Padgett v. Fieldwood Energy L L C

District Court, W.D. Louisiana·Decided January 31, 2020·No. 6:18-cv-00632·Unknown

Opinion

UNITED STATES DISTRICT COURT

WESTERN DISTRICT OF LOUISIANA LAFAYETTE DIVISION RICHARD PADGETT CASE NO. 6:18-CV-00632

VERSUS JUDGE TERRY A. DOUGHTY

FIELDWOOD ENERGY, LLC, ET AL. MAG. JUDGE CAROL WHITEHURST RULING

Pending here are two Motions for Summary Judgment filed by two different Defendants. Defendant Wood Group PSN, Inc. (“Wood Group”) filed the first Motion for Summary Judgment [Doc. No. 56], to which Plaintiff Richard Padgett (“Padgett”) has filed an opposition [Doc. No. 62]. Wood Group has filed a reply to the opposition [Doc. No. 63]. Defendant Fieldwood Energy, LLC (“Fieldwood”) filed the second Motion for Summary Judgment [Doc. No. 58], to which Padgett has filed an opposition [Doc. No. 61]. Fieldwood has filed a reply to that opposition [Doc. No. 66]. Additionally, Defendant Facilities Consulting Group, LLC (“Facilities”), who did not file a Motion for Summary Judgment, has nevertheless filed a response to Padgett’s oppositions to both Motions for Summary Judgment [Doc. No. 69]. For the following reasons, both Motions for Summary Judgment are GRANTED. I. FACTS AND PROCEDURAL HISTORY This litigation arises out of an October 10, 2017 accident involving Padgett, a pipe fitter employed by Fluid Crane Company (“Fluid Crane”). Fluid Crane was hired by Fieldwood to perform offshore construction work, primarily post-hurricane repair work on some of Fieldwood’s offshore production platforms. Fieldwood also hired Facilities to provide a construction consultant in connection with the work. Jason Simmons (“Simmons”), a Facilities employee, was the construction consultant assigned to the work. Fieldwood additionally hired Wood Group to provide production workers for its offshore platforms. Randall Mitchell (“Mitchell”) was an employee of Wood Group and was assigned to work for Fieldwood as a Production Operator. On the day of the accident, Fieldwood had

tasked Mitchell with inspecting WD70-D, an offshore production platform, with regard to damage caused by Hurricane Nate. After arriving at the platform, Mitchell discovered that a four-inch drainpipe was leaking and needed to be repaired before the platform could be brought back into production. Mitchell reported this to the area construction supervisors for Fieldwood, who then requested that the Fluid Crane crew go to the platform and perform the repairs. As Production Operator, Mitchell was then tasked with drying out the platform generator and getting the generator back online. Thus, Fieldwood’s only direct involvement in the drain repair project was limited to directing the Fluid Crane crew to the platform to repair the drains. Mitchell was also the crane operator on the platform. When the Fluid Crane crew

arrived by crewboat, Mitchell facilitated the transfer of the construction equipment to the platform by crane. He then showed the leaking drainpipe to Simmons and to Khamla “Chicago” Vilayphanh, the foreman of the Fluid Crane crew. Chicago prepared a Job Safety Analysis (“JSA”) outlining what operations the construction crew was going to perform. All of the personnel on the platform attended a safety meeting. Mitchell signed the JSA as the Production Person in Charge and then returned to his duties. The drain line was approximately 6 to 8 feet above the flooring. As it was late in the day

2 by the time the Fluid Crane crew arrived, the plan was for Padgett, using a safety harness, to perform a preliminary assessment to determine the extent of repairs needed and for the Fluid Crane crew, using scaffolding, to perform the actual repairs the next day. Padgett climbed up to the drain line that was to be repaired, attached his safety lanyard to the drain line, and was in the process of attempting to attach his second lanyard to an I-beam, when he shifted his weight to the

drain line, which then fell, bringing Padgett down with it. Padgett suffered injuries as a result of the fall. On May 11, 2018, Padgett filed a Complaint against Defendants Fieldwood and Facilities alleging negligence on the part of those Defendants, including an asserted duty of Fieldwood to provide him with a safe place to work or to otherwise ensure his safety. [Doc. No. 1]. On February 12, 2019, Padgett filed his First Amended Complaint adding Wood Group as an additional Defendant and alleging that Fieldwood was responsible for the defective and ruinous condition of the drainpipe. [Doc. No.23]. On January 10, 2020, Wood Group filed its Motion for Summary Judgment, seeking

judgment as a matter of law dismissing Padgett’s claims against it on the grounds that its employee, Mitchell, was at all times employed as a Production Supervisor on the platform and was not charged with supervising or giving instructions to the independent contractors on site, including Padgett’s employer Fluid Crane, or to the construction supervisor, Simmons, who was employed by Facilities. [Doc. No. 56]. Wood Group further contends that it was entitled to rely upon the expertise of the independent contractors conducting the construction operations, and, therefore, Padgett’s claims against it should be dismissed. On that same day, Fieldwood filed its Motion for Summary Judgment asserting that it is

3 entitled to judgment as a matter of law dismissing Padgett’s claims against it because it does not owe Padgett a legal duty under the circumstances of this case. Fieldwood further contends that it is not liable for the negligence or fault of its independent contractors and that it was not independently negligent as a matter of law. [Doc. No. 58]. In his oppositions, Padgett does not contest Wood Group’s or Fieldwood’s independent

contractor arguments. Instead, Padgett’s oppositions are devoted to narrating a version of the evidence that blames Facilities’ employee, Simmons, for the accident because he did not order scaffolding to be erected prior to Padgett’s inspection of the drainpipe to be repaired. Padgett argues that scaffolding should have been used at all times in this case and that Fieldwood’s own Bureau of Safety and Environmental Enforcement (“BSEE”) mandated Safe Work Practices in fact required scaffolding. With specific regard to Wood Group’s motion for summary judgment, Padgett states that the issue before the Court is whether Fieldwood delegated any duties regarding the administration and execution of its BSEE-mandated Safe Work Practices to Wood Group. In

the event the Court finds that Fieldwood did not delegate any such responsibilities under the facts of this case, Padgett agrees that Wood Group is entitled to summary judgment, and he has no objection to it. [Doc. No. 62]. In its reply, Wood Group asserts that Padgett had failed to produce any evidence which would support a negligence claim against Wood Group or Wood Group’s employee, Mitchell, as Mitchell had no operational control and had no duty to intervene into the operations of Padgett’s employer, Fluid Crane. Wood Group further submits that the contractual relationship between Fluid Crane and Fieldwood, who assigned Mitchell to the platform, makes it clear that Fluid

4 Crane was responsible for the safety of Padgett and for providing trained personnel to work on the platform, as an independent contractor. [Doc. No. 63]. With specific regard to Fieldwood’s motion for summary judgment, Padgett states that the issue before the Court is whether Fieldwood can legally delegate the administration and execution of its BSEE-mandated Safe Work Practices to Facilities (and its employee Simmons),

as a consultant, and whether in fact it effectively did so in this case. In the event the Court finds that Fieldwood can legally delegate such responsibilities to Facilities and Simmons, and under the cited facts did in fact effectively do so, Padgett agrees that Fieldwood is entitled to summary judgment, and he has no objection to it. [Doc. No. 61].

Free access — add to your briefcase to read the full text and ask questions with AI

Padgett v. Fieldwood Energy L L C, (W.D. La. 2020).

Padgett v. Fieldwood Energy L L C (Padgett v. Fieldwood Energy L L C) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Norman v. Apache Corp.
19 F.3d 1017 (Fifth Circuit, 1994)
Graham v. Amoco Oil Co.
21 F.3d 643 (Fifth Circuit, 1994)
Coulter v. Texaco, Inc.
117 F.3d 909 (Fifth Circuit, 1997)
Roberts v. Cardinal Services, Inc.
266 F.3d 368 (Fifth Circuit, 2001)
Turner v. Baylor Richardson Medical Center
476 F.3d 337 (Fifth Circuit, 2007)
Rodrigue v. Aetna Casualty & Surety Co.
395 U.S. 352 (Supreme Court, 1969)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Davenport v. Amax Nickel, Inc.
569 So. 2d 23 (Louisiana Court of Appeal, 1990)
Guillory v. CONOCO, INC., CONTINENTAL OIL COMPANY
521 So. 2d 1220 (Louisiana Court of Appeal, 1988)
Davis v. Dynamic Offshore Resources, L.L.C.
865 F.3d 235 (Fifth Circuit, 2017)
Jana Davidson v. Rockwell International Cor
882 F.3d 180 (Fifth Circuit, 2018)
JMCB, LLC v. Bd. of Commerce
336 F. Supp. 3d 620 (M.D. Louisiana, 2018)
Landry v. Huthnance Drilling Co.
889 F.2d 1469 (Fifth Circuit, 1989)