PALMISANO v. CROWDERGULF, LLC

CourtDistrict Court, D. New Jersey
DecidedJune 16, 2023
Docket3:17-cv-09371
StatusUnknown

This text of PALMISANO v. CROWDERGULF, LLC (PALMISANO v. CROWDERGULF, LLC) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PALMISANO v. CROWDERGULF, LLC, (D.N.J. 2023).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW JERSEY

JOSEPH PALMISANO, JAY Civil Action No. HAJESKI, SEAN WALL, WALTER 3:17-cv-9371 (PGS)(TJB) EVERETT, and MATTHEW MANIBUSAN individually and on MEMORANDUM behalf of all other similarly situated,

Plaintiff,

v.

CROWDERGULF, LLC, BIL-JIM CONSTRUCTION CO., INC., MAPLE LAKE, INC., R. KREMER AND SON MARINE CONTRACTORS, LLC, ABC CORPORATIONS (1-100), DEF CORPORATIONS (1-500), and JOHN DOES (1-10), et al.,

Defendants.

BIL-JIM CONSTRUCTION CO., INC., Third-Party Plaintiff, v.

TOWNSHIP OF BRICK, Third-Party Defendants

This case is before the Court on four motions for summary judgment: (1) Plaintiffs (ECF No. 121); (2) Defendant CrowderGulf, LLC (ECF No. 126); (3) Defendants BIL-JIM Construction Co., Inc. and Maple Lake, Inc. (collectively Bil-Jim) (ECF No. 129); and (4) third-party Defendant Township of Brick (Brick)

(ECF No. 132). All of the motions seek a determination of whether the wages paid to the named Plaintiffs are subject to the New Jersey Prevailing Wage Act (PWA). More specifically, the named Plaintiffs are employees of Bil-Jim or a related entity

who allege that they were underpaid because their wages were less than the amount that should have been paid under the PWA. (N.J.S.A. 34:11-56.25, et. seq.). The moving parties agree that the crux of the four motions hinges on whether the PWA applies to the type of work performed.

I. When Hurricane Sandy struck and devastated the New Jersey coastline on or about October 29, 2012, extensive government relief was required to restore the

coastline communities (recovery services). Hurricane Sandy caused extraordinary damage throughout the State, especially in coastal areas, including beaches and waterways. In order to provide recovery services, government aid was required from local, state and federal governments. In this case, the recovery services were

subject to two separate projects – a Municipal Project (Bil-Jim/Brick), and a State Project (CrowderGulf/DEP). The terms of the contracts for each project are discussed separately below. The only common thread between the State and Municipal Projects is that Bil-Jim was involved with debris removal on both projects.

Brick/Bil-Jim (Municipal Project) Prior to Hurricane Sandy, Bil-Jim entered into a three-year “Snow Removal Services” contract with Brick (July 19, 2011). (ECF No. 132-6). Snow removal

services are exempt from the PWA. The snow removal services contract was operative in October, 2012 – when Hurricane Sandy struck. On October 29, 2012, Hurricane Sandy devastated Brick and its beaches. In order to provide relief to many municipalities like Brick, then Governor Chris Christie authorized the use of

snow removal funds for Hurricane Sandy recovery services. On November 5, 2012, the Governor issued Executive Order 111, which provided that: [a] local government unit that has established a snow removal fund pursuant to N.J.S.A. 40A:4-62.1, may, by resolution, utilize existing reserves as necessary to protect the safety, security, health, and welfare of its citizens from the damage caused by Hurricane Sandy . . .

Executive Order No. 111 (Nov. 5, 2012). 44 N.J.R. 2985(a) (Dec. 3, 2012). At that time, Brick and Bil-Jim did not negotiate a new contract for Hurricane Sandy recovery services; instead, the parties agreed to be bound by the terms of the existing snow removal contract. This required Bil-Jim to “prepar[e] for the impending storm,” and clear debris from the public rights of way by pushing it to the sides of the roads using front-end loaders, skid steers, and rubber tire backhoes. (ECF No. 123-2, ¶ 4).

The scope of the recovery work by Bil-Jim was extraordinary. Initially, “clearing the streets” provided access to neighborhoods for emergency vehicles, and subsequently Bil-Jim removed and disposed of the debris. For example, Walter

Everett testified that after Hurricane Sandy hit “[w]e cleaned up sand from all the streets and debris from the streets.” (ECF No. 123-2, ¶6). According to Mr. Everett, this debris consisted of “[e]verything from basic garbage, house doors, . . . brick, [and] vehicles . . . piece of homes . . . [t]ree limbs . . . and [a]ppliances[.]”

(ECF No. 123-2, ¶6). Glenn Campbell, former Director of Public Works for Brick, testified that “[t]here was 525,000 tons of debris that needed to be removed.” (ECF No. 123-2, ¶7). Similarly, Andrew Johnson, a foreman and estimator for Bil-Jim,

described the municipal project: The work initially started with preparation for the impending storm, and then it evolved to rescuing individuals from their residence that were flooded and submerged in water. It then evolved to clearing the public right of way of debris and sand so that the emergency services could access portions of the township and conduct physical searches of homes, structures, for any signs of life or fatalities just to make sure those structures were cleared. And then it continued with debris removal from public property and a screening operation to screen some sand and place the sand back on the beach. (Johnson Dep.1, JT.180:17- JT.181:4, ECF No. 122).

Johnson explained that preparing for the storm involved mobilizing and transporting approximately two bulldozers to Brick and demobilizing transporting equipment away from the site. (JT.181:14 - JT.182:24). At an early stage, Bil-Jim rescued stranded Brick residents with approximately four front loaders carrying people in the bucket. (JT.182:25 - JT.183:13). According to Johnson, Bil-Jim commenced clearing the roads on or about

November 1, 2012 and continued until March or April, 2013. (JT.184:3-6). Bil- Jim performed road clearance on the mainland and the barrier island. (JT.187:2-4). On or about November 30, 2012, streets on the mainland were clear to the extent

that the debris had been pushed to the side of the road. (JT.187:20-24). In December, the debris remaining on the side of the road was transported to a staging area where it was sorted. (JT.187:25-JT.118:10). Roads on the barrier island were also cleared by pushing the debris to the side of the road. (JT.188:18-22). Bil-Jim

operated front end loaders, skid steers, rubber tire backhoes, various trucks including dump trucks and pick trucks2. (JT.190:8-25). Debris, not mixed with sand, “went directly – loaded on trucks and directly to the landfill.” (JT.196:4-7).

If there was debris mixed with a large amount of sand, such debris was loaded and

1 “JT” refers to the deposition of Andrew Johnson. 2 A pick truck is equipped with a hydraulic arm. (JT.191:9-12). transported to a staging area where it was screened to separate the debris from the sand, using a trammel. (JT.96:15- JT.100:25). Bil-Jim then transported sand to the

beach where it “fill[ed] in any voids or depressions or low-lying areas that the Office of Emergency Management deemed to be a public safety hazard.” (JT.196:17-19).

State Project (CrowderGulf/DEP) The scope of the State Project covered a much broader area than the Municipal Project, and it principally focused on clearing waterways. Bil-Jim and other companies performed dredging work under the State Project Contract. (ECF

No. 126-1, ¶ 51). More specifically, Bil-Jim, or an affiliate (Maple Lake, Inc.), were subcontractors to CrowderGulf (ECF No. 67 ¶18); and Bil-Jim subcontracted some of its work to R. Kremer and Son Marine Contractors, LLC, (Kremer) (ECF

No. 67 ¶ 24). Under its subcontract with CrowderGulf, Bil-Jim removed artificial debris, sand, and other natural debris from waterways (using long-reach excavators), transported the debris to shore, and sifted it with a trammel. (JT.72:8– 19; JT.75:11 – 22; JT.83:1 - JT.84:12; JT.85:21 - JT.86:1; JT.96:12 - JT.97:9).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hunt v. Cromartie
526 U.S. 541 (Supreme Court, 1999)
Best v. C&M Door Controls, Inc.
981 A.2d 1267 (Supreme Court of New Jersey, 2009)
Department of Labor v. Titan Construction Co.
504 A.2d 7 (Supreme Court of New Jersey, 1985)
Ali Razak v. Uber Technologies Inc
951 F.3d 137 (Third Circuit, 2020)
Ali Razak v. Uber Technologies Inc
979 F.3d 192 (Third Circuit, 2020)
Marr v. ABM Carpet Service, Inc.
669 A.2d 864 (New Jersey Superior Court App Division, 1995)
Bankston v. Housing Authority
777 A.2d 74 (New Jersey Superior Court App Division, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
PALMISANO v. CROWDERGULF, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmisano-v-crowdergulf-llc-njd-2023.