Palek Corp. v. A.P. O'Horo Co., Unpublished Decision (3-6-2007)

2007 Ohio 1121
CourtOhio Court of Appeals
DecidedMarch 6, 2007
DocketNo. 05 MA 141.
StatusUnpublished
Cited by1 cases

This text of 2007 Ohio 1121 (Palek Corp. v. A.P. O'Horo Co., Unpublished Decision (3-6-2007)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palek Corp. v. A.P. O'Horo Co., Unpublished Decision (3-6-2007), 2007 Ohio 1121 (Ohio Ct. App. 2007).

Opinion

OPINION *Page 2
{¶ 1} Appellant Palek Corp. appeals a judgment of the Mahoning County Court of Common Pleas in a civil case involving a contract dispute. Appellant was a subcontractor in a bridge renovation project being completed by Appellee A.P. O'Horo Co., the general contractor. Appellant began painting the steel components of the bridge, but encountered problems with concrete residue that had recently been deposited on the steel during the repair process. Appellant worked for eight days, completing 30% of the job, and then stopped. On or about the time Appellant stopped work, Appellee asked Appellant to produce a liability insurance certificate as required by the contract. Appellant did not provide the required insurance, and was soon replaced by another subcontractor. Appellant sued for breach of contract in the amount of $39,360. Appellee filed a counterclaim also alleging breach of contract but seeking the amount of $77,042.38. The trial court granted judgment to Appellee on the original complaint, and also judgment in the counterclaim, with an offset for the work that Appellant had completed, resulting in an award to Appellee of $28,130.62.

{¶ 2} Appellant argues on appeal that Appellee waived the insurance requirement by waiting eight days after work had started before requesting proof of insurance. The record does not support this argument. Although the lack of sufficient liability insurance may not have been the primary dispute between the parties, the record reveals that it was a condition of the contract, was not waived, and was breached by Appellant. Therefore, the trial court was correct.

{¶ 3} The relevant facts in this case are not particularly in dispute and are set out quite succinctly in the magistrate's decision. In November of 2000, Appellee *Page 3 submitted its bid to the Ohio Department of Transportation to serve as the general contractor for the renovation of two bridges in Ashtabula County, Ohio. Appellee was awarded the contract. Appellant submitted the lowest estimate to Appellee to do the final painting work of the steel components of the bridges, and on January 29, 2001, Appellant was awarded the subcontract to paint the bridges for the amount of $129,112.00.

{¶ 4} One of the conditions of the subcontract was that Appellant was to provide Appellee with certificates of liability insurance with limits of not less than $2 million per each occurrence. The exact wording of the insurance requirement is as follows:

{¶ 5} "Prior to commencing work under this Agreement, the Subcontractor shall furnish to the Contractor Certificates of Insurance evidencing coverage written thru an insurance company licensed to transact business in the state where the work is located which meets the following:

{¶ 6} "* * *

{¶ 7} "The types and minimum requirements are as follows:

{¶ 8} "a.) Commercial General and Umbrella Liability Insurance. Subcontractor shall maintain commercial general liability (CGL) and if necessary, commercial umbrella liability with a limit of not less than $2,000,000 each occurrence.

{¶ 9} "* * * *Page 4

{¶ 10} "b.) Business Auto and Umbrella Liability Insurance. Subcontractor shall maintain business auto liability and, if necessary, commercial umbrella liability insurance with a limit of not less than $2,000,000 each accident. * * *" (Contract, p. 9.)

{¶ 11} The contract also contains the following provision concerning the insurance certificate:

{¶ 12} "Contractor shall have the right, but not the obligation, of prohibiting Subcontractor or any of their subcontractors from entering the project site until such certificates or other evidence that insurance has been placed in complete compliance with these requirements is received and approved by Contractor. Failure to maintain the requiredinsurance may result in termination of this contract byContractor." (Emphasis added.) (Contract, p. 10.)

{¶ 13} In July, 2001, Appellee advised Appellant that the bridges were ready to be painted. Appellant began performing the preparation and painting work on August 1, 2001. As Appellant was preparing the steel to be painted, it found that there was an unusual amount of hardened concrete slurry on the surface of the steel, and that this was slowing down the painting process. The parties all agree that some concrete residue was expected to be found on the steel as a byproduct of the rehabilitation of the bridges. This residue occurs during the removal of the old concrete road surface of the bridge. The concrete is removed by cutting it with a powerful diamond-edged saw that is cooled with water, and the resulting concrete dust mixes with the water to form a slurry that drips down to the lower surfaces of the *Page 5 bridge, including the steel framework of the bridge that will later be painted. The slurry normally dries into a powder or thin coating on the surface of the steel support structure underneath. In this particular case, though, there was apparently more dried slurry residue than usual.

{¶ 14} Appellant worked at the bridge site until August 8, 2001, at which time the problem of the excess dried slurry was brought to Appellee's attention. Appellant stopped all work at the site on August 10, 2001, having completed approximately 30% of the work.

{¶ 15} On August 13, 2001, Appellant sent Appellee a letter asking for an additional $24,600 to complete the contract. Appellant also stated that it needed an answer by the end of the day or else it would have to mobilize to a different job site and that there would be an extra charge when the crew returned to work on the two bridges.

{¶ 16} On or about August 10, 2001, Appellee asked Appellant to produce a certificate of liability insurance in the amount of at least $2,000,000, as required by the contract. Appellee also requested a payment and performance bond for $129,112.00, a maintenance bond, a current workers compensation certificate, and two copies of Appellant's safety program.

{¶ 17} Appellant removed at least some of its equipment on or about August 15, 2001. It is not clear from the record whether Appellant removed the equipment of its own volition, or whether it left in response to a verbal directive from Gerald ("Jerry") Bailey, Appellee's project manager. *Page 6

{¶ 18} Appellant could not obtain a $2,000,000 insurance certificate. Appellant's certificate of insurance listed a $1,000,000 limit, and Appellant was not able to obtain any more insurance coverage. The parties attempted to procure additional insurance for the next four weeks, but were unsuccessful.

{¶ 19} On September 11, 2001, Appellee sent a letter to Appellant, which stated that: "We must have the correct documentation in our office no later than September 14, 2001 at 12:00 noon. If the proper documents are not received or complete in their presentation our only option is to cancel your subcontract and have the bridge painting completed by another painting contractor." Appellant did not submit the proper documentation by September 14, 2001.

{¶ 20}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hitchcock v. Denison
2017 Ohio 9328 (Ohio Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2007 Ohio 1121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palek-corp-v-ap-ohoro-co-unpublished-decision-3-6-2007-ohioctapp-2007.