Palladino v. Mayor of New York

3 Silv. Ct. App. 390
CourtNew York Court of Appeals
DecidedFebruary 6, 1891
StatusPublished

This text of 3 Silv. Ct. App. 390 (Palladino v. Mayor of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palladino v. Mayor of New York, 3 Silv. Ct. App. 390 (N.Y. 1891).

Opinion

Daniels, J.

The action was brought to recover the amount claimed to be unpaid for regulating and grading Fort George avenue from Tenth to Eleventh avenues, and setting curbstones and flagging sidewalks therein. The work was let by a contract, executed by the commissioner of public works and James H. Sullivan, on or about the 17th of August, 1886. And after it had been in part performed, the contract was assigned to the plaintiff, who completed [391]*391the work. His claim consisted of two items. The first was 0 for money retained by the city from the contract price, amounting to the sum of $432.02. And the other was for the value or cost of material used for filling on the avenue to bring it up to the grade adopted for the improvement.

It was claimed on behalf of the defendant that it was entitled still to retain the balance remaining unpaid upon the contract price of the work, because of proceedings taken to establish a lien against the contract or by other persons. But the evidence tended so directly to prove that this lien had been satisfied as to leave no substantial reason for doubting the right of the plaintiff to recover the amount of this balance. And accordingly the verdict of the jury in his favor for that sum, together with the interest upon it, should not be unnecessarily disturbed.

But the claim made by the plaintiff for filling furnished by him to raise the street to the grade prescribed, stands upon different grounds. For by the terms of the proposals for the contract, no material of this description was included or required to be furnished. But the entire work, as proposals were invited for it, consisted of earth and rock to be excavated, curbstones to be furnished and set, and flagging stones to be furnished and laid. The amount of this work and materials were included in the published proposals. But no material for filling was mentioned, nor required to be estimated, which should be obtained, or supplied by the person whose proposals should be accepted for the performance of the work.

The work was ordered by a resolution adopted by the aldermen on the 11th, and approved by the mayor on the 18th of May, 1885. And this work was directed to be done under the action of the commissioner of public works. And sealed estimates for this work were invited by a notice published, as the charter required that to be done, in the early part of July, 1886. When the resolution was approved by the mayor, the earth included within the line of the [392]*392avenue to be regulated and graded had not been disturbed or removed. But after that, and in the year 1885, a large part of the earth in the avenue, which was capable of being used to fill the lower portions of it up to the prescribed grade, had been taken and carried away. This was alleged to have been done through the act, default and neglect of the defendant, its officers and agents. And the plaintiff, as the assignee of the contract afterwards entered into for the grading and improvement of the avenue, insisted that the city was responsible to him for the removal of this earth. But it appeared by the evidence that it was not so removed by any person acting in its employment, or under its authority, or even with its knowledge. But the persons who removed.it were trespassers, having no right whatever to take it, and themselves alone liable for the wrong in this manner committed. Upon these facts, therefore, no right of compensation for the earth removed within the lines of the avenue existed against the defendant.

It was further insisted on behalf of the plaintiff that he was entitled under the contract to recover the value of the earth obtained and used by himself from other localities in filling the avenue up to its requisite grade. This claim proceeded upon the ground that it was mentioned in the specifications, which were inserted in the contract, that the “ street which is above the grade line is to be excavated, and such and so much of the material excavated as may be fit for the purpose, and as may be necessary, shall be filled in those parts of the street which are below the grade lines in the manner hereinafter provided; the material excavated not so used for filling shall be removed from the street; if the amount of material excavated that is fit for filling shall not be sufficient to regulate the street, the contractor shall furnish and supply material of proper kind and quality sufficient for the purpose, but only the difference between the total quantity of filling to finish grade and line, as shown in cross section, and the total quantity of excavation to the [393]*393finished grade and line, as shown in cross section, with slopes in each case as herein described, will be considered as filling to be furnished, and as such to be paid for.

And the contract itself declared that: “ For any work the price of which is not specified in this contract, the provisions herein contained in relation to work not provided for in this contract shall apply.” But no other provision appears to have been inserted in the contract relating to this subject, beyond that which was made a part of the specification. And while the difference in the quantity of filling exceeding that supplied by the earth taken from the avenue itself is stated to be considered as filling to be furnished, and as such to be paid for, there is yet no provision in the contract binding the defendant to make such payment. But, on the contrary, it was agreed by the contractor that he would receive in full for his compensation for furnishing all the materials and labor for, and the faithful performance of the whole of the work mentioned in the agreement, the following prices :

For excavating earth, per cubic yard, the sum of twenty- ■ seven (27) cents.

For excavating rock, per cubic yard, the sum of ninety-five (95) cents.

For furnishing and setting new curbstone, per linear foot, the sum of sixty-seven (67) cents.

For furnishing and laying new flagging, per square foot, the sum of thirty-one (31) cents.

And by a preceding part of the agreement it was also agreed by the contractor that he would, “ at his or their own cost and expense, furnish and provide all the materials and labor for the purpose of regulating and grading Fort George avenue from Tenth to Eleventh avenue, and set curbstones and flag sidewalks therein.” And that he would “complete the entire work to the satisfaction of the commisioner of public works and in substantial accordance with said specifications and the plan therein mentioned, and that he [394]*394will not ask, demand, sue for or recover for the entire work any extra compensation beyond the amount payable for the several classes of work in this contract enumerated, which shall be actually performed, at the prices therefor herein agreed upon and fixed.”

It was further declared that “ this contract is made with reference to the proposals for estimates for the above described work hereto annexed, which are to be taken as part and parcel of these presents.” And in and by the proposals it was stated that “no extra compensation beyond the amount payable for the several classes of work before enumerated, which shall be actually performed, at the prices therefor to be specified by the lowest bidder, shall be due or payable for the entire work.”

And also that “ work or materials not specified, and for which a price is not fixed in the contract, will not be allowed for.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mulholland v. Mayor, Aldermen Commonalty, N.Y.
20 N.E. 856 (New York Court of Appeals, 1889)
Poillon v. . City of Brooklyn
4 N.E. 191 (New York Court of Appeals, 1886)
Nelson v. Mayor of New York
63 N.Y. 535 (New York Court of Appeals, 1876)
Brady v. . the Mayor, C., of the City of New York
20 N.Y. 312 (New York Court of Appeals, 1859)
Syracuse Water Co. v. . City of Syracuse
22 N.E. 381 (New York Court of Appeals, 1889)
McDonald v. Mayor of New York
68 N.Y. 23 (New York Court of Appeals, 1876)

Cite This Page — Counsel Stack

Bluebook (online)
3 Silv. Ct. App. 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palladino-v-mayor-of-new-york-ny-1891.