Pacificorp v. Public Utility Dist. No. 2 of Grant

780 F. Supp. 2d 1133, 2011 U.S. Dist. LEXIS 8220, 2011 WL 310172
CourtDistrict Court, D. Oregon
DecidedJanuary 25, 2011
DocketCivil Case 09-1012-KI
StatusPublished

This text of 780 F. Supp. 2d 1133 (Pacificorp v. Public Utility Dist. No. 2 of Grant) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacificorp v. Public Utility Dist. No. 2 of Grant, 780 F. Supp. 2d 1133, 2011 U.S. Dist. LEXIS 8220, 2011 WL 310172 (D. Or. 2011).

Opinion

OPINION AND ORDER

KING, Judge:

This is a declaratory judgment and breach of contract action, removed from Multnomah County Circuit Court, in which plaintiff PacifiCorp seeks to terminate a contract with defendant Public Utility District No. 2 of Grant County, Washington (“Grant”). The parties have filed cross motions for partial summary judgment.

Factual Background

In 1961, PacifiCorp and Bonneville Power Administration (“BPA”) entered into a power transmission agreement (“the Vantage Agreement”). Section 4 of the Vantage Agreement contained a rate provision permitting BPA to make changes every three years. Over the lifetime of the Vantage Agreement, BPA periodically changed the rate under Section 4 until the Vantage Agreement expired on October 31, 2009.

In 1982, PacifiCorp and Grant entered into an Agreement for Sale of Power (“the Power Purchase Agreement” or “PPA”), under which PacifiCorp agreed to purchase a 14-megawatt output from Grant.

Section 4 of the PPA contains the following provision:

Term

This Agreement shall be effective for a term commencing September 1, 1983, and shall terminate on the later of (a) September 1, 1988, or (b) the first September 1 two years following written notice of intent to terminate given by Grant; PROVIDED, HOWEVER, that Grant shall not terminate this Agreement in order to sell the electric power and energy made available hereunder other than to its own retail customers. The parties agree that this provision is not intended to prohibit Grant from maintaining a reasonable resource reserve margin nor to prohibit Grant from terminating this Agreement rather than acquiring any other resource or power supply other than power and energy available to Grant from the Priest Rapids Project. Upon termination of this Agreement, any obligations then accrued or incurred shall be preserved until satisfied.

PPA, Compl., Exhibit 1 ¶ 4. The PPA is governed by Washington law. Id. at ¶ 11. Under the PPA, pricing for the power sold to PacifiCorp by Grant was to be the larger of two rates: (a) the difference obtained by applying BPA’s NR-1 New Resource Firm Power Rate or its successor rate and subtracting from the result the amount obtained by multiplying 14,000 kilowatts by the charge provided for in Section 4 of the Vantage Agreement, or (b) 35.0 mills per kilowatt hour. Amended Compl. ¶ 17; PPA ¶ 8.

When the Vantage Agreement expired, Casey Sprouse, a senior marketing manager at Grant, sent an email dated December 7, 2009 to Laurie Barbeau, a PacifiCorp billing manager, as follows:

Hey Laurie, the spread sheet you sent mentions the expiration of your transmission agreement with BPA [the Vantage Agreement]. What do you suggest we do for November? Do you have a new transmission contract with BPA that would apply to our agreement?

Campbell Deck, Ex. 11. In response, Bar-beau proposed using the BPA point to point (“PTP”) transmission rate, subject to the “existing billing and contract dispute” between Grant and PacifiCorp:

Effective 11/1/09, the transmission contract with BPA [the Vantage Agreement] used in the billing of the 14 MW contract between our companies has been replaced with the firm BPA PTP service. Notwithstanding the existing billing and contract dispute, the credit *1137 should now be based on the current BPA firm PTP rate (currently at $1.298/kW mo). This credit for November would be calculated as 14,000 kW times $1.298/kW mo. or $18,172.

Id. PacifiCorp and Grant have used the PTP rate since the Vantage Agreement expired. Barbeau does not have authority to amend, extend or enter into contracts. Sprouse at that time had authority to enter into contracts on behalf of Grant for the purchase and sale of energy, so long as the contracts were of no more than one year’s duration, 130,000 megawatts, or $3.5 million.

The wholesale market price for power has now fallen below the price provided for in the PPA. On April 9, 2009, PacifiCorp met with Grant to discuss PacifiCorp’s right to terminate the PPA. During that meeting, Grant denied that PacifiCorp had the right to terminate the PPA. The parties continued the discussions until PacifiCorp filed this action on July 28, 2009.

The Amended Complaint asserts four claims: two for declaratory judgment and two for breach of contract. As its First Claim, PacifiCorp seeks the following declarations from the court: 1) the PPA is an agreement for an indefinite term and not in perpetuity; 2) PacifiCorp has the right to terminate the PPA on reasonable notice; 3) the filing of the complaint and the passage of a reasonable period thereafter as determined by the court constitutes such reasonable notice of termination. The Second Claim is a for breach of contract, asserting that Grant breached the express terms of the PPA or the implied covenant of good faith and fair dealing by refusing to recognize PacifiCorp’s right to terminate the PPA. The Third Claim seeks a declaration that the PPA expired on its own terms October 31, 2009, because the Vantage Agreement expired on that date, and thereby eliminated an essential price term of the PPA. 1

PacifiCorp moves for partial summary judgment on three issues: 1) Grant is subject to personal jurisdiction in this court; 2 2) the PPA terminated on October 31, 2009, as a matter of law, because the PPA required the Vantage Agreement to provide an essential term of the PPA, i.e., price, so that when the Vantage Agreement expired, the PPA terminated for lack of an essential term; and 3) even if the PPA did not terminate with the Vantage Agreement, PacifiCorp is entitled to terminate the PPA by giving reasonable notice to Grant, which it gave when it filed this action.

Grant moves for partial summary judgment in its favor on 1) PacifiCorp’s Second Claim, because Grant has not breached either an express or implied term of the PPA; 3 and 2) PacifiCorp’s declaratory re *1138 lief claims (First and Third Claims) if the court dismisses the Second Claim, based either on its discretion to do so or on the merits.

STANDARDS

The PPA is governed by Washington law. Under Washington law, interpretation of a contract consists of ascertaining the meaning of a promise or agreement. Berg v. Hudesman, 115 Wash.2d 657, 663, 801 P.2d 222 (1990) (en banc), citing Restatement (Second) of Contracts § 200 (1981). On the other hand, construction of a contract is a “process by which legal consequences are made to follow from the terms of the contract and its more or less immediate context, and from a legal policy or policies that are applicable to the situation.” Id. (Internal quotation and citation omitted).

Washington courts apply the “context rule” rather than the “plain meaning rule” in interpreting contracts. Id., 115 Wash.2d at 667, 801 P.2d at 228-29.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brillhart v. Excess Insurance Co. of America
316 U.S. 491 (Supreme Court, 1942)
United States v. Foster Transfer Co.
183 F.2d 494 (Ninth Circuit, 1950)
Principal Life Ins. Co. v. Robinson
394 F.3d 665 (Ninth Circuit, 2005)
Eurick v. Pemco Insurance Co.
738 P.2d 251 (Washington Supreme Court, 1987)
Stender v. Twin City Foods, Inc.
510 P.2d 221 (Washington Supreme Court, 1973)
Hall v. Custom Craft Fixtures, Inc.
937 P.2d 1143 (Court of Appeals of Washington, 1997)
Oak Bay Properties, Ltd. v. Silverdale Sportsman's Center, Inc.
648 P.2d 465 (Court of Appeals of Washington, 1982)
US Life Credit Life Ins. v. Williams
919 P.2d 594 (Washington Supreme Court, 1996)
Berg v. Hudesman
801 P.2d 222 (Washington Supreme Court, 1990)
Badgett v. Security State Bank
807 P.2d 356 (Washington Supreme Court, 1991)
Bryant v. Country Life Insurance
414 F. Supp. 2d 981 (W.D. Washington, 2006)
McGuire v. Bates
234 P.3d 205 (Washington Supreme Court, 2010)
Hearst Communications v. Seattle Times Co.
115 P.3d 262 (Washington Supreme Court, 2005)
Kirk v. Mt. Airy Ins. Co.
951 P.2d 1124 (Washington Supreme Court, 1998)
Cascade Auto Glass v. PROGRESSIVE CAS. INS.
145 P.3d 1253 (Court of Appeals of Washington, 2006)
Hay v. Chehalis Mill Co.
19 P.2d 397 (Washington Supreme Court, 1933)
U.S. Life Credit Life Insurance v. Williams
129 Wash. 2d 565 (Washington Supreme Court, 1996)
Kirk v. Mount Airy Insurance
134 Wash. 2d 558 (Washington Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
780 F. Supp. 2d 1133, 2011 U.S. Dist. LEXIS 8220, 2011 WL 310172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacificorp-v-public-utility-dist-no-2-of-grant-ord-2011.