P.A.L. Environmental Safety Corp. v. North American Dismantling Corp.

CourtDistrict Court, E.D. Michigan
DecidedMarch 10, 2023
Docket2:19-cv-11630
StatusUnknown

This text of P.A.L. Environmental Safety Corp. v. North American Dismantling Corp. (P.A.L. Environmental Safety Corp. v. North American Dismantling Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P.A.L. Environmental Safety Corp. v. North American Dismantling Corp., (E.D. Mich. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

P.A.L. ENVIRONMENTAL SAFETY CORP.,

Plaintiff/Counter-Defendant,

v. Civil Case No. 19-11630 Honorable Linda V. Parker NORTH AMERICAN DISMANTLING CORP., NORTH AMERICAN SPECIALTY INSURANCE COMPANY, and CONSUMERS ENERGY COMPANY,

Defendants.

And

NORTH AMERICAN DISMANTLING CORP.,

Counter-Plaintiff / Cross-Plaintiff,

v.

CONSUMERS ENERGY COMPANY,

Cross-Defendant. __________________________________/

OPINION AND ORDER GRANTING NORTH AMERICAN DISMANTLING CORP.’S MOTION TO VOLUNTARILY DISMISS COUNT II OF ITS AMENDED COUNTERCLAIM [ECF NO. 81]

This is a diversity action arising out of a breach of contract dispute. The matter is presently before the court on North American Dismantling Corp.’s (“NADC”) “Motion to Voluntarily Dismiss Count II of its Amended Counterclaim Without Prejudice,” filed on July 19, 2022. (ECF No. 81.) The motion has been

fully briefed. (ECF Nos. 83, 84, 87.) Finding the facts and legal arguments sufficiently presented by the parties, the Court is dispensing with oral argument with respect to the parties’ motions pursuant to Eastern District of Michigan Local

Rule 7.1(f). For the reasons that follow, the Court is granting NADC’s motion. FACTUAL BACKGROUND The following facts are undisputed. On August 4, 2017, NADC entered into a written agreement (“Prime Contract”) with Consumers Energy Company

(“Consumers”) for the abatement, dismantling, and demolition of the JC Weadock Power Plant (henceforth “the Project”). Specifically, the Prime Contract provided that NDAC was responsible for the abatement and removal of any Asbestos

Containing Material (“ACM”) at the Project. However, because ACM abatement work requires a contractor to be licensed under Michigan and federal law, and NADC lacked the necessary license, NADC entered into a “Subcontract Agreement” with PAL—who was licensed for ACM abatement—on August 29,

2017. The amount agreed upon for services under the Subcontract was $7,996,131.00. (ECF No. 18-8 at Pg ID 658.) On September 18, 2017, PAL began to perform under the agreement. Federal Lawsuit On June 3, 2019, PAL filed the original Complaint against NADC,

Consumers, and North American Specialty Insurance Company. (ECF No. 1.) On July 15, 2019, NADC filed an Answer to the Complaint, ECF No. 11, and a Counterclaim against PAL. (ECF No. 12.) In the Counterclaim, NADC alleges

that PAL failed to complete the work “on or before October 31, 2018,” which was the date provided under the “Contract Schedule.” (Id. at Pg ID 307, ¶¶ 30, 32.) Further, NADC alleges that as a result of PAL’s failure to complete the work, the demolition portion of the Project was delayed. NADC’s Counterclaim alleges the

following counts: breach of contract for failure to timely complete the work (Count I); breach of contract for failure to pay employees, agents, and subcontractors (Count II); indemnification regarding claims brought against NDAC by

Consumers1 (Count III); and breach of contract regarding work performed under a second subcontract between NADC and PAL, involving PAL working with Indiana Power and Light Company (“IPL”) (Count IV.). On August 16, 2019, PAL filed a motion to dismiss Count IV of NADC’s

counterclaim, ECF No. 22, which the Court granted on May 28, 2020. (ECF No.

1 At the time of the filing of the original Counterclaim, NADC maintains that it filed the indemnity claim “anticipating that Consumers . . . would seek damages from NADC due, at least in part, to PAL’s [alleged] failure to timely and properly abate the asbestos from Consumers’ Weadock Power Plan prior to its demolition by NADC.” (ECF No. 84 at Pg ID 3173.) 39.) On October 16, 2020, PAL filed an Amended Complaint, ECF No. 44, to which NADC filed an Amended Counterclaim on October 20, 2020. (ECF No. 46.)

In the Amended Counterclaim, NADC alleges the following against PAL: breach of contract for failure to timely complete the work (Count I); and indemnification regarding the claims brought against NADC by Consumers (Count II).

State Lawsuit On June 16, 2020, Consumers filed a separate complaint against NADC in the Lapeer County Circuit Court. See Consumers Energy Company v. North American Dismantling Corp., Case No. 20-053835-CK; (Ex. D., ECF No. 46-5.)

In the lawsuit, Consumers claims that NADC breached the Prime Contract causing numerous damages. Specifically, Consumers alleges the following: breach of contract (Count I), express contractual indemnity (Count II), negligence, errors,

and omissions (Count III); and breach of fiduciary duty and duty to act in good faith (Count IV). On December 10, 2020, NADC filed a motion for summary disposition in light of the instant federal court case, “believing that the claims pled [by

Consumers] should have been brough as part of [the federal] case.” (ECF No. 81 at Pg ID 3096, ¶ 6.) On January 21, 2021, the state court denied NADC’s motion to dismiss and NADC was unsuccessful at appealing the ruling with the Michigan

Court of Appeals. (Id. ¶ 7.) On May 16, 2022, NADC filed a third-party complaint against PAL seeking indemnification “should Consumers prevail on its claims against NADC.” (Id. ¶ 9; ECF No. 83 at Pg ID 3110-11.) Subsequently, on

June 17, 2022, PAL filed a motion for summary disposition on NADC’s third- party complaint. On January 27, 2023, the state court issued an order staying the proceedings pending this Court’s ruling.

LEGAL STANDARD Under Rule 41(a), which governs voluntary dismissals, “an action may be dismissed at the plaintiff’s request only by court order, on terms that the court considers proper.” FED. R. CIV. P. 41(A)(2). It is within the court’s sound

discretion to determine whether a dismissal should be granted. See Grover by Grover v. Eli Lilly & Co., 33 F.3d 716, 718 (6th Cir. 1994) (citing Banque de Depots v. National Bank of Detroit, 491 F.2d 753, 757 (6th Cir. 1974)). The rule’s

primary purpose of creating a requirement that the court approve a voluntary dismissal is “to protect the nonmovant from unfair treatment. Id. (citing Ikospentakis v. Thalassic S.S. Agency, 915 F.2d 176, 177 (5th Cir. 1990)). A district court is found to abuse its discretion “only where the defendant

would suffer ‘plain legal prejudice’ as a result of a dismissal without prejudice, as opposed to facing the mere prospect of a second lawsuit.” Bridgeport Music, Inc. v. Universal-MCA Music Pub., Inc., 583 F.3d 948, 953 (6th Cir. 2009) (quoting

Grover, 33 F.3d at 718)). Under the Sixth Circuit, to determine whether a defendant may be subjected to plain legal prejudice, a court must consider “the defendant’s effort and expense of preparation for trial, excessive delay and lack of

diligence on the part of the plaintiff in prosecuting the action, insufficient explanation for the need to take a dismissal, and whether a motion for summary judgment has been filed by the defendant.” Walther v. Fla. Tile, Inc., 776 F.

App’x 310, 315 (6th Cir. 2019) (quoting Grover, 33 F.3d at 718.) “These factors are neither exhaustive nor conclusive” Id.; see also Malibu Media, LLC v. [Redacted], 705 F. App’x 402, 407 (6th Cir. 2017) (“These factors are only a guide, however, and the trial judge ultimately retains discretion to grant the motion

to dismiss.”) (citation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Banque De Depots v. National Bank of Detroit
491 F.2d 753 (Sixth Circuit, 1974)
Larrabee v. Sachs
506 N.W.2d 2 (Michigan Court of Appeals, 1993)
Malibu Media v. David Ricupero
705 F. App'x 402 (Sixth Circuit, 2017)
Grover v. Eli Lilly & Co.
33 F.3d 716 (Sixth Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
P.A.L. Environmental Safety Corp. v. North American Dismantling Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pal-environmental-safety-corp-v-north-american-dismantling-corp-mied-2023.