Palmer v. County of Shasta

245 P. 777, 76 Cal. App. 672, 1926 Cal. App. LEXIS 485
CourtCalifornia Court of Appeal
DecidedFebruary 27, 1926
DocketDocket No. 3053.
StatusPublished

This text of 245 P. 777 (Palmer v. County of Shasta) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmer v. County of Shasta, 245 P. 777, 76 Cal. App. 672, 1926 Cal. App. LEXIS 485 (Cal. Ct. App. 1926).

Opinion

*673 PLUMMER, J.

Action by plaintiffs to recover balance alleged to be due upon a contract for the construction of an approach to Anderson Free Bridge in the County of Shasta, state of California. The plaintiffs had judgment in the sum of $10,568.04. From this judgment the defendant appeals.

On or about the tenth day of September, 1920, the plaintiffs and defendant entered into a contract for the construction of an approach to the Anderson Free Bridge in Shasta County. The approach was to consist of a re-enforced concrete bridge 560 feet in length, of 14 spans. The contract price for the bridge was the sum of $39,000. At a later date a supplemental contract was entered into, which changed the dates of payment provided for in the original contract, but otherwise leaving the original contract in full force and effect. The plans and specifications were prepared by C. R. Weigel, county surveyor of Shasta County, and the bridge was constructed under the personal inspection of Mr. Wiegel and his deputy. According to the defendant’s interpretation, the bridge was designed as a simple span bridge, of spans 40 feet in length resting upon piers, with expansion joints on the even-numbered piers and construction or stop joints on the odd-numbered piers. There is no controversy as to the expansion joints being provided for in the plans and specifications, or as to the piers where the expansion joints were to be placed and were placed. There is controversy as to whether construction joints were provided for in the plans and specifications. After the work had been finished according to plans and specifications, as interpreted by the plaintiffs, there appeared certain defects in the bridge, to remedy which the defendant expended the sum of some $12,955. The defendant also filed a counterclaim in which it alleged the expenditure of this sum of money to complete the bridge according to the plans and specifications; that the plaintiffs had not finished the bridge according to contract and plans and specifications; that there was due the plaintiffs for the work performed by them the sum of $10,464.94, and that by reason of thé expenditures made by the defendant, as just alleged, there was a balance due to the county of the sum of $2,490.53. The amount claimed by the plaintiffs was the sum of $18,406.22. Upon trial the court gave judgment for the plaintiffs in the sum first herein mentioned.

*674 It is alleged by the defendant that construction joints were omitted from the fixed piers; that expansion joints were not properly constructed; that the cement used in the construction of the bridge was deficient in quantity and that different materials from those provided in the specifications were substituted by the contractors. As to the substitution of materials, it may be here stated that the court found that the specifications called for" half-inch spacing bars and the bars actually used were only three-eighths inch in size; that the difference in value was the sum of $150, or thereabouts, credit for which was given to the county and that the substitution in the size of the bars did not in anywise affect the strength of the bridge.

It appears from the record that there are two types of construction used in the erection of concrete bridges such as the approach to the Anderson Free Bridge. One is called the continuous span and the other is a simple span. A simple span bridge in this instance would be the construction of each span independently, that is, 40 feet at a time, with a construction joint over every alternate pier with an expansion joint between the alternate piers. The construction joint consists simply of placing an abutment at the end of alternate spans and pouring the concrete up to the abutment, letting it set, then removing the abutment and proceed with the pouring of the cement of the next following span. A continuous span bridge is one in which expansion joints are placed over the piers or abutments at the end of alternate spans and over the solid or fixed piers the re-enforcing steel is continuous, including reverse bending moment steel. This steel holds the deck of the bridge rigid and prevents it from cracking. In the simple span the reverse bending moment steel and the re-enforcing steel both end at the expansion joint and also at the opposite end of the span at the so-called fixed pier. It would appear from the testimony that cracks are inevitable in concrete bridge construction and therefore it is necessary to have the cracks occur on the line across the bridge that will not affect its supporting strength. If the crack occurs at the end of the girder which is near the center of the pier, the supporting strength of the girder is not affected, but if it occurs at the point where the girder reaches the pier, the crack becomes very material. It is also necessary to have expan *675 sion joints sufficiently near together to permit the come and go of the bridge as it may be affected by climatic conditions. Controverting the claims of the defendant, the plaintiffs set forth that construction joints were not provided for in the plans and specifications to be placed over alternate piers, that in fact no construction joints were provided for, that the plans and specifications were defective in their reference to expansion joints and called for the use of material not calculated to function properly, that the defects in the bridge were due to the defects in the plans and specifications and not in the work performed by the plaintiffs.

The trial court found that the plaintiffs had substantially complied with their contract, had built the bridge according to the plans and specifications, that expansion joints were constructed according to the plans and specifications, that construction joints were not ordered placed over any of the piers. The court also found that the plaintiffs had done extra work in the sum of $3,149.13 and that the defendant was entitled to credit for materials furnished and for work done in stripping forms and back-filling, etc., in the total sum of $2,339.09, leaving due the plaintiffs the sum for which judgment was entered herein. The court also gave judgment to the plaintiffs for interest on the amount of the judgment from the third day of November, 1921, the date on which the plaintiffs alleged completion of their contract.

Practically no questions of law are involved in this case. The appeal is brought to us upon questions of fact and the allegation that certain findings of the court relating to the points which we have herein stated are not supported by the evidence. It is further argued on the part of the appellant that the findings are in conflict with the uncontradicted evidence and that the finding, in substance, that the plans and specifications did not call for construction joints over the piers is against uncontradicted evidence. We do not quite see how this claim can be made in view of the fact that the findings printed in this case and called to our attention show that upon every material point the finding of the court is based upon conflicting testimony. There is also testimony in the record of a substantial nature which, if believed by the trial court, is sufficient to sustain every finding challenged in this case. We might rest our decision upon the statement that our investigation of the record shows the *676

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
245 P. 777, 76 Cal. App. 672, 1926 Cal. App. LEXIS 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmer-v-county-of-shasta-calctapp-1926.