Packing v. Dore & Associates Contracting, Inc.

48 F. App'x 392
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 17, 2002
DocketNo. 01-2740
StatusPublished

This text of 48 F. App'x 392 (Packing v. Dore & Associates Contracting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Packing v. Dore & Associates Contracting, Inc., 48 F. App'x 392 (3d Cir. 2002).

Opinion

OPINION OF THE COURT

STAPLETON, Circuit Judge.

I.

This action arises out of a complex set of commercial relationships among appellant Dore & Associates Contracting, Inc. (“Dore”), appellee Oregon Steel Mills, Inc. (“Oregon Steel”), non-party Integra Metals Technology, Inc. (“Integra”), and appellee Diversified Packing & Development Corporation (“Diversified”).

In early 1996, Andrew Denuzzio and Alex Simkovich incorporated Integra with the goal of locating a steel mill in Washington, Pennsylvania. At the same time, Oregon Steel wanted to sell certain equipment from its mill site in Fontana, California, because it lease was about to expire and it planned to shut down the mill. In order to accommodate these complementary needs, on April 3, 1996, Integra and Oregon Steel entered into a Capital Contribution Agreement (“CCA”). Under the CCA, Integra was to receive the Fontana mill assets, and Oregon Steel was to receive 13% of Integra’s stock and a cash payment of $1,000,000. The transfer of title was to take place upon the equipment’s delivery to Integra in Pennsylvania. In order to secure certain rights of Oregon Steel as a shareholder of Integra, Integra and Oregon Steel also entered into a Shareholder Agreement on the same day they entered into the CCA.

Integra was responsible for dismantling and transporting Oregon Steel’s mill assets to Pennsylvania at its own expense. The CCA expressly states that Integra will contract with a third party to transport the assets. The relevant paragraph states in part:

3.4 Fontana Dismantling Contract. [Integra], as a licensee from [Oregon Steel], shall contract (the “Fontana Dismantling Contract”) with a third party (the “Fontana Dismantler”) to, on behalf of [Oregon Steel], dismantle, package, load onto a common carrier and deliver to [Integra] in Pennsylvania (or to an alternate location as designated by [Integra]) the Fontana Mill Assets.... [Oregon Steel] agrees to deliver possession of the Fontana Mill Assets to Dismantler in California for Delivery to [Integra] in Pennsylvania.

App. at 75 (¶ 3.4).

After signing the CCA and Share Purchase Agreement, Integra solicited bids for the dismantling work. Dore and Diversified each submitted proposals to Integra. Integra selected Dore. Pursuant to the Dismantling Contract, dated May 3, 1996, Integra agreed to pay Dore $1,037,500 plus a percentage of the proceeds from the sale of the scrap to serve as the general contractor for the job. The first page of the Dismantling Contract states, ‘Whereas Integra is the licensee and agent of Oregon Steel Millfe, Inc. pursuant to that certain Capital Contribution Agreement dated April 4, 1996 between Integra and Oregon Steel Mills, Inc.... ” App. at 120.

Dore kept the demolition and scrapping work for itself and subcontracted with Diversified for the dismantling portion, which [395]*395requires the precise disassembly of component parts for future reuse. On May 5, 1996, Dore and Diversified signed an agreement by which Dore agreed to pay Diversified $715,000 for its part of the job — 10% in the form of a mobilization fee.

Diversified in turn subcontracted with Sydel Corp., t/a Jopac, Inc. (“Jopac”), to provide certain necessary labor in the form of millwrights and riggers to disconnect and dismantle the designated steel mill equipment and to remove it with cranes or other special equipment. Diversified agreed to pay Jopac $580,000 for this labor, 10% of which was paid up front as a mobilization fee.

Integra contracted directly with Diversified for transportation of the dismantled equipment. Integra agreed to pay $730,000 for Diversified’s services. This agreement was signed on June 21, 1996.

On May 3, 1996, the day the Integra-Dore Dismantling Contract was executed, a pre-construction conference was held at the Fontana site. Representatives of Integra, Dore, and Oregon Steel were all present. Dore claims that it was unaware, until arriving at the Fontana site, that Integra had to obtain additional financing for the project. Therefore, in a series of letters between Dore and Integra, which were not copied to Oregon Steel, Dore repeatedly sought assurances of payment from Integra. This issue was settled in a May 29, 1996, letter agreement which permitted the imposition of hens upon Oregon Steel’s equipment to secure payment for Dore’s work. Dore did not communicate with Oregon Steel about this letter agreement.

Work began at the Fontana site on May 13, 1996. Dore and Diversified shut down work at the site on two occasions. First, on May 28, 1996, Dore and Diversified shut down work as a result of concerns about financial assurances. This shutdown was resolved by the May 29, 1996, letter agreement discussed above. The second and final shutdown occurred on July 3, 1996, as a result of nonpayment by Integra, which was unable to obtain construction financing.

Diversified filed a complaint in the Western District of Pennsylvania against Dore, Oregon Steel, Integra and Denuzzio and Simkovieh seeking damages in the amount of $121,500 for breach of the Dismantling Subcontract. Diversified also filed suit in the Western District of Pennsylvania against Oregon Steel and Integra seeking damages of $146,000 for breach of the Transportation Contract. These two cases were consolidated. The individual defendants, Denuzzio and Simkovieh, were dismissed prior to trial; Integra was dropped as a defendant at trial. Dore subsequently asserted a cross-claim against Oregon Steel for breach of the agreement to pay for the dismantling of the equipment.

The District Court held a jury trial beginning on April 2, 2001, on all claims. The Court finished its charge and reviewed the verdict slip with the jury at around 9:30 on the morning of Tuesday, April 10. Thereafter, the jury submitted three questions for the Court: a) “If we deem Integra as being the agent of Oregon Steel, does Oregon automatically have to pay on the contract?” b) “They can be an agent, but under what terms?” and c) ‘What is the definition of licensee?” App. at 1036. The court informed the jury, “you must decide these issues based on the instructions of the Court. I’ve already covered all aspects of these questions in the instructions of the Court.” App. at 1038.

The jury asked another question even later that day: “can we have the Judge recharge the jury? Some of the definitions and terms need [to be] reexplained to [396]*396us.” App. at 1038-39. The court decided not to recharge the jury explaining “the jury has failed to itemize any specific concepts, and until it does that, I’m not going to recharge the jury ab initio.” Id.

At 2:00 P.M., the jury returned with two further questions: a) “Do we have to award the amounts based on breach of contract laws of profit, cost, or can we pick any figure we choose for settlement?” and b) “When was the lawsuit filed? We need this to determine the amount of interest owed, if any.” App. at 1040. The court directed the jury to decide the case on the facts in the record and the law as explained by the judge.

The next day, on April 11, 2001, the jury presented the court with its last request: “We are at a standstill in deliberations. The only way to clarify and resolve any further is to have the law explained again by the Judge. Can we please have the law re-explained?” App. at 1044. In response to this, the court indicated to the jury that it was going to re-explain the law of agency and the contentions of the parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
48 F. App'x 392, Counsel Stack Legal Research, https://law.counselstack.com/opinion/packing-v-dore-associates-contracting-inc-ca3-2002.