Palos Verdes Properties v. County Sanitation District No. 5

177 Cal. App. 2d 679, 2 Cal. Rptr. 537, 1960 Cal. App. LEXIS 2533
California Court of Appeal·Decided February 8, 1960·No. Civ. 23966·Published·Cited by 4 cases

Opinion

KINCAID, J. pro tem. *

Defendant appeals from a judgment in an action for declaratory relief and for damages. The judgment ordered, adjudged and decreed that defendant be required by the terms of the July 1, 1955, agreement of the parties as amended, to accept the transfer from plaintiff of the latter’s right, title and interest in and to that portion *681 of the South Slope Trunk sewer line here in question and to pay to plaintiff the sum of $193,828.55, together with interest and costs.

Defendant, as a sanitation district of Los Angeles County, owned and operated sewer lines, with the usual appurtenances, and plaintiff is a land developer in the Palos Verdes area of said county.

In June, 1955, the parties decided that it was to their mutual interest to enter into a written agreement providing for the construction and acquisition of a trunk sewer line on the Palos Verdes Peninsula. It was to be known as the South Slope Trunk and was to connect with defendant’s existing White Point Outfall facilities. Thereafter such an agreement was drafted by defendant and it was executed by the parties on July 1, 1955.

Because of defendant’s lack of available funds and the mutual desire for early construction it was agreed that plaintiff was to advance the necessary money and would sell and transfer the sewer to defendant for a price equal to the total actual and direct costs of construction as determined by defendant’s chief engineer.

The agreement provided that defendant was to prepare plans and specifications for the construction of the South Slope Trunk and present same to plaintiff for approval. Upon receipt of such approval, defendant’s chief engineer was to proceed, as agent for plaintiff, with the calling for bids and the entering into of contracts for the construction and completion of the sewer. Defendant was to furnish, at no cost to plaintiff, engineering, inspection and supervision required to complete the construction, and to furnish all necessary advertising and proceedings incidental to the receipt of bids and the award of contracts. Defendant was to have the exclusive right to determine to whom contracts were to be awarded by plaintiff, and of selection of all materials and equipment to be used in the construction.

Defendant additionally agreed to prepare plans and specifications, award contracts, and inspect, supervise and approve construction of the Trunk, in sufficient time to assure completion of the line in a usable condition within one year from July 1, 1955.

Defendant agreed to obtain all necessary rights of way, including occupational rights of way, and plaintiff agreed to pay the cost of acquisition thereof if demanded by de *682 fendant, the cost, if paid by plaintiff, to be deemed a part of the direct cost of construction.

It was further agreed that no payment for the cost of any part of the Trunk should.be made by plaintiff without approval of defendant’s chief engineer. Plaintiff agreed that it would not approve or accept a job from a contractor engaged in doing the work of construction until plaintiff had first received written certification from defendant’s chief engineer that the job had been completed in accordance with the plans and specifications prepared by defendant, and certifying that the job was ready for acceptance by plaintiff. Upon completion of the Trunk in accordance with the plans and specifications, defendant’s chief engineer was to certify that fact in writing to plaintiff and to defendant, together with his certification of the total, actual, and direct cost of construction approved by him.

It was further agreed that upon receipt of such certification plaintiff would sell and defendant would purchase said Trunk and appurtenant works by documents of title approved by defendant’s counsel for a sum equal to the total costs thereof as certified.

The final paragraph of the agreement provides that defendant, in preparing plans and specifications, advertising for bids, awarding contracts, requiring bonds, and inspecting and supervising the work, would in all possible respects follow the customary procedure employed and used by it with respect to its own contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Palos Verdes Properties v. County Sanitation District No. 5, 177 Cal. App. 2d 679, 2 Cal. Rptr. 537, 1960 Cal. App. LEXIS 2533 (Cal. Ct. App. 1960).

177 Cal. App. 2d 679 (Palos Verdes Properties v. County Sanitation District No. 5) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chevron U.S.A. v. IRA Administrators CA3
California Court of Appeal, 2015
Household Finance Corp. v. Arlett (In Re )
22 B.R. 732 (E.D. California, 1982)
Long v. Keller
104 Cal. App. 3d 312 (California Court of Appeal, 1980)
Krone v. Goff
53 Cal. App. 3d 191 (California Court of Appeal, 1975)