Packard Square LLC v. Canyon Partners LLC

CourtDistrict Court, E.D. Michigan
DecidedJanuary 23, 2020
Docket2:19-cv-10374
StatusUnknown

This text of Packard Square LLC v. Canyon Partners LLC (Packard Square LLC v. Canyon Partners LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Packard Square LLC v. Canyon Partners LLC, (E.D. Mich. 2020).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION PACKARD SQUARE LLC, Plaintiff, Civil Action No. 19-CV-10374 vs. HON. BERNARD A. FRIEDMAN CANYON PARTNERS LLC, et al., Defendants. _____________________________/ OPINION AND ORDER GRANTING DEFENDANTS’ MOTION TO DISMISS PLAINTIFF’S RICO CLAIMS AND DECLINING TO EXERCISE SUPPLEMENTAL JURISDICTION OVER THE REMAINING CLAIMS This matter is presently before the motion of defendants Canyon Partners LLC and Can IV Packard Square LLC (collectively, “Canyon”) to dismiss the second amended complaint (“SAC”) [docket entry 22], and on the individual defendants’ motion to dismiss and joinder in Canyon’s motion to dismiss [docket entry 30]. Plaintiff has responded, and defendants have replied, to both motions. Pursuant to E.D. Mich. LR 7.1(f)(2), the Court shall decide these motions without a hearing. For the reasons stated below, the Court shall grant defendants’ motions as to plaintiff’s federal claims and decline to exercise supplemental jurisdiction over the remaining claims. This case is one of several that has arisen from a construction project. In 2014, plaintiff Packard Square LLC (“Packard Square”) borrowed money from defendants Canyon Partners LLC and Can IV Packard Square LLC (collectively, “Canyon”) to build an apartment building and retail space in Ann Arbor, Michigan. The project did not proceed in a timely and businesslike fashion, and in 2017 Packard Square filed for Chapter 11 bankruptcy protection. In an opinion issued in October 2017, the Bankruptcy Court summarized the tortured history of the project, and the parties’ growing antagonism toward one another, as follows: Pre-petition, in October 2014, the Debtor obtained a construction loan from Canyon in the maximum principal amount of $53,783,184.00 (the “Construction Loan”) to finance the construction of “a 360,000 square foot mixed-use development [project] on a six and a half acre site on Packard Street in Ann Arbor, Michigan,” including “249 residential units with high-end amenities, nearly 30,000 square feet of retail space and over 450 parking space[s] including an underground parking garage” (the “Project”). The Debtor signed a promissory note, and other loan documents, and granted Canyon a mortgage on the real property of the Project “together with the related easements, privileges and licenses, and the buildings, structures, improvements, fixtures and personal property located [on it]” to secure the Debtor's indebtedness for the Construction Loan. The Debtor also executed an assignment of leases and rents in favor of Canyon. B. The appointment of a receiver in the state court suit On October 21, 2016, Canyon filed suit against the Debtor in Washtenaw County Circuit Court, in the case of CAN IV Packard Square LLC v. Packard Square, LLC, et al., Case No. 16–000990 CB (the “state court case”). In its verified complaint in the state court case, Canyon requested the appointment of a receiver over the property securing its debt, due to the Debtor's alleged failure “to fulfill its obligations to complete construction of improvements for which funds were provided in accordance with the relevant loan agreements” and “to maintain the [p]roperty i[n] a suitable condition.” Canyon also sought foreclosure of its mortgage in the state court complaint. On October 27, 2016, the state court held a hearing in which it heard oral argument regarding the appointment of a receiver. Counsel for Canyon and counsel for the Debtor both appeared at the hearing and argued their respective positions at length, for and against the appointment of a receiver. During the hearing, Canyon alleged, in relevant part, that there had been multiple material defaults by the Debtor, in the form of missing critical construction milestone dates under the terms of the Construction Loan and the mortgage, despite Canyon having granted some extensions of those dates. Canyon alleged that, among other defaults, the Debtor had defaulted by missing the “substantial completion date which was October 25[, 2016],” and that the Debtor had defaulted on its obligation to enclose the building of the Project by July 1, 2016, which was “a critically important aspect of the [construction] schedule” to avoid damage to 2 the building, from the inclement weather that had already occurred and that would be getting worse due to the approaching winter season. Canyon alleged that although it had worked with the Debtor and extended the original contractually-agreed date of July 1, 2016 to August 26, 2017, the Debtor had also defaulted on its promise to enclose the building by the extended date. According to Canyon, that default still had not been cured, and the building was “still open and exposed to the elements” at the time of the hearing. Canyon also alleged that Gaylor Electric Inc. d/b/a Gaylor, Inc. (“Gaylor”) and Jermor Plumbing & Heating, Inc. (“Jermor”), two subcontractors who had worked on the Project but had not been paid, had recorded construction liens against the property subject to its mortgage, and that more liens would soon be filed based on the Debtor's firing of Quandel Construction Group, Inc. (“Quandel”), the former general contractor for the Project. Canyon informed the Court that due to the Debtor's defaults, it had accelerated the promissory note and so the promissory note was due and owing in full. Canyon argued that “under either the [parties'] contract or the Construction Lien Act, the [c]ourt was authorized to appoint a receiver under the current existing circumstances” because the Project was only partially completed; the Debtor had defaulted on its obligations under its contract with Canyon; and the building was not enclosed and at risk of being damaged. The Debtor argued that although there had been “technical defaults” due to missed construction milestone dates, the Debtor was entitled to an extension of the construction milestone dates of “up to 150 days” due to the force majeure clause in the parties' loan agreement. Debtor also argued that the “fundamental equities” of the case favored denying Canyon's request for the appointment of a receiver. At the conclusion of the hearing, the state court gave a bench opinion in which it rejected the Debtor's arguments and ruled that it would “appoint McKinley, Incorporated [“McKinley”] as receiver for the [P]roject and that that [would] be done immediately.” On November 1, 2016, the state court entered an order appointing McKinley as the receiver (the “Receivership Order”). * * * During the more than 10–month period after the state court appointed the Receiver and before the Debtor filed this bankruptcy case, there was considerable activity on the Project by the Receiver and its chosen general contractor on the project, O'Brien Construction 3 Company, Inc. And there was a great deal of litigation in the state court case, between the Debtor and some of the construction lien holders on the one hand, and the Receiver and Canyon on the other hand. The state court case has been contentious. For example, almost immediately after appointment of the Receiver, the Debtor appealed the Receivership appointment and sought a stay pending appeal. The Debtor also sought an order requiring the Receiver to use the Debtor's preferred general contractor at the time, C.E. Gleeson Constructors, Inc., in place of the Receiver's chosen contractor O'Brien. [Footnote: Quandel Construction Group, Inc. had been the Debtor's general contractor on the Project, but disputes between the Debtor and Quandel led the Debtor to terminate Quandel, effective October 17, 2016.] The state court heard these motions on November 17, 2016, and denied them. The Debtor then filed a motion for reconsideration of the Receivership order on December 8, 2016, which the state court denied on December 19, 2016.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kremer v. Chemical Construction Corp.
456 U.S. 461 (Supreme Court, 1982)
Taylor v. Sturgell
553 U.S. 880 (Supreme Court, 2008)
In re Packard Square LLC
575 B.R. 768 (E.D. Michigan, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Packard Square LLC v. Canyon Partners LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/packard-square-llc-v-canyon-partners-llc-mied-2020.