Pan-Alaska Construction, Inc. v. State, Department of Administration, Division of General Services

892 P.2d 159, 1995 Alas. LEXIS 29, 1995 WL 124675
CourtAlaska Supreme Court
DecidedMarch 24, 1995
DocketNo. S-6082
StatusPublished
Cited by2 cases

This text of 892 P.2d 159 (Pan-Alaska Construction, Inc. v. State, Department of Administration, Division of General Services) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pan-Alaska Construction, Inc. v. State, Department of Administration, Division of General Services, 892 P.2d 159, 1995 Alas. LEXIS 29, 1995 WL 124675 (Ala. 1995).

Opinion

OPINION

MOORE, Chief Justice.

I. INTRODUCTION

This case concerns an alleged abuse of administrative discretion by the Department of Administration (DOA) in its handling of a contractor’s claim for reimbursement of reasonable bid preparation costs. This is the second time that the contractor, Pan-Alaska Construction, Inc. (Pan-Alaska), has appealed its case to this court. See Pan-Alaska Constr., Inc. v. State, Dep’t of Admin., Mem. Op. & J. No. 537 (Alaska, February 27,1991) (Pan-Alaska I). In Panr-Alaska I, we reversed the superior court’s denial of Pan-Alaska’s claim and remanded with instructions for the DOA to afford the contractor an administrative hearing. Id. at 4-5.

[160]*160Following the ordered hearing, the hearing officer denied Pan-Alaska’s claim, finding that Pan-Alaska had failed to prove that the State was liable for the contractor’s bid preparation costs under former AS 44.77.010(c). Pan-Alaska appealed, arguing that in light of the DOA’s decision to reimburse three other claimants for costs expended in preparing bids for the same procurement, the denial of its claim violated the corporation’s right to equal protection. The superior court affirmed the DOA’s decision. We also affirm, holding that Pan-Alaska has not proved its entitlement to bid preparation costs under either a statutory or equal protection theory.

II. FACTS AND PROCEEDINGS

The involved history of this case spans over ten years of administrative and legal proceedings. In late 1984, the DOA requested that contractors submit bids to design and build the Anchorage Office Complex (AOC), a procurement that the State had previously cancelled twice. Five contractors submitted proposals, including Pan-Alaska. The DOA sent a notice of award to Dick Fischer Development No. 2, Inc. (Dick Fischer), but terminated the project less than three months later in June 1985. The State has since cited several reasons for cancelling the AOC project, including a lack of legislative support and problems with financing. Dick Fischer Dev. No. 2., Inc. v. Department of Admin., 838 P.2d 263, 266 (Alaska 1992) (case arising out of same cancelled procurement).

In response to the cancellation, within four months Dick Fischer and two unsuccessful bidders other than Pan-Alaska submitted claims to the DOA for bid preparation costs. DOA regulations require that claims for reimbursement be submitted within six months of the date the services were provided. AS 44.77.010(a); 2 AAC 25.010(b). Former AS 44.77.010(e)1 provided the standard by which aggrieved bidders could recover bid preparation costs, but required claimants to prove that their bid proposals were rejected “wrongfully]” or that the bid solicitation was cancelled in an “arbitrary and unreasonable” manner.

After considering the three bidders’ claims, DOA Commissioner Eleanor Andrews decided to partially reimburse their bid preparation costs not as a matter of statutory entitlement, but rather due to “overriding policy concerns.” In an October 1985 memorandum to Governor William Sheffield, she expressly discounted any liability the DOA might have to the bidders, but acknowledged that, in her judgment, the DOA should reimburse their bid costs:

I have concluded that, under the circumstances of this procurement, it is fair and appropriate for the state to pay reasonable bid preparation costs. The project has a long and unfortunate history of false starts dating well before this administration.... Each procurement prompts bidders to spend considerable time and money toward preparation of a proposal.... I believe it fundamentally unfair to ask bidders to bear the economic burden of the state’s repeated decision to cancel the procurement in midstream. Bidders have repeatedly responded in good faith on AOC procurements, and we should respond accordingly if we expect bidders to have confidence in subsequent procurements for major state office facilities.... My decision, in sum, is not based on a finding of legal liability, but on independent policy considerations.

(Emphasis added.)

A team of auditors reviewed the three contractors’ claims to assess their reasonable expenses. Due to the complexity of the structure of each claim, by February 1986 the Commissioner opted to extend each claimant a uniform payment of $238,222. This amount was determined by dividing the total funds appropriated for the AOC project by the number of bidders who had submitted claims. Dick Fischer Dev. Co., 838 P.2d at 265.

Pan-Alaska submitted its claim for reimbursement of bid preparation costs in April 1986, ten months after the cancellation of the AOC project. DOA Commissioner Andrews denied Pan-Alaska’s $303,380 claim by a letter dated May 22, 1986, on the grounds that it was submitted after the expiration of the [161]*161six-month time limitation set by DOA regulation 2 AAC 25.010(b), and that it failed to articulate a basis for legal entitlement under AS 44.77.010(c). The Commissioner noted that her “decision to pay limited bid preparation expenses to the three bidder groups who submitted timely claims has no bearing on [Pan-Alaska’s] legal entitlement to recoup bid preparation costs.”

Pan-Alaska appealed the DOA’s denial of its claim. In an October letter, Commissioner Andrews granted Pan-Alaska the opportunity to show at an administrative hearing “good cause” why its claim for bid preparation costs should be accepted as timely. If “good cause” could be shown, Pan-Alaska would be given a second hearing on the merits of its claim.

At the administrative hearing in March 1987, the DOA stipulated that Pan-Alaska had shown sufficient “good cause” to obtain a waiver of any applicable time limitation on its claim for bid preparation costs. The DOA formally “accepted” Pan-Alaska’s claim, but noted that the stipulation was “binding upon the parties only as to the issue of timeliness.”

Instead of proceeding to a hearing on the merits, counsel for the DOA then denied Pan-Alaska’s claim by letter. It stated that even though Pan-Alaska’s claim was regarded as timely, the “policy decision made by former Commissioner Andrews during the Sheffield administration to pay a portion of the bid preparation cost of some of the bidders on the AOC” would not be carried forward by the new administration of Governor Steven Cowper. Moreover, it concluded that Pan-Alaska lacked any other factual or legal basis for entitlement, and that any applicable administrative procedures should be considered “exhausted.”

Pan-Alaska filed suit against the DOA in June 1987. In its motion for summary judgment, Pan-Alaska argued that by reimbursing all claimants except Pan-Alaska, the DOA failed to treat similarly situated parties alike, thereby violating the contractor’s right to equal protection under article I, section 1 of the Alaska Constitution.

The State filed a cross-motion for summary judgment, contending that Pan-Alaska must show that the DOA cancelled the AOC procurement arbitrarily or capriciously in order to recover bid preparation costs under AS 47.77.010(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
892 P.2d 159, 1995 Alas. LEXIS 29, 1995 WL 124675, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pan-alaska-construction-inc-v-state-department-of-administration-alaska-1995.