Paktin Construction Company v. United States

CourtUnited States Court of Federal Claims
DecidedApril 19, 2021
Docket19-1817
StatusPublished

This text of Paktin Construction Company v. United States (Paktin Construction Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paktin Construction Company v. United States, (uscfc 2021).

Opinion

In the United States Court of Federal Claims No. 19-1817 (Filed: 19 April 2021)

*************************************** PAKTIN CONSTRUCTION COMPANY, * * Plaintiff, * Statute of Limitations; 28 U.S.C. 2501; * Accrual Suspension Rule; Rule 12(b)(1); v. * Standing; Fifth Amendment; Taking Clause; * Substantial Connection Test. THE UNITED STATES, * * Defendant. * * ***************************************

Daniel Marino, Marino Finley LLP, of Washington, D.C., with whom was Tillman Finley, Marino Finley LLP, of Washington, D.C., for plaintiff.

Miles Karson, Trial Attorney, Commercial Litigation Branch, Civil Division, Department of Justice, with whom were Joseph Hunt, Assistant Attorney General, Robert Kirschman, Jr., Director, Kenneth Dintzer, Deputy Director, all of Washington DC, for defendant. James Van Debergh, U.S. Army Corps of Engineers, of Washington DC, Assistant Counsel for Litigation.

OPINION AND ORDER

HOLTE, Judge

When the government engages in a long-running partnership with a foreign entity assisting the advancement of United States interests in a war zone, does the Constitution prohibit the government from taking the entity’s property without just compensation? That is the question plaintiff presents to the Court. Afghan plaintiff Paktin Construction Company alleges the United States took its property without compensation in violation of the Fifth Amendment. Before 2011, plaintiff “maintained a business relationship with Coalition Forces in Afghanistan for many years,” and plaintiff’s work in the reconstruction and repair of local infrastructure damaged during the war was praised as “unparalleled thus far.” According to plaintiff, in 2011, while it was working on a major development on behalf of the Army Corps of Engineers, the Army unilaterally terminated the contract and refused to return plaintiff’s equipment or provide compensation. Plaintiff’s efforts to retrieve its property continued for years, culminating in the Army instructing plaintiff to “never ask about the matter anymore” and leading to the present dispute. A foreign national receives constitutional protections when they operate within United States territory or have developed substantial connections with the United States over time. The government filed a 12(b)(1) motion to dismiss for lack of subject matter jurisdiction, arguing this Court does not have jurisdiction to entertain plaintiff’s claim because plaintiff did not raise the claim within six years of its accrual and plaintiff does not have substantial connections with the United States. Based on the facts alleged, including that plaintiff was repeatedly recognized and appreciated by the United States government for almost ten years of contributions to the overseas efforts in Afghanistan, the Court finds plaintiff sufficiently pleads substantial connections to establish standing to sue under the Fifth Amendment. For those and the following reasons elaborated in this Order, the Court DENIES the government’s motion to dismiss.

I. Factual and Procedural History

A. Factual History

The Court draws the following facts from plaintiff’s amended complaint, plaintiff’s response to the government’s motion to dismiss, and plaintiff’s supplemental paper, assuming for the purpose of this motion all factual allegations are true. See, e.g., Boyle v. United States, 200 F.3d 1369, 1372 (Fed. Cir. 2000) (when ruling on a motion to dismiss for failure to state a claim, this Court “must accept all well-pleaded factual allegations as true and draw all reasonable inferences in [plaintiff’s] favor”). Plaintiff is a construction company organized under the laws of Afghanistan and domiciled in Kabul, Afghanistan. Am. Compl., ECF No. 11 at ¶ 2. On 6 August 2011, plaintiff entered into an agreement to act as a subcontractor for Supreme Ideas- Highland Al Hujaz JV (“SI-HAH”), the prime contractor in the construction of a project for the United States Army Corp. of Engineers (“USACE”) in the Paktia Province of Afghanistan. Am. Compl. at ¶ 7. Plaintiff was responsible for performing “planning and construction services under a scope of work . . . and schedule of values . . . for the USACE in accordance with the Prime Contract.” See Declaration of Rahmatullah Zaland (“Zaland Declaration”), ECF No. 16-1 at 1.

SI-HAH informed USACE plaintiff would serve as “the primary subcontractor on this project,” and plaintiff’s employees and representatives “attended and participated in the weekly meetings with USACE personnel regarding the project.” Zaland Declaration at 1. Plaintiff’s job site was subject to the control of the U.S. Army and USACE, and the United States restricted access to the job site to only authorized individuals. Zaland Declaration at 1. Plaintiff’s work was subject to “inspection, testing and, ultimately, acceptance by the United States and the health and sanitary requirements of the USACE” through provisions of USACE’s prime contract with SI-HAH. Am. Compl. at ¶ 9. Pursuant to the subcontractor agreement, plaintiff moved various construction supplies and equipment onto the worksite. Id. at ¶ 10.1

On 25 January 2012, USACE sent a notice to SI-HAH demanding all work under the contract be stopped. Id. at ¶ 11. On the same day, SI-HAH directed plaintiff to stop work on the project and vacate the premises within 10 days of the notice. Id. at ¶ 12. SI-HAH further instructed plaintiff not to remove any materials from the construction site “until [SI-HAH] arranged an inventory procedure with the Government.” Id. While there was “discussion of what amounts were owed and would be paid” to plaintiff and SI-HAH, plaintiff claims the U.S. Government never began a formal inventory procedure of the equipment and materials left at the

1 The specific equipment and supplies plaintiff claims it moved to the job site include “mixers, compactors, vibrators, a welding machine, 207 tons of rebar, 500 bags of cement, piping, multiple generators, two 25,000-liter water tanks, and portable office and living quarters and facilities.” Am. Compl. at ¶ 10.

-2- job site. See Zaland Declaration at 2. Plaintiff claims a “dispute arose over payments” due from SI-HAH to plaintiff which, along with “security concerns,” prevented plaintiff from recovering its property during this time. Am. Compl. at ¶ 13.

During the summer of 2013, plaintiff’s CEO began inquiring whether he would be able to return to the site to retrieve plaintiff’s construction equipment and materials. Zaland Declaration at 2. On 19 July 2013, plaintiff received an email from a representative of the U.S. military informing plaintiff it had until 22 July 2013 to remove some of its property from the construction site. See id. at 21. When plaintiff’s CEO thereafter attempted to approach the construction site to remove its property, U.S. Government personnel informed plaintiff’s CEO he could not enter the site or remove the equipment and threatened him with arrest should he attempt to return. Id. at 2.

On 4 August 2013, a special agent with the United States Special Inspector General for Afghanistan Reconstruction communicated with United States military personnel on the subject of plaintiff’s attempts to recover its property and requested clarification on the dispute. See id. at 2, 22. The special agent informed plaintiff at the time he “would contact a USACE commander and let [plaintiff] know what to do.” Id. at 2. Plaintiff followed up with the special agent on 22 August 2013 and included an inventory list of property still on the construction site but received no response. Id. On 14 September 2013 the U.S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Turner v. Williams
194 U.S. 279 (Supreme Court, 1904)
Russian Volunteer Fleet v. United States
282 U.S. 481 (Supreme Court, 1931)
United States v. Causby
328 U.S. 256 (Supreme Court, 1946)
United States v. Dickinson
331 U.S. 745 (Supreme Court, 1947)
United States v. Dow
357 U.S. 17 (Supreme Court, 1958)
Scheuer v. Rhodes
416 U.S. 232 (Supreme Court, 1974)
United States v. Verdugo-Urquidez
494 U.S. 259 (Supreme Court, 1990)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Ingrum v. United States
560 F.3d 1311 (Federal Circuit, 2009)
North Hartland, L.L.C. v. United States
309 Fed. Appx. 389 (Federal Circuit, 2009)
Atamirzayeva v. United States
524 F.3d 1320 (Federal Circuit, 2008)
Steel Improvement & Forge Company v. The United States
355 F.2d 627 (Court of Claims, 1966)
Hopland Band of Pomo Indians v. The United States
855 F.2d 1573 (Federal Circuit, 1988)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Paktin Construction Company v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paktin-construction-company-v-united-states-uscfc-2021.