TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
NO. 03-10-00059-CV
Panté Technology Corporation, Appellant
v.
Austin Concrete Solutions, Inc., Appellee
FROM THE DISTRICT COURT OF TRAVIS COUNTY, 261ST JUDICIAL DISTRICT
NO. D-1-GN-09-000809, HONORABLE STEPHEN YELENOSKY, JUDGE PRESIDING
M E M O R A N D U M O P I N I O N
Appellee Austin Concrete Solutions, Inc. ("Austin") sued Christopher M. Steele and
appellant Panté Technology Corporation ("Panté") for fraud and breach of contract. Austin later
dropped its suit against Steele, but Panté filed a cross-claim against Steele for breach of fiduciary
duty. The jury found that Panté entered into and breached a contract with Austin, but did not commit
fraud. The jury also found that Steele did not breach his fiduciary duty to Panté. The trial court
rendered judgment consistent with the jury's findings. Panté appeals in five issues, asserting that
(1) the evidence was legally and factually insufficient to support the jury's finding that Panté entered
into a contract with Austin, and (2) the evidence conclusively showed that Steele breached
his fiduciary duty to Panté, or in the alternative, the jury's finding that Steele did not breach his
fiduciary duty is against the great weight and preponderance of the evidence. We will affirm the
trial court's judgment.
FACTUAL AND PROCEDURAL BACKGROUND
Seeking to diversify its investment portfolio, Panté, a provider of technology services
and products, decided to invest in real estate by building high-end houses. Lacking experience in
the building trade, Panté sought to partner with professionals who had construction expertise.
Martin Ward, Panté's president, testified that he identified four knowledgeable building
professionals with whom he wanted to partner, one of whom was Steele, a construction expert Ward
knew from Steele's work for another builder. When he learned that Steele was nearing the end of
a construction project with his then-current employer, Ward approached Steele about working with
Panté on several building projects.
The exact nature of Steele's relationship with Panté was unclear. Ward testified that
he and Steele envisioned working together, "building a better mousetrap" by creating a "team
concept . . . by bringing together more partnerships and builders . . . to work on one single project
or multiple projects having multiple project managers." According to Ward, Steele shared his
enthusiasm for this apparently novel approach to home-building, and the two men began discussing
plans for collaborating on their first building project in a new subdivision near Lake Travis called
Spanish Oaks ("the project"). Ward testified that Steele originally suggested that he (Steele) act as
general contractor on the project and that Panté take the role of "owner" or financier. Ward,
however, envisioned having more control over the day-to-day aspects of the project and, according
to his testimony, specifically wanted to retain control over the hiring of contractors and
subcontractors. Steele testified that in practice, his company, Construction & Company, made the
day-to-day decisions, paid the various suppliers and subcontractors directly, and submitted the
invoices to Panté for reimbursement. Steele testified that he had no direct financial investment in
the project apart from his time, for which he received a "salary" or "fee"--the parties disagree on
the label--of roughly $9,200 per month. Although Steele and Panté never entered into a written
contract to define the parties' precise roles with respect to the project, it is undisputed that Steele was
affiliated with Panté and had authority to act on its behalf for some purposes.
The extent of that authority is central to the dispute here. The parties agree that Steele
had Panté's authority to purchase the lot in Spanish Oaks, clear it, and prepare it for the foundation
to be poured. Panté asserted that, after those tasks were complete, "Ward repeatedly instructed
Steele not to enter in contracts on behalf of Panté, never authorized Steele to enter into [the contract
at issue here], and repeatedly instructed him to stop all work that had been started on the [Spanish
Oaks project]." Steele testified differently. He stated that, despite receiving several e-mails from
Ward instructing him to stop building, Ward orally repudiated his e-mailed instructions and
instructed Steele to continue building the foundation.
Austin, a concrete subcontractor that Steele hired to build the house's foundation,
completed a large part of the foundation per the contract, but Panté refused to pay for most of the
work done. Austin sued Steele and Panté for breach of contract and fraud. Panté answered and
asserted that it was not liable to Austin because Steele was not acting as Panté's agent when he
contracted with Austin. Panté also filed a cross-claim against Steele asserting that if Steele was
found to be Panté's agent, he breached his fiduciary duty to Panté by contracting with Austin. Panté
asserted that Steele put his own interests--having a finished "show house" ready in time for the
Parade of Homes (1)--ahead of Panté's financial interest by not soliciting additional bids for the
foundation and by continuing to build the foundation after being ordered to stop. Before trial,
Austin dropped its claims against Steele. The jury returned a verdict in favor of Austin on the
breach-of-contract claim and in favor of Steele on Panté's fiduciary-duty claim against him. The trial
court rendered judgment consistent with the verdict and denied Panté's motion for new trial. Panté
filed this appeal.
STANDARD OF REVIEW
In reviewing a jury verdict for legal sufficiency, we consider the evidence in the light
most favorable to the verdict, crediting evidence favorable to the verdict if reasonable jurors could
and disregarding contrary evidence unless reasonable jurors could not. City of Keller v. Wilson,
168 S.W.3d 802, 827 (Tex. 2005). We reverse the court's judgment only if the evidence presented
at trial would not allow reasonable and fair-minded jurors to reach the finding under review. Id. We
will sustain a legal-sufficiency challenge if the record reveals: (1) the complete absence of evidence
of a vital fact; (2) that the court is barred by rules of law or evidence from giving weight to the only
evidence offered to prove a vital fact; (3) that the evidence offered to prove a vital fact is no more
than a mere scintilla; or (4) that the evidence conclusively establishes the opposite of a vital fact.
Id. at 810. More than a scintilla of evidence exists when reasonable and fair-minded people could
differ in their conclusions based on the evidence in the record. Forbes, Inc. v. Granada Biosciences,
124 S.W.3d 167, 172 (Tex. 2003).
"When reviewing a jury verdict to determine the factual sufficiency of the evidence,
the court of appeals must consider and weigh all the evidence, and should set aside the verdict only
if it is so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust."
Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986). "The court of appeals is not a fact finder.
Accordingly, the court of appeals may not pass upon the witnesses' credibility or substitute its
judgment for that of the jury, even if the evidence would clearly support a different result." Maritime
Overseas Corp. v. Ellis, 971 S.W.2d 402, 407 (Tex. 1998).
DISCUSSIONAgency
In its first three issues, Panté challenges the legal and factual sufficiency of
the evidence supporting the jury's affirmative answer to Question 1 of the court's charge.
Question 1 asked: "Did [Panté] and [Austin] agree that [Austin] would construct a residential
concrete foundation in exchange for payment?" (2) Challenging the jury's affirmative answer to that
question, Panté asserts that (1) there is no evidence that Panté directly entered into a contract with
Austin, (2) there is no evidence that Steele was Panté's agent when he contracted with Austin, and
(3) there is factually insufficient evidence to support the jury's finding. The parties appear to agree
that Panté never directly contracted with Austin. The parties also agree that Steele negotiated and
entered into a contract with Austin. They dispute, however, whether Steele was acting as Panté's
agent when doing so. Thus, by finding that Panté had a contract with Austin, the jury apparently
concluded that Steele acted as Panté's agent in contracting with Austin. Consequently, we must
examine the evidence regarding Steele's agency relationship with Panté.
"The law does not presume agency. Absent actual or apparent authority, an agent
cannot bind a principal." Suarez v. Johnson, 35 S.W.3d 268, 272-73 (Tex. App.--Houston [14th
Dist.] 2000, no pet.) (citation omitted). "Actual authority denotes that authority which the principal
intentionally confers upon the agent, or intentionally allows the agent to believe he has, or by want
of ordinary care allows the agent to believe himself to possess." Id. at 273. "Actual authority is
created through written or spoken words or conduct of the principal communicated to the agent. The
existence of an agency relationship based on actual authority may be implied from the conduct of
the parties or from the facts and circumstances surrounding the transaction in question." Walker Ins.
Servs. v. Bottle Rock Power Corp., 108 S.W.3d 538, 549-50 (Tex. App.--Houston [14th Dist.] 2003,
no pet.) (citation omitted).
While actual authority is created by words or conduct of the principal to the agent,
apparent authority is created by words or conduct by the principal to a third party. Id.
To establish apparent authority, one must show that a principal either knowingly
permitted an agent to hold himself out as having authority or showed such lack of
ordinary care as to clothe the agent with indicia of authority. A party seeking to
charge a principal through the apparent authority of an agent must establish conduct
by the principal that would lead a reasonably prudent person to believe the agent had
the authority it purported to exercise.
Id. at 550-51.
Evidence of Steele's Authority
Panté admits that "the evidence is disputed as to whether [Steele] had a
builder/developer and/or employee/employer relationship with Panté." (3) Panté also acknowledges
that Steele testified that he had authority to "go ahead" with the Austin contract, but asserts that
Steele's testimony about his authority amounts to no more than a scintilla in light of the other
evidence presented at trial.
Steele admitted receiving several e-mails from Ward ordering him, first, not to begin
construction and, later, to stop construction. Steele testified, however, that each time Ward
instructed him to stop building, the two men would communicate either in person or by telephone
and, encouraged by Steele, Ward would relent and allow construction to continue. Steele testified:
Q. You heard Mr. Ward's lawyers say that possibly one of their positions is that
[Ward] told you to stop building this house . . . .
A. Correct.
Q. Okay. Tell the jury what your response is to that. If they claim that, what's
your response?
A. Indeed, he did tell me to stop multiple times, e-mailings. I agree with that
statement.
Q. Did you stop?
A. No.
Q. Why?
A. Because we talked in person on the phone all the time, had meetings that
lasted six or eight hours talking about things. And I guess we contradicted
ourselves.
. . . .
Q. Your position is, I never told him to stop [sic] because I always talked to him
after he would say stop. I'd go talk, we'd get it fixed. I always had his
approval to keep going?
Q. So you didn't feel like you had to ask him for permission, even though you
did that several times?
A. Correct. It seems like--I mean, we had meetings, phone calls, e-mailings,
everything it was always, go, go, go; stop, go, stop, go, stop. Go, go, go, go,
stop. Go. You know, so--
Austin's counsel next questioned Steele about the series of e-mails exchanged
between him and Ward in which Ward appeared to order Steele to stop construction:
Q. Let's look at Exhibit 82, please. 82 is an e-mail from--actually two
e-mails. . . . Let's start there first, lower part of the page dated August 8th,
and this is an e-mail to you from Mr. Ward, right?
Q. And this says--if you look down there about halfway down there, it says,
"Do not commit Panté to any financial obligations."
Q. And then . . . if you look, same date, you see the first one was at August 8th.
So now we just looked at July 28th. So this is about a week--about a week
later. And this one says 1:23 p.m. Then we go to 7:50 p.m., a couple of
hours later the same day. You respond to Mr. Ward, "All is well from
our"--look at the very beginning. "All is well from our meeting today." Is
that--did you meet with him on August 8th.
A. I am assuming so, yes.
Q. What did you talk about?
A. I believe this is the day that I met with [Ward] and his wife. And I had sent
[Ward] an e-mail that was kind of trying to get him on the ball. He thought
it was--you know, he thought it wasn't very nice, more or less. I was trying
to light a fire under him to start acting correctly, in my opinion. And he sent
me one that said, Don't send me e-mails like this. I don't appreciate it. And
then he called me and we met up at Barnes & Nobles and kind of made up.
And him and his wife were there. And he gave me a book. You know, today
everything is good, pats me on the back, yea. And we were on our way.
Q. So go--
A. So I went home, sent him this e-mail that night.
Q. So still on Exhibit 82 where he says, "Do not commit Panté to any financial
obligations," August 8, 2008 in the afternoon. You then meet with him and
his wife at Barnes & Noble later that afternoon and talked that out. And your
testimony is that he basically agreed that you were going to keep going?
Q. I think I said keep going. Keep working on the project at this house, okay,
Spanish Oaks?
A. Yes.
Steele also testified that, nine days after the August 8 e-mail exchange and the
meeting at Barnes & Noble, he sent Ward a progress report indicating that construction of the
foundation was proceeding as planned.
Q. Okay. Let's go to Exhibit 83, please. . . . August 17, this is an e-mail to
Mr. Ward. Again, that's who MW is, right?
Q. And the--from you. And it says, "The slab should be ready to start
depending on weather this week." So this is a couple of weeks that--we
were at August 8, now we're two weeks later, week and a half later. You're
telling him the slab's getting ready to start. As of this date, are you going
forward on the slab.
A. Correct, correct.
Steele testified that, after sending the August 17 progress report indicating that the foundation work
was proceeding, he received no response from Ward. Steele further testified that he e-mailed
Ward other status reports discussing the planned foundation work, yet never received a response.
Steele testified:
Q. Next e-mail, Exhibit 84. . . . August 22. This is an e-mail again to Mr. Ward
from you, right?
Q. If you look down at the second paragraph--so here we are, that was the 18th.
19, 20, 21, 22, four days later and you tell him, "If everything goes well, we
should be started on the slab by next Tuesday." So you started--you had like
three weeks before you said, I am doing the slab soon; two weeks before that
you said, slab, depending on the weather, we're getting ready to do the slab.
Now, you are saying getting ready to start the slab as of August 22. On this
date, are you going forward or not?
Q. Next exhibit, please, 85. E-mail dated August 23, next day from what we just
looked at. Look at what you tell him here. This is from you to him again,
right?
Q. Okay. And let's see, you tell him, I am ready to start the foundation on
Tuesday of this week coming up, 8/26. And the foundation guys are ready.
You say, I am done with the basement cut and lot cut. . . .
A. Right.
Q. Did he ever come out and say, stop on this date? Did he come out there and
say stop?
Q. "The foundation should start Tuesday and go"--"be going on for the next
two months plus a little bit." As of August 22, '08, are you going forward
or not?
A. Yes. We're doing construction out there, correct.
Q. Okay. August. Now, we're on Exhibit 86, September 2. So here we are a
couple of--let's say that was August 23, a week and a half, two weeks later.
Look at the first line on the second paragraph. "I am ready to start the slab
tomorrow." That Lot 142 in Spanish Oaks, that is this house, right?
Q. As of September 2 are you going forward with the slab or not?
Q. Okay. Next e-mail, please, Exhibit 87. September 5, 2008. So here we are,
three days after the last one we just looked at. Look down on the second
paragraph about halfway down. "The slab started today and I am moving full
steam ahead!" That was an e-mail you sent to Mr. Ward, right?
Steele also testified that, meanwhile, Panté was paying Austin's bills for the foundation work as they
were submitted.
Ward testified that, despite receiving Steele's progress-report e-mails, he did not
know the foundation was being built prior to September 11, 2008. That same day, Ward sent Steele
an e-mail instructing him to "[p]lease stop all work including the foundation until we have a
finish[ed] set of plans in place" and expressing concerns that "[r]ight now the budgetary number
given $5 million, are [sic] extremely too high for this project." Steele testified that he did not stop
work immediately when he received Ward's e-mail because "[Ward] and I would discuss stuff and
keep rolling." Steele also testified that between September 11 and the parties' next e-mail exchange
on October 6, Steele and Ward had discussed the project and they "had talked about keep going, keep
going, keep going."
The October 6, 2008 e-mail exchange, however, appears to contradict Steele's
assertion that Ward instructed him to continue building the foundation. Ward's e-mail states that
Panté "need[ed] to have a complete set of plans to determine cost for all area including foundation"
and mentions the need for the two men to meet "prior to any work being performed." Steele replied
later that evening, noting that they had not spoken that day and telling Ward to "call [him] tomorrow
morning or anytime so we can catch up." In a follow-up e-mail to Ward, Steele appears to be
surprised and confused at Ward's instruction to halt work. Steele's e-mail states: "After you sent
me the attached e-mail we spoke in person and you said for me to keep going and that you do not
want to be the one dragging behind." Steele indicates that Ward told him to "keep going" on "that
day at Barnes and Nobles."
Meanwhile, construction continued. In one of Ward's next e-mails to Steele, dated
October 29, 2008, he indicates to Steele that he is "greatly disturbed" about an invoice "received for
a period of performance that exceed[s] the date in which I requested and informed that all work was
to cease on this project." At this point, construction on the foundation stopped on Panté's order.
Following this, the e-mails between Ward and Steele became increasingly antagonistic, with Steele
demanding money and support and Ward demanding that Steele cease all building work. The
exchanges culminated in a February 16, 2009 e-mail from Ward to Steele informing Steele that
Panté's attorney instructed him to "cut communication" for the time being.
Panté argues that the e-mail evidence proves that Steele lacked Panté's authority to
order the foundation's construction. It points to several of Steele's progress reports in which he
requests Ward's permission to proceed on the foundation work--e-mails that were sent well after
the point at which Steele claimed he had authority to begin construction. Through his testimony,
however, Steele provided an explanation. Steele testified that he "asked for permission [to go ahead
with the Austin contract] about ten times . . . because certain times I did have permission, certain
times I didn't." Steele testified that Ward had a tendency to get "cold feet" as the project progressed
and Panté's investment increased. He also stated that Ward would "blow hot and cold" on the same
issues from one day to the next, which led Steele to view Ward's seemingly clear instructions with
a degree of skepticism.
Viewing the evidence in the light most favorable to the verdict, we conclude that
Steele's testimony, coupled with the documentary evidence, amounts to more than a scintilla of
evidence to support the jury's implied finding that Steele was acting as Panté's agent when he
entered into a contract with Austin. Although there is evidence in the record supporting Panté's
assertion that Steele lacked authority, Steele's testimony that he had Ward's oral permission to
proceed with the foundation work alone is enough evidence to allow reasonable and fair-minded
jurors to conclude that Steele had actual authority from Panté to contract with Austin on Panté's
behalf. As the sole judge of the credibility of the witnesses and the documentary evidence, the jury
could reasonably have chosen to believe Steele's testimony and discount contrary evidence.
Furthermore, the various e-mail exchanges, read as a whole, are ambiguous at best
about Steele's authority or lack thereof. A reasonable jury could have concluded, as Austin argued,
that Ward's lack of response to Steele's various progress reports about the continuing foundation
work gave rise to a reasonable inference that Ward knew about Steele's actions and agreed with them
or at least acquiesced in them. Although Ward testified that his health did not allow him to respond
immediately to many of those e-mails, his testimony does not render such an inference unreasonable
as a matter of law. Thus, we conclude that the jury's verdict was supported by legally sufficient
evidence. Likewise, after considering and weighing all the evidence, we cannot say that the
judgment is so contrary to the overwhelming weight of the evidence as to be clearly wrong and
unjust. Although Panté presented evidence in support of its assertion that Steele lacked
actual authority, Steele's testimony to the contrary was detailed. We conclude, therefore, that
the trial court's judgment is supported by factually sufficient evidence. We overrule Panté's
first three issues.
Fiduciary Duty
In its fourth issue, Panté asserts that it presented conclusive evidence that Steele
breached his fiduciary duty to Panté. In the alternative, Panté argues in its fifth issue that the jury's
finding that Steele complied with his fiduciary duty is not supported by factually sufficient evidence.
Waiver
As a preliminary matter, we consider sua sponte whether Panté waived these
two issues by failing to comply with several rules of appellate procedure. See, e.g., Vortt
Exploration Co. v. EOG Res., Inc., No. 11-07-00159-CV, 2009 WL 1522661, at *2 (Tex.
App.--Eastland May 29, 2009, no pet.) (mem. op.) ("An appellate court has the inherent power to
control its own docket."). Issues four and five challenge the jury's findings as to Steele's alleged
breach of fiduciary duty, yet Panté failed to (1) name Steele as an appellee on the cover of its
appellant's brief; (2) name Steele as an appellee in its list of parties and counsel in its appellant's
brief, (4) see Tex. R. App. P. 38.1(a); (3) list Steele as an appellee in its docketing statement, see id.
R. 32.1(e); or (4) serve Steele with copies of any of its filings in this Court, see id. R. 9.5. (5) It is too
late to correct these deficiencies, especially the last one. In light of these violations, we hold that
Panté has waived its appellate issues against Steele. See id. R. 25.1 ("Any party's failure to take any
other step required by these rules, . . . does not deprive the appellate court of jurisdiction but is
ground only for the appellate court to act appropriately, including dismissing the appeal."); Whiteside
v. Ford Motor Credit Co., 220 S.W.3d 191, 193 (Tex. App.--Dallas 2007, no pet.) (positing without
deciding that appellant waived issues by failing to comply with rules, but addressing the merits);
Mixson v. Kirby Lumber Co., 298 S.W. 476, 477 (Tex. Civ. App.--Beaumont 1927, no writ)
(striking appellant's issues for failure to properly serve appellee). Notwithstanding this waiver by
Panté, we will, in the interest of justice, briefly address the merits as to issues four and five.
The Merits
The elements of breach of fiduciary duty are: the existence of a fiduciary relationship,
and a breach of duty by the fiduciary that causes damages to the client or improper benefit to the
fiduciary. Burrow v. Arce, 997 S.W.2d 229, 237 (Tex. 1999); see also Beck v. Law Offices of
Edwin J. (Ted) Terry, Jr., P.C., 284 S.W.3d 416, 429 (Tex. App.--Austin 2009, no pet.). In Texas,
an agent is a fiduciary of his principal. Johnson v. Brewer & Pritchard, P.C., 73 S.W.3d 193, 200
(Tex. 2002). Because of that "special relationship," the agent must (1) act primarily for the benefit
of the principal; (2) account to the principal for profits arising out of the agency; (3) not act for, or
on the account of, a party whose interests are adverse to the principal's; (4) not compete with the
principal in matters relating to the agency; and (5) deal fairly with the principal in all transactions
between them. Id. (citing Restatement (2d) of Agency § 387 (1958)).
Panté asserts that Steele violated his fiduciary duty by advancing his own interests
and those of his fledgling company, Construction & Company, ahead of Panté's. Panté asserts that
"[b]ecause of Steele's focus on showcasing himself as a builder through the Parade of Homes, he
ignored Ward's requests to wait for completed plans before beginning the foundation, and he ignored
Ward's request to stop work." Panté points to three specific ways that Steele breached his fiduciary
duty: (1) by excluding Panté from the advertising materials for the Parade of Homes and "only
giving his name and his company's name," (2) "by 'apparently' committing Panté to financial
obligations with Austin," and (3) "by not stopping the foundation work when he was told to stop."
Panté argues that there is "conclusive evidence" to establish Steele's breach of fiduciary duty. "A
matter is conclusively established if ordinary minds could not differ as to the conclusion to be
drawn from the evidence." W.H.V., Inc. v. Associates Hous. Fin., LLC, 43 S.W.3d 83, 87 (Tex.
App.--Dallas 2001, pet. denied).
Based on the evidence presented at trial and discussed above, we cannot say that
"ordinary minds could not differ as to the conclusion to be drawn from the evidence" relevant to
Steele's alleged breach of his fiduciary duty. See id. As we have already discussed, there was
enough evidence for a reasonable jury to find that Steele had actual authority to proceed with the
foundation construction as he did. In finding that Steele complied with his fiduciary duties to Panté,
the jury could have focused on Steele's testimony that he had Panté's permission to contract with
Austin and build the foundation. Crediting that testimony, the jury could have found that Steele
complied with his fiduciary duty by following the orders of his principal. Further, Steele's failure
to include Panté's name in the advertising for the Parade of Homes is not a per se breach of his
fiduciary duty. This is especially true in light of the contradictory testimony about the parties' roles
in the project--i.e., whether Steele was the "builder" and Panté the "owner" or whether they were
"co-builders." Given this contradictory testimony, the jury could have concluded that Steele was the
sole "builder" on the project. Accordingly, failing to list Panté as a "co-builder" in the Parade of
Homes advertising documents is not conclusive evidence that Steele acted improperly. We conclude
that the record contains more than a scintilla of evidence to support the jury's finding that Steele
complied with his fiduciary duty to Panté.
Finally, after considering all the evidence, we cannot say that the evidence supporting
the jury's verdict is so weak as to make the finding clearly wrong and unjust. Thus, the verdict is
supported by factually sufficient evidence.
We overrule Panté's fourth and fifth issues.
CONCLUSION
Having overruled Panté's issues on appeal, we affirm the trial court's judgment.
__________________________________________
J. Woodfin Jones, Chief Justice
Before Chief Justice Jones, Justices Puryear and Pemberton
Affirmed
Filed: October 7, 2010
1. The Spanish Oaks Parade of Homes was a marketing event organized by the developer of
the subdivision to "showcase" several new-home builders. Essentially, the parade was a coordinated
series of open houses providing an opportunity for builders to display their best designs to potential
clients and "kick-start" demand for the neighborhood.
2. The court instructed the jury in the relevant law of agency, which is discussed below.
3. Ward himself was equivocal about Panté's relationship with Steele. Ward testified:
Q. Do you agree that [Steele] was your builder?
A. [Steele] was hired--let me be very clear, as it relates to "builder" so everyone
can understand as it relates to the roles and definition.
Q. Can you answer my question first?
A. Was he my builder?
Q. Yes, sir.
A. For the Spanish Oaks property?
Q. Yes, sir, the only one we're talking about.
A. No and yes.
Ward then explained that Steele was hired to perform various tasks in preparation for building the
house in Spanish Oaks, among other remodeling and construction jobs, but that the parties did not
have a formal "contractual" relationship. Later, however, when questioned by Austin's counsel,
Ward admitted that Panté published a prospectus that was distributed to potential investors listing
Steele and his then-existing construction firm as one of Panté's "builders."
4. In the "Identity of Parties and Counsel" section of Panté's brief, Steele is listed as
"Defendant Non-suited below."
5. We note that Panté's notice of appeal, a copy of which was mailed to Steele, was
sufficiently broad to invoke this Court's jurisdiction over Steele and Panté's issues against him. See
Tex. R. Civ. P. 25.1(b) ("The filing of a notice of appeal by any party invokes the appellate court's
jurisdiction over all parties to the trial court's judgment or order appealed from.").