Paddleford v. State

103 Misc. 398
CourtNew York Court of Claims
DecidedMay 15, 1918
DocketNo. 2400-A
StatusPublished

This text of 103 Misc. 398 (Paddleford v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Paddleford v. State, 103 Misc. 398 (N.Y. Super. Ct. 1918).

Opinion

Cunningham, J.

On the 11th day of June, 1912, the claimants made a contract with the state, through the state commission of highways, for the improvement of county highway No. 705 in the county of Chenango. The claimants began the construction of the road promptly. Later, a steel bridge on said highway was found to be defective and in such condition that probably it was insufficient to carry the traffic after the improvement of the highway. The state’s division engineer directed the resident engineer to arrange with the town of Sherburne for the construction of a concrete bridge, to replace the steel bridge, and abutments, the town to build the top, or “ slab,” and the state the remainder, that is, the abutments, pier and wing walls. This arrangement was made. The resident engineer, pursuant to instructions from the divi[400]*400sion engineer, prepared the plans and specifications for the work, and the claimants were directed by the resident engineer to perform the work pursuant thereto, which they did. The bridge is of two spans and is fifty-six feet long and twenty-two feet wide, and the abutments are twenty-two feet long, eleven feet high, and an average of four and one-half feet thick. The pier in the center of the bridge is twenty-four feet long, eleven feet high and about four and one-half feet thick. The four walls are twelve and one-half feet long and an average of ten feet high and four feet thick. A supplemental agreement in writing, which included among other matters the items of the state’s alleged share of the work, was prepared and executed by the claimants, by the division engineer, the county superintendent of highways, and the chairman of the county board of supervisors, but it never was executed by the state commissioner of highways. On the contrary, he refused to execute it, because these items of work were included. On April 9,1914, he executed a supplemental agreement for all the items of work and materials included in the previous agreement submitted to him, except the items relating to the bridge. The claimants fully performed the contract for the construction of the highway, final estimate for the work was approved, and all sums due the claimants paid, but payment for the items of work involved in the construction of the bridge was refused. These items total the sum of $1,802.57.

The state contests the claim on two grounds. '

First. That the items for which claim is made were not included within the original contract of June 11, 1912, and were not provided for by any supplemental agreement in writing, executed by the commission, and therefore constitute no claim against the state.

Second. That the said items were unauthorized by [401]*401law, because the bridge was of a span exceeding five feet.

This inquiry involves no doubt concerning the good faith of the claimants. It is not denied that the work was done properly, and that the amounts claimed are reasonable, and that the claimants have not been paid. Naturally, the facts tend to create some sympathy for the claimants, in their predicament, but the court has no other recourse than to determine the rights of the parties, in consonance with the law applicable thereto.

The Highway Law reads, “All contingencies arising during the prosecution of the work shall be provided for to the satisfaction of the commission and as may be agreed upon in the original or by a supplemental contract executed by the commission. "Laws of 1909, chap. 30, § 130, subd. 9. There is a suggestion in the brief of the claimants ’ counsel that this work was done under the original contract, because the latter contained provisions for the alteration of the plans and specifications, and for changes in quantities and because this work was of the same character as that covered by one of the unit prices in the original contract. There is no merit to this contention. These provisions in the original contract refer to work fairly within the purview of the latter, although, perhaps, differing in detail, measurements or quantity from that originally contemplated. The original contract, plans and specifications contained no provision for the construction of any bridge. No bridge was then contemplated by the parties. The claimants’ proof shows, and their brief says, that this work was done pursuant to the arrangement made subsequently to the execution of the contract, to which we have referred, and for which plans and specifications were made long afterward.

. -The provisions of the contract, which are quoted bi-[402]*402the claimants, are contained in the “ information for bidders,” proposal and specifications. The entire contract is not before us. Exhibit No. 3 has been referred to as the contract, but it is incomplete, consisting only of the information for bidders, proposal and specifications, but it does not include the contract itself. We are unable to determine whether there are any other provisions, modifying or defining those quoted by the claimants. Many of the forms of state highway contracts in use contemporaneously with the one at issue contain an express provision, as follows: “It is further agreed that any increase of quantities, or extra work performed, or materials furnished, shall be covered by a supplemental contract, as provided in chapter 30, Laws of 1909, and amendments thereto.” We are not informed whether this contract contained any such provision. If it did, it would merely confirm the result at which we arrive. In the absence of proof, we have not assumed that it contained this clause.

It is patent, therefore, that the work for which claim is made was not provided for in the original contract. The statute requires that it shall have been provided for by a supplemental contract, executed by the commission, if recovery is to be had. The claimants are not able to produce such a supplemental contract, as authority for the performance of the work, and as a basis for their claim. Not only did the commission omit to execute a supplemental contract for this work, but the commissioner expressly refused to do so, and signed the supplemental contract tenderéd for his signature, only after the excision of these items therefrom,

The claimants rely on the last clause of subdivision 9 of section 130 of the Highway Law, which reads as follows : “ Such supplemental contract shall not be binding unless it be approved by the commission in case of a state highway and in case of a county highway, by [403]*403the chairman of the board of supervisors and the district or county superintendent. ” They construe this to mean, substantially, that supplemental contracts, when necessary, require, in the case of a county highway, execution and approval by the chairman of the board of supervisors, and the district or county superintendent only. This is not the meaning of the statute. The 1st paragraph of section 130 of the Highway Law indicates the scope of all the subdivisions of the section. They apply to both state and county highways, and the excerpt from subdivision 9 of section 130, which we quoted first, supra, applies to both state and county highways. There is no distinction between them, in the requirement that all the work must be provided for in the original or by a supplemental contract executed by the commission, The last sentence of the subdivision, upon which the claimants rely, imposes an additional requirement, to wit: that a supplemental contract in the case of a county hightvay must also be approved by the chairman of the board of supervisors and the district or county superintendent.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
103 Misc. 398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/paddleford-v-state-nyclaimsct-1918.