications.

1 Covendis asserts that the margin caps were intended to achieve additional savings for the State of Georgia for services provided by Paragon by cutting the fee Paragon took for each hour that a contractor worked. And according to Tsao, at a meeting on April 20, 2010, Paragon’s representatives suggested that they maintain the March 1, 2010 billing rates and instead provide a six percent discount to the State, but Covendis refused the offer because it would not lower the billing rates as much as the margin caps. But Paragon denies that Covendis ever told it, either before the March Agreement was signed or after, that this was the intent of the margin caps.

The Subcontractor Pay Dispute. In addition to the parties’ dispute over the background verifications, a dispute arose over Paragon’s payment of its subcontractors. Around February 2010, two of Paragon’s subcontractors began complaining to Covendis that they were not receiving payment from Paragon for IT work performed for the State. Paragon contends that it was slow in making payments to its subcontractors during this period because Covendis had been slow in remitting payment to Paragon. According to Paragon, however, Covendis misrepresented to the subcontractors that Paragon was the source of the failure to pay because Paragon had already been paid by Covendis. Paragon also contends that Covendis falsely told the subcontractors that Paragon was no longer an approved supplier with the State.

Free access — add to your briefcase to read the full text and ask questions with AI

Paragon Technologies, Inc. v. uwork.com, Inc., (Ga. Ct. App. 2013).

Paragon Technologies, Inc. v. uwork.com, Inc. (Paragon Technologies, Inc. v. uwork.com, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

National Council on Compensation Insurance v. Strickland
526 S.E.2d 924 (Court of Appeals of Georgia, 1999)
Florida Rock & Tank Lines, Inc. v. Moore
365 S.E.2d 836 (Supreme Court of Georgia, 1988)
Allen v. Hub Cap Heaven, Inc.
484 S.E.2d 259 (Court of Appeals of Georgia, 1997)
Potts v. UAP-GA AG CHEM, INC.
567 S.E.2d 316 (Court of Appeals of Georgia, 2002)
Stanford v. Otto Niederer & Sons, Inc.
341 S.E.2d 892 (Court of Appeals of Georgia, 1986)
Moore v. Florida Rock & Tank Lines, Inc.
359 S.E.2d 356 (Court of Appeals of Georgia, 1987)
Megel v. Donaldson
654 S.E.2d 656 (Court of Appeals of Georgia, 2007)
Clay v. Oxendine
645 S.E.2d 553 (Court of Appeals of Georgia, 2007)
Pardue v. BANKERS FIRST FEDERAL SAVINGS & LOAN ASSOCIATION
334 S.E.2d 926 (Court of Appeals of Georgia, 1985)
Holmes v. Grubman
691 S.E.2d 196 (Supreme Court of Georgia, 2010)
Almond v. McCranie
643 S.E.2d 535 (Court of Appeals of Georgia, 2007)
Physician Specialists in Anesthesia, P.C. v. Wildmon
521 S.E.2d 358 (Court of Appeals of Georgia, 1999)
Ansley Marine Construction, Inc. v. Swanberg
660 S.E.2d 6 (Court of Appeals of Georgia, 2008)
Jennings v. Smith
487 S.E.2d 362 (Court of Appeals of Georgia, 1997)
Craig v. BAILEY BROS. REALTY, INC.
697 S.E.2d 888 (Court of Appeals of Georgia, 2010)
Service Merchandise, Inc. v. Jackson
473 S.E.2d 209 (Court of Appeals of Georgia, 1996)
Steimer v. Northside Building Supply Co.
415 S.E.2d 688 (Court of Appeals of Georgia, 1992)
Board of Regents of the University System v. Doe
630 S.E.2d 85 (Court of Appeals of Georgia, 2006)
ReMax North Atlanta v. Clark
537 S.E.2d 138 (Court of Appeals of Georgia, 2000)
Hightower v. Century 21 Farish Realty
448 S.E.2d 271 (Court of Appeals of Georgia, 1994)