Packard Englewood Motors, Inc. v. Packard Motor Car Co.

116 F. Supp. 629, 1953 U.S. Dist. LEXIS 2276
CourtDistrict Court, D. New Jersey
DecidedNovember 24, 1953
DocketCiv. A. No. 511-51
StatusPublished

This text of 116 F. Supp. 629 (Packard Englewood Motors, Inc. v. Packard Motor Car Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Packard Englewood Motors, Inc. v. Packard Motor Car Co., 116 F. Supp. 629, 1953 U.S. Dist. LEXIS 2276 (D.N.J. 1953).

Opinion

MODARELLI, District Judge.

This is an action by plaintiff, a Packard automobile dealer corporation, which [631]*631operates under a year-to-year franchise agreement with the defendant-manufacturer, Packard Motor Car Company. The action is not based on the franchise contract, but is to recover alleged loss of profits resulting from defendant’s alleged breach of contract to deliver in the year 1948 ninety-seven so-called bonus cars to plaintiff. The case was tried without a jury.

By mimeographed letter dated December 18, 1947, from defendant’s Detroit, Michigan office, addressed to all Packard Dealers in the New York zone, defendant offered a special inducement to its dealers by which they could obtain bonus cars in addition to their normal allotments from defendant. The offer was '“for each ton of scrap gray iron furnished us by a Dealer, one additional Packard car will be alloted to” the dealer. The offer-letter recited that because of the shortage of cast iron scrap, many cars were “not being produced that could otherwise be shipped to dealers.” Also set forth in the letter were certain general instructions relating to the type of .scrap needed, shipping and payment. A follow-up letter setting forth detailed .shipping instructions for transporting the scrap was mailed under date of December SO, 1947, by defendant’s New York zone office to the dealers.

Plaintiff accepted the offer by shipping fifty-three tons of scrap on June 26,1948, and forty-four tons on July 27, 1948, which shipments were received and approved by defendant in Detroit. Thus, the parties entered into a contractual relationship and the plaintiff became entitled to ninety-seven bonus cars from defendant.

The issue is clear: When or during what period of time was defendant obligated to deliver to plaintiff the bonus cars ? The offer did not specify any date or period of delivery; nor did any writing pertaining thereto pass between the parties. Plaintiff argues that defendant was obligated to deliver all of the cars in the year 1948; defendant argues that it did not obligate itself to deliver at any specified time. In fact, actual deliveries were during the months of October, November, December, 1948, and January, 1949, totaling thirty-four bonus cars. Thus, plaintiff seeks damages for alleged loss of profits resulting from defendant’s failure to deliver to plaintiff sixty-three bonus cars in the year 1948.

Jurisdiction in this case is based solely on the diversity of citizenship of the parties. New Jersey substantive law applies. Erie Railroad Co. v. Tompkins, 1988, 804 U.S. 64, 58 S.Ct. 817, 82 L.Ed. 1188, including its conflict of laws rules, Klaxon Co. v. Stentor Electric Mfg. Co., 1941, 313 U.S. 487, 61 S.Ct. 1020, 85, L. Ed. 1477.

Defendant contends that it made no promise to deliver all of the bonus cars during any specified period of time. Such an argument, in effect, is that there is no contract between the parties' — an agreement to deliver at will is an illusory contract in that the apparent promisor has not promised that he ever will perform. Thus, at the outset, it is necessary to decide whether there is a contract.

While counsel have not considered the problem of conflict of laws, the facts in this case present such a question in that the parties negotiated and acted in New Jersey, Michigan, and New York. And although, as will be discussed, New Jersey’s substantive and conflict of laws rules clearly govern this case, proper analysis requires this court to set forth its reasoning.

What law would a New Jersey State Court choose as the governing law on the question of whether or not a contract exists ? Counsel have cited no cases to aid the court and none directly in point have been found. The general rule as to whether or not the acts of the parties constitute a binding legal obligation is that the law of the place of the making of the contract governs. Specialties Development Corp. v. C-O-Two Fire Equipment Co., 3 Cir., 207 F.2d 753; Avery v. Sielcken-Schwarz, 1949, 5 N.J.Super. 195, 68 A.2d 635; James H. Rhodes & Co. v. Chausovsky, S.Ct.1948, 137 N.J.L. 459, [632]*63260 A.2d 623; Polyckronos v. Polyckronos, 1939, 8 A.2d 265, 17 N.J.Misc. 250; Hinkly v. Freick, E. & A.1914, 86 N.J.L. 281, 90 A. 1108, L.R.A.1916B, 1041; Goodrich on Conflict of Laws (3d Ed. 1949), Section 110.

In the case at bar, the contract was made in New Jersey. By the terms of the offer, plaintiff had to furnish scrap gray iron for which defendant offered to pay “the current Detroit market price” and “transportation f. o. b. the Dealer point to Detroit.” The contract was made the moment the plaintiff’s collection of scrap left its control pursuant to instructions from defendant’s zone office. At that moment, plaintiff had performed and thereby accepted the unilateral offer of defendant. It is settled law that a contract comes into existence when and where the last act is done to make it a binding obligation upon the parties thereto. Northampton Mutual Live Stock Ins. Co. v. Tuttle, 1878, 40 N.J.L. 476. Even if it be argued that the contract was made in Michigan in that the defendant’s offer contained certain specifications pertaining to the type of scrap needed, so that there could be no performance-acceptance by. plaintiff until and unless defendant inspected and approved the scrap sent by plaintiff, nevertheless, the Michigan law is the same as New Jersey law as to when there must be performance when the contract is silent; the law in both states is that performance must be within a reasonable time. Wemple v. B. F. Goodrich Co., E. & A. 1941, 126 N.J.L. 465, 19 A.2d 692; Bollenbacher v. Reid, 1908, 155 Mich. 277, 118 N.W. 933.

The rule requiring performance within a reasonable time does not prohibit this court from obtaining assistance, in deciding what is a reasonable time, from the subsequent, practical interpretation of the contract by the parties thereto. This is not a case where one party has aided his cause by making an interpretation in his own favor. “The practical construction given to a contract by one of the parties may be used in support of the construction now urged in court by the other party.” Corbin on Contracts, 1951, Vol. 3, Section 558, p. 141; Mantell v. International Plastic Harmonica Corp., E. & A.1947, 141 N.J. Eq. 379, 55 A.2d 250, 173 A.L.R. 1185.

In order to understand the conduct of the parties, it is necessary to describe the customary procedure by which the-plaintiff-dealer obtained cars from the defendant-manufacturer. Plaintiff would receive an allotment notice from defendant’s zone office in New York to the effect that either regular or bonus cars had been allotted to plaintiff and that it should place orders therefor; whereupon plaintiff would place orders for the shipment of cars. Although Traendly, plaintiff’s president, testified that the defendant would send cars without orders, he admitted that ordinarily defendant would await orders from plaintiff before sending any cars.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Albert v. Ford Motor Co.
172 A. 379 (Supreme Court of New Jersey, 1934)
James H. Rhodes & Co. v. Chausovsky
60 A.2d 623 (Supreme Court of New Jersey, 1948)
Lippincott v. Content
8 A.2d 362 (Supreme Court of New Jersey, 1939)
Mantell v. International Plastic Harmonica Corp.
55 A.2d 250 (Supreme Court of New Jersey, 1947)
I. Tannenbaum Son & Co. v. Taglareni
179 A. 633 (Supreme Court of New Jersey, 1935)
Thomsen v. Riedel
176 A. 701 (Supreme Court of New Jersey, 1935)
Basic Iron Ore Co. v. Dahlke
137 A. 423 (Supreme Court of New Jersey, 1927)
Wemple v. B. F. Goodrich Co.
19 A.2d 692 (Supreme Court of New Jersey, 1941)
Corn Exchange National Bank & Trust Co., Philadelphia v. Taubel
175 A. 55 (Supreme Court of New Jersey, 1934)
Avery v. Sielcken-Schwarz
68 A.2d 635 (New Jersey Superior Court App Division, 1949)
Polyckronos v. Polyckronos
8 A.2d 265 (New Jersey Court of Chancery, 1939)
Bollenbacher v. Reid
118 N.W. 933 (Michigan Supreme Court, 1908)
Northampton Mutual Live Stock Insurance v. Tuttle
40 N.J.L. 476 (Supreme Court of New Jersey, 1878)
Hinkly v. Freick
90 A. 1108 (Supreme Court of New Jersey, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
116 F. Supp. 629, 1953 U.S. Dist. LEXIS 2276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/packard-englewood-motors-inc-v-packard-motor-car-co-njd-1953.