Paige International, Inc. v. Xl Speciality Insurance Company

Procedural entryThis page is a short order in Paige International, Inc. v. Xl Speciality Insurance Company. Read the opinion of the Court — 267 F. Supp. 3d 205
District Court, District of Columbia·Decided May 25, 2016·No. Civil Action No. 2014-1244·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

PAIGE INTERNATIONAL, INC.,

Plaintiff, v. Civil Action No. 14-1244 (JEB)

XL SPECIALTY INSURANCE CO., et al., Defendants.

MEMORANDUM OPINION

Plaintiff Paige International and Defendants XL Specialty Insurance Company and its related entities are locked in a heated dispute concerning costs associated with the construction of the Marriott Marquis hotel in Washington, D.C. Paige was a subcontractor on the project, working under Truland Systems Corporation, itself a subcontractor to the prime contractor. When Truland subsequently became insolvent, it ceased work and also stopped paying Paige. Prior to Truland’s insolvency, it took out a bond with Defendants to insure against its failure to pay its subcontractors (including Paige). This suit against the insurers seeks payment under that bond.

XL’s primary argument in defense of full payment is that it has already paid out substantial sums to the prime contractor under a separate performance bond, including reimbursement to cover costs for incomplete and shoddy work by Truland, Paige, and other subcontractors. Defendants thus argue that these costs should be subtracted from what Paige is owed under the payment bond. Determining who owes what to whom is no easy feat, as the overarching construction contract was worth well north of $370 million. To this end, XL has

identified an expert, Donald Harrington, to testify at trial concerning completion-related construction costs in the hopes of reducing Paige’s recovery.

Evidently not content to wait until trial, Paige has now fired off four separate Motions to Strike Harrington’s Report on account of dozens of alleged flaws in his methodology. While these combined Motions are quite lengthy, they can be reduced to the core contention that the contents of the Report fall short of the standard for expert testimony under Federal Rule of Evidence 702. While Plaintiff may certainly challenge Harrington’s testimony at trial, the Court does not believe that his Report should be stricken at this stage of the litigation. It will thus deny the Motions. I. Background Plaintiff Paige International, Inc. is a Washington, D.C.-based corporation that was one of many subcontractors involved in the construction of the Marriot Marquis hotel, built next to the District of Columbia Convention Center. See Compl., ¶ 2; Mot. to Strike I (ECF No. 18) at 2. As with most large construction projects, the prime contractor, Hensel Phelps Construction Company, subcontracted portions of its work, including electrical, fire alarm, security, audio visual, and telecommunications, to a subcontractor, Truland Systems Corporation. See Compl., ¶¶ 7-8; Def. Opp. (ECF No. 27) at 4. Truland, in turn, subcontracted a portion of its work – involving security, audio-visual, and telecommunications – to Paige. See Compl., ¶ 9; Opp. at 4.

Truland purchased a payment bond from XL and its co-Defendants, pursuant to which Defendants, as sureties, pledged to make payments to those persons under contract with Truland who supplied labor, material, and equipment to the project in the event it ever failed to pay. See Comp., ¶ 10. Truland also obtained a performance bond, which similarly provided Hensel Phelps with a guarantee as to compensation in the event Truland failed to perform. See Mot. to

Strike I at 2. When Truland later became insolvent and stopped performing on its contract, it also ceased making payments to its lower-tier subcontractors such as Paige. See Mot. to Strike I at 3. As a result of its failure to meet its contractual obligations, Truland was terminated by Hensel for default and subsequently filed for liquidation in bankruptcy. Id.

Paige’s Complaint here alleges that it “provided labor, materials and equipment to Truland in partial satisfaction of Truland’s subcontract obligations to Hensel Phelps, and is hence a proper claimant under the [payment] Bond.” Compl., ¶ 11. Paige thus seeks payment for contract work completed on behalf of Truland in the amount of $1,854,830, id., ¶¶ 18-20; for extra work performed by Paige in accordance with proposed change orders in the amount of $462,147, id., ¶¶ 22-23; and for additional costs incurred by Paige resulting from Truland’s breach of its implied duty of cooperation and non-interference, to the tune of $762,768. Id., ¶¶ 26-28.

What complicates Paige’s pursuit of reimbursement under the payment bond is that Hensel – as the prime contractor – has already sought to be made whole on the performance bond. After Truland was terminated for default, Hensel demanded that XL and co-Defendants, as sureties, honor their obligation under the performance bond to cover the costs of hiring a replacement subcontractor to complete the electrical portion of the project. See Mot. to Strike I at 3-4. XL claims it ultimately paid Hensel $3,550,000 under the performance bond to cover those additional costs. See Opp. at 4. As a result, XL’s defense is that payments it made under its performance bond associated with completing (and cleaning up after) Paige’s electrical work should be deducted from any payments XL makes to Paige under its payment bond.

In preparing this likely defense, XL relies in part on the contents of an expert report completed by Donald Harrington pursuant to Fed. R. Civ. P. 26(a)(2), which governs expert

witness reports disclosures. See Opp. at 2. Harrington is a senior consultant for Sage Consulting Group, which provides consulting and expert-witness services within the construction industry. See Aff. of Donald Harrington (ECF No. 27), Attach. 2, ¶ 1. Harrington’s Report assesses and allocates responsibility for specific costs associated with finishing the work Truland – and Paige – started but failed to complete.

Seeking to exclude Harrington’s Report, Paige has filed four separate Motions to Strike, each relating to a particular aspect of the dispute:

1. Cleanup/Trash Removal Claim, see Mot. to Strike I (ECF No. 18);

2. Dry[w]all and Painting Claim, see Mot. to Strike II (ECF No. 19);

3. Management Costs, see Mot. to Strike III (ECF No. 20); and 4. Electrical Work Completion Costs. See Mot. to Strike IV (ECF No. 21).

The four Motions collectively exceed 100 pages and include dozens of exhibits. Defendants do not exaggerate in lamenting that “Paige is effectively attempting to litigate this entire case through the Motions.” Opp. at 1. Despite the length of these Motions, Harrington himself examined them and, consequently, revised some of the findings of his original Report. He then generated a Supplemental Report, which supersedes the original and will be the document at all times considered here. See Opp. (ECF No. 27), Exh. A (Supplemental Harrington Report of April 15, 2016). Because Paige has filed its Motions to Strike pursuant to Federal Rule of Evidence 702 and the legal principles enunciated by Daubert v. Merrell Dow Pharmaceuticals, Inc., 509 U.S. 579 (1993), the Court will focus on the admissibility of the Report’s conclusions, rather than on the factual disputes Paige raises.

Free access — add to your briefcase to read the full text and ask questions with AI

Paige International, Inc. v. Xl Speciality Insurance Company, (D.D.C. 2016).

Paige International, Inc. v. Xl Speciality Insurance Company (Paige International, Inc. v. Xl Speciality Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Guerrero
5 F.3d 868 (Fifth Circuit, 1993)
United States v. Richard Junior Frazier
387 F.3d 1244 (Eleventh Circuit, 2004)
Luce v. United States
469 U.S. 38 (Supreme Court, 1984)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
General Electric Co. v. Joiner
522 U.S. 136 (Supreme Court, 1997)
Kumho Tire Co. v. Carmichael
526 U.S. 137 (Supreme Court, 1999)
United States v. Jennifer Juliet Gatling
96 F.3d 1511 (D.C. Circuit, 1996)
Boyar v. Korean Air Lines Co., Ltd.
954 F. Supp. 4 (District of Columbia, 1996)
Lakie v. SmithKline Beecham
965 F. Supp. 49 (District of Columbia, 1997)
C & E SERVICES, INC. v. Ashland, Inc.
539 F. Supp. 2d 316 (District of Columbia, 2008)
Harris v. Koenig
815 F. Supp. 2d 6 (District of Columbia, 2011)
Groobert v. PRESIDENT AND DIRS. OF GEORGETOWN COL.
219 F. Supp. 2d 1 (District of Columbia, 2002)
Graves v. District of Columbia
850 F. Supp. 2d 6 (District of Columbia, 2011)
Hana Financial, Inc. v. Hana Bank
135 S. Ct. 907 (Supreme Court, 2015)
Hana Financial, Inc. v. Hana Bank
735 F.3d 1158 (Ninth Circuit, 2013)
Clay ex rel. Estate of Clay v. Ford Motor Co.
215 F.3d 663 (Sixth Circuit, 2000)
Joy v. Bell Helicopter Textron, Inc.
999 F.2d 549 (D.C. Circuit, 1993)