Panhandle Eastern Pipe Line Co. v. Michigan Consolidated Gas Co.

173 F. Supp. 738, 1959 U.S. Dist. LEXIS 3358
CourtDistrict Court, E.D. Michigan
DecidedMay 15, 1959
DocketCiv. A. No. 7518
StatusPublished

This text of 173 F. Supp. 738 (Panhandle Eastern Pipe Line Co. v. Michigan Consolidated Gas Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panhandle Eastern Pipe Line Co. v. Michigan Consolidated Gas Co., 173 F. Supp. 738, 1959 U.S. Dist. LEXIS 3358 (E.D. Mich. 1959).

Opinion

LEVIN, District Judge.

This action by Panhandle Eastern Pipe Line Company (hereinafter referred to as Panhandle) seeks to recover $601,354.-39 from Michigan Consolidated Gas Company (hereinafter referred to as Consolidated) an amount deducted by Consolidated from amounts due to Panhandle for deliveries of gas from July 23 through October 31, 1948, hereinafter referred to as the 101-day curtailment period. Consolidated contends that this sum was lawfully withheld as a setoff from payments made for gas delivered during that period, and that in addition to the setoff it is entitled by way of counterclaim to recover $548,067.1

Panhandle is a Delaware corporation owning and operating a natural gas pipeline system. In 1948 the main line of Panhandle consisted essentially of two pipe-line systems extending approximately 1,100 miles from the natural gas producing area in the Texas and Oklahoma Panhandles, and extending across the State of Kansas, Missouri, Illinois, Indiana and Ohio, and terminating in the State of Michigan. This main pipe line begins in southwestern Kansas at Panhandle’s Liberal Compressor Station in the town of Liberal. Between Liberal and Detroit there are twelve compressor stations, as shown on the map accompanying this opinion. The basic func[740]*740tion of a compressor station is to raise the suction pressure to a higher discharge pressure by which the gas is moved along to the next station.

[741]*741Most of Panhandle’s customers were served under so-called full requirement contracts wherein the customers were entitled to take all the gas they needed at any time without limitation. Some customers, including Consolidated, were served under maximum contract limitations wherein they were permitted to take all of their gas requirements up to the contract limitation. Panhandle also sold gas on an interruptible basis. Such sales are subject to curtailment when the gas is needed to meet present requirements of customers receiving gas on a firm basis.

It takes three days for gas to be pumped from Panhandle’s station in Kansas to Detroit. Quantity changes in customers’ demands occur due to day-to-day and seasonal variations in home and industrial requirements. Panhandle stationed a dispatcher at its Kansas City office to attempt to forecast the demands of customers and to change operating conditions to meet them. Customer demands, however, are not determinable with mathematical accuracy, and it was not possible for Panhandle to operate its pipe line with hundreds of delivery points precisely on a designed theoretical basis for an extended period.

On August 31, 1935 (prior to the enactment of the Natural Gas Act) Panhandle entered into a contract with Consolidated. This contract, as supplemented and amended, provided that Panhandle would sell and deliver to Consolidated, and that Consolidated would purchase “all of the natural gas requirements of Buyer [Consolidated] for distribution and sale to any and all of its present and future customers and for its own use” up to, but not in excess of 125,000,000 cubic feet per day (125,000 Mcf).2

With the enactment of the Natural Gas Act on June 21, 1938 (52 Stat. 821-833, Title 15 U.S.C.A. § 717-717w) Panhandle’s service to Consolidated became subject to the jurisdiction of the Federal Power Commission. In 1946 the Commission authorized Panhandle to deliver 3,100,000 Mcf per month to Michigan Gas Storage Company, a Michigan corporation, not a party to this action, during the months of May, July, August and October, and 3,000,000 Mcf per month during June and September, or an average of 100,000 Mcf per day during this period. Prior to 1948 Consolidated did not take the maximum volume of gas permitted by its contract with Panhandle. In 1948 Consolidated undertook new interruptible sales and began taking deliveries to the full contract limit. The increased take of defendant and delay by Panhandle in completing a proposed construction program resulted in a shortage of gas in the area east of Panhandle’s Edgerton Indiana Compressor Station, which is the most easterly compressor station before the gas enters Michigan. The Commission on March 23,1948, instituted an investigation of this shortage. (Docket No. G-1023). Hearings were held and on July 17, 1948 the Commission issued opinion No. 166 and an accompanying order. In its opinion the Commission stated:

“ * * * we are unwilling to make a finding with respect to the availability east of Edgerton station of specific volumes of gas. Rather we believe that Panhandle will exert every reasonable effort to deliver through that station the largest volume of gas possible; and we shall expect that, if necessary to do so, and to the extent required, Panhandle will make appropriate curtailment of interruptible deliveries pursuant to the provisions of effective tariffs and contracts.”

The pertinent part of the order provides as follows:

“Upon consideration of the entire record herein, and in conformity with our Opinion No. 166 adopted this date, it is ordered that:
“(B) Until October 31,1948, Panhandle Eastern Pipe Line Company [742]*742shall make deliveries to Michigan Consolidated Gas Company at Detroit and to Michigan Gas Storage Company of such volumes of natural gas as may be available after making deliveries to all of its other customers east of its Edgerton Compressor Station (including deliveries provided for in Paragraph (A) hereof), pursuant to the provisions of the effective, tariffs and contracts, as follows:
“Panhandle shall deliver to Michigan Consolidated 52% and to Michigan Gas Storage 48% of such available volumes of natural gas until such date as the total volumes delivered to both such companies from and after May 15, 1948, shall have reached a proportion of 55.6% to Michigan Consolidated and 44.4% to Michigan Gas Storage; and, from such date until October 31, 1948, such volumes of gas as may be available for delivery to these two companies shall be delivered by Panhandle on a daily basis in the proportion of 55.6% to Michigan Consolidated at Detroit and 44.4% to Michigan Gas Storage. Any variation in the daily delivery to either customer from the aforesaid percentages shall be adjusted within seven days.”

Panhandle instituted this action in 1948, seeking damages against Consolidated in seven counts totaling approximately $2,000,000. Consolidated filed a counterclaim asking damages in excess of $1,000,000. The counterclaim was based on the contractual provision which provides that in the case of deficiencies in delivery, Panhandle is to “reimburse * * * Buyer [Consolidated] for any * * * loss * * * which it may sustain by reason of such failure, including the expense of putting into operation any gas manufacturing equipment, and/or obtaining manufactured gas or natural gas to remedy such deficiency.” The counterclaim was dismissed by this court on a motion for summary judgment, on the ground that the court had no jurisdiction to consider the counterclaim as it was a matter solely within the purview of the Federal Power Commission. This court also entered a judgment of no cause of action on Counts I, II, III, V, and VII but determined that Panhandle was entitled to recover $601,354.39 on Counts IV and VI, an amount which Consolidated had set off against the amounts due_ Panhandle for deliveries of gas to Consolidated during the curtailment period. Panhandle Eastern Pipe Line Company v. Michigan Consolidated Gas Company, D.C., 117 F.Supp. 551.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
173 F. Supp. 738, 1959 U.S. Dist. LEXIS 3358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panhandle-eastern-pipe-line-co-v-michigan-consolidated-gas-co-mied-1959.