Page v. United States

56 Ct. Cl. 176, 1921 U.S. Ct. Cl. LEXIS 151, 1921 WL 1241
United States Court of Claims·Decided April 4, 1921·No. No. 32484·Published·Cited by 1 cases

Opinions

Hat, Judge,

delivered the opinion of the court:

This is a suit brought by the plaintiffs against the United States for the sum of $325,931.97.

On May 19, 1906, the plaintiffs entered into a contract in writing with E. A. Hitchcock, Secretary of the Interior, .acting in behalf of the United States, which contract was made in pursuance and by virtue of the act of Congress approved June 17, 1902, and known as the reclamation act. The plaintiffs in said contract undertook to construct and complete the work provided for in Schedules Nos. 2 and 3 of main canal, Payette Boise project, Idaho, in accordance with the terms of the advertisement, proposal, and specifications attached to the contract, and made a part of the same. For this work the plaintiffs wei'e to be paid as provided in the specifications.

It was provided that the work should be commenced within thirty days after the contract was signed by the Secretary of the Interior, and that the same should be completed by March 1, 1908. The work was not completed by the plaintiffs, and on October 27, 1908, the contract was annulled.

In a general way the contract and specifications and the maps, plans, drawings, and profiles furnished to bidders by the defendant set forth the termini, location, dimensions, and proportions of the canal to be constructed. The specifications (par. 12) provided: “Bidders must satisfy themselves as to the nature of the material and as to all local conditions affecting the work, and no information derived from the maps, plans, specifications, profiles, or drawings, or [186] from the engineer or his assistants; will in any way relieve the contractor from any risks or from fulfilling all the terms of his contract. No bid on work depending on local conditions will be considered unless the bidder, his representative, or his engineer has visited the work and made himself familiar with the conditions.” The plaintiffs complain that there was a change in the final location of the canal, and that this final location differed from that shown on the maps and profiles. It is true that the location was different, but it is shown by the evidence that the plaintiffs knew of this final location when it was made, knew that it differed from that indioated on the maps and drawings, but they made no complaints as to the location when made and none during the progress of the work.

The total amount of material to be excavated on schedules 2 and 3 was shown in the estimates furnished plaintiffs to be 583,000 cubic yards, classified as follows: Class 1, 475,000 cubic yards; class 2, 80,000 cubic yards; class 3, 22,000 cubic yards-; class 4,. 6,000 cubic yards. The total quantity of material actually required to be moved by the plaintiffs exceeded largely the total quantity of the estimates submitted to bidders, and was 773,823 cubic yards, classified as follows: Class 1, 470,401 cubic yards; class 2, 119,791 cubic yards; class 3, 23,156 cubic yards; class 4, 60,475 cubic yards. For moving and hauling this material the plaintiffs Avere paid in accordance with the terms of the contract, and under the terms of the contract can not base a claim against the defendant, by reason of the fact that the estimates of quantity of material submitted to bidders differed largely from the quantity of material which they were required to recover and handle. The contract in this connection is as follows: “ The quantities given in the proposal are for the purpose of comparing bids, and are approximate only, and no claim shall be made against the United States on account of any excess or deficiency, absolute or relative, in the same ” (par. 24). It may be well to state here that the Secretary of the Interior extended the time of the contractors, when they asked for it, basing his action upon the fact that the amount of material to be removed was more than had been estimated for, and that there was a change in the amount and kind of [187] work actually required of the plaintiffs and that showed in the estimates. But this did not give to the plaintiffs any right upon which to base a claim against the defendant, especially as the contract further provided: “ The right to make material changes in the quantities listed in the proposal is an essential part of the contract, and bidders must make their estimates accordingly” (par. 25).

There was a material change in the amount and kind of work required to be and actually performed by the plaintiffs from that shown on the plans, drawings, profiles, and specifications. There was a reduction of 1.23 miles in the length of the two schedules, the plans, etc., stating that the length of the two schedules was about 13 miles, but as they were, required to be constructed the length was 11.77 miles; there was also a reduction from that indicated on the maps and drawings in the average depth of the material excavated from the prism of the canal of 1.76 feet on schedule 3, and 0.53 foot on schedule 2. But the contract provided: “ The Secretary of the Interior reserves the right to make such changes in the specifications of work or material at any time as may be deemed advisable, without notice to the surety or sureties on the bond given to secure compliance with the contract, by adding thereto or deducting therefrom, at the unit prices of the contract, or at such allowances for changes of materials as shall be deemed just and reasonable by the engineer, whose decision shall be binding on both parties ” (par. 25).

The plaintiffs complain that they were greatly damaged by reason of the large increase of overhaul made necessary by the change of location, and they undertake to show what that damage was in dollars and cents. But there is no evidence as to this, which can be relied upon. At most, it could only be claimed for as extra work, and this was not done at the time, nor were the terms of the contract complied with which set out specifically what steps the contractor was to take in the event he claimed for extra work. It is true that the change of location did necessitate more overhaul than was indicated by the plans and specifications, but the paragraphs of the specifications above quoted provided for this, and the [188] plaintiffs can not now maintain a claim for doing work for which they were paid the unit prices of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Page v. United States, 56 Ct. Cl. 176, 1921 U.S. Ct. Cl. LEXIS 151, 1921 WL 1241 (cc 1921).

56 Ct. Cl. 176 (Page v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bondurant Construction Co. v. United States
61 Ct. Cl. 593 (Court of Claims, 1926)